AI summaryThree Rivers District Council Full Council approved revenue virements, supplementary estimates and capital variances for the 2025/26 budget at Period 3, with a small favourable forecast variation.
Written from the decision and the officer reportPDF Pro
OutcomeApprovedVirements, supplementary estimates and capital variances approved
Money£15.105m forecast revenue, £14.829m capitalFavourable revenue variation of £0.003m against latest budget
What happens nextUpdates to three-year medium-term financial planReflected at Period 6 monitoring in September 2025
Who it affectsCouncil budgets and reservesGeneral Fund forecast to remain above £2.0m minimum
What was decided
Revenue budget virements in appendices 1 to 3 were approved and added to the three-year medium-term financial plan. Report 2.1
Revenue budget supplementary estimates in appendices 1 to 3 were approved and added to the plan. Report 2.2
Revenue variances to be managed in appendices 1 to 3 were noted, and capital variances in appendices 1 to 2 were approved and added to the plan. Report 2.3, 2.4
Why
The report sets out the council's financial position at 30 June 2025, with a forecast favourable revenue variation of £0.003m against the latest budget of £15.108m. Report P7, P11, P14
Officers recommended approval so that budgets reflect agreed service activity, grant income and reserve use, and so the medium-term financial plan is updated. Report P43, 5.1
Significant items include changes in shared services with Watford Borough Council, a secondment of a part-time Housing Enforcement Assistant, higher planning subscription costs and increased rental income from Herts Constabulary. Report P20
What happens next
Committee budgets will be updated for the 2025/26 pay award of 3.2% at Period 6 monitoring in September 2025. Report P60
A detailed report on the social housing decarbonisation grant was circulated to all members after the meeting.
The money
£14.677m Original 2025/26 net revenue budget approved on 25 February 2025 Report P7, P9
Chosen: Approve revenue budget virements in appendices 1 to 3. Aligns budgets to service activity, management responsibilities, grant income and planned reserve use. Report 2.1, P43
Chosen: Approve revenue budget supplementary estimates in appendices 1 to 3. Used where a budget pressure is certain and cannot be managed within the service area; funded by General Balances. Report 2.2, P43
Chosen: Note revenue variances to be managed in appendices 1 to 3. Variances of £0.010m at Period 3 are managed within existing budgets. Report 2.3, P44
Chosen: Approve capital variances in appendices 1 to 2. Includes a £60,000 virement from Basing House Whole Life Costing to Temporary Accommodation for works at 38 Lincoln Drive. Report 2.4, P29, P30
Implications
Financial: Forecast revenue variations of (£3,306), (£3,936) and (£2,912) across 2025/26, 2026/27 and 2027/28 respectively, with no capital variation. Report P98, P99
Financial: Property Investment Board portfolio of £14.378m is forecast to deliver £0.871m of rent at a 5.72% average yield, above the 5% target. Report P51, P52
Risk: Key risks include inflation (CPI 3.6% and RPI 4.4% in June 2025), 2025/26 pay award of 3.2% agreed on 23rd July 2025, business rates and council tax collection, recycling disposal costs linked to global demand, and interest rate movements. Report P59, P60, P64, P66, P69
Staffing: Six vacant posts at end of June 2025, equal to 1.66% of 362 council posts, including one in each service committee and four in Policy and Resources. Report P90, P91, P92
Legal: The report states there are no legal implications directly arising from it. Report 7.1
Equalities: A relevance test was completed and concluded that no full Equality Impact Assessment was required. Report P104
Who and where
All council service committees, with material variances in General Public Services and Community Engagement, Climate Change and Leisure, and Policy and Resources Report P15, P16, P17, P18, P19
Watford Borough Council through changes in shared services agreements Report P20
Hertsmere Borough Council as the council's parking enforcement provider, with 31 penalty charge notices recommended for write-off Report P70, P71, P72
Herts Constabulary as a tenant generating increased rental income following a rent review Report P20
Residents of 38 Lincoln Drive, South Oxhey, where capital works are planned Report P29, P30
Council tenants and businesses paying council tax and business rates Report P61, P63, P64
Timeline
25 February 2025: Council approved the original 2025/26 revenue budget of £14.677m and capital budget of £5.522m Report P7, P22
30 June 2025: End of Period 3 monitoring; revenue outturn forecast at £15.105m and capital outturn at £14.829m Report P14, P27
23rd July 2025: 2025/26 pay award of 3.2% agreed for all employees Report P60
September 2025: Pay award to be reflected in committee budgets at Period 6 monitoring Report P60
21 October 2025: Full Council meeting approves the Period 3 budget monitoring recommendations Report P1
Plain English for the jargon
Virement: A transfer of budget from one service area to another, which must net to zero across the council's budget.
Supplementary estimate: Additional budget approved where a spending pressure is certain and cannot be managed within the existing service budget; funded from General Balances.
MTFP: Medium Term Financial Plan, the council's three-year financial planning document.
NNDR: National Non Domestic Rates, also known as business rates.
PWLB: Public Works Loans Board, the government body from which councils can borrow.
DMO: Debt Management Office, through which councils can deposit cash with HM Treasury.
CVA: Company Voluntary Arrangement, a formal insolvency process allowing a company to pay creditors reduced amounts.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item82c
Resolved
· That the revenue budget virements as set out in appendices 1 to 3 be approved and incorporated into the three-year medium-term financial plan. · That the revenue budget supplementary estimates as set out in appendices 1 to 3 be approved and incorporated into the three-year medium term financial plan. · That the revenue variances to be managed as set out in appendices 1 to 3 be noted. · That the capital variances as set out in appendices 1 to 2 be approved and incorporated into the three-year medium-term financial plan. Post Meeting Note: A detailed report on the social housing decarbonization grant was circulated to all members.
Word for word from the decision Three Rivers published for this meeting.Source: moderngov.threerivers.gov.uk
2.1That the revenue budget virements as set out in appendices 1 to 3 be approved and incorporated into the three-year medium-term financial plan.
2.2That the revenue budget supplementary estimates as set out in appendices 1 to 3 be approved and incorporated into the three-year medium-term financial plan.
2.3That the revenue variances to be managed as set out in appendices 1 to 3 be noted.
2.4That the capital variances as set out in appendices 1 to 3 be approved and incorporated into the three-year medium-term financial plan.
2.5Revenue Summary
The original 2025/26 budget as approved by Council on 25 February 2025 was £14.677m. The latest budget which totals £15.108m includes the variances previously reported to Policy & Resources Committee in March 2025 (Period 10 Budget Monitoring) and approved by urgent decision in July 2025 (2024/25 year end report). The forecast year end position for 2025/26 at Period 3 is estimated to be £15.105m giving a favourable variance of (£0.003m). The table below shows how the forecast year end position has been constructed:
Revenue Budget 2025/26 £000
Original Net Revenue Budget 14,677
Carry Forward from 2024/25 (Year end report approved by urgent 431 decision July 2025)
2 Original Budget Plus Carry Forwards from 2024/25 15,108
Supplementary Estimates to budget reported at Period 3 (to be (13) approved)
Variances to budget reported at Period 3 (to be noted) 10
Forecast Total Net Expenditure 2025/26 15,105
3 The main variances are shown in the table below: 2025/26 Revenue Account - General Fund Summary (C) (A) (B) (B-A) (B-C) Original Budget Net Supplimentary Variation Committee Original Plus Latest Previous Latest Spend to Estimates and to Latest Budget 2024/25 Budget Forecast Forecast Date Variances Budget Carry Forwards £000 £000 £000 £000 £000 £000 £000 £000
General Public Services & 6,030 6,106 6,106 6,106 (1,236) 6,131 25 25 Community Engagement
Corporate Costs (Interest Earned/Paid) 2,258 2,258 2,258 2,258 1,207 2,258 0 0 and Parish Precepts Net General 14,677 15,109 15,109 15,109 4,604 15,105 (3) (3) Fund
The significant supplementary estimates and variances above include changes in the shared services agreements with Watford Borough Council, a request from Salary Contingency to facilitate the employment of a part-time Housing Enforcement Assistant on a 2 year fixed term secondment, increase in planning subscription costs and an increase in rental income from Herts Constabulary due to a rent review and using additional space.
2.6Capital Summary
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Budget monitoring report to 30 june 2026That: · The revenue budget virements as set out in Appendices 1 to 3 and noted in paragraph 4.1.4 be approved and inc...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.