AI summaryThree Rivers District Council approved revenue budget changes, including £0.272m in added revenue budget, plus £0.277m in capital budgets, and noted £0.128m of revenue variances to manage [D]. The approved changes are incorporated in the three year medium term financial plan [D].

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedRevenue and capital changes enter three year plan [D]
Money£0.272m, £0.128m and £0.277m [D]Revenue additions, variances and capital budgets [D]
What happens nextThree year plan updated [D]Approved revenue and capital changes are incorporated [D]
Who it affectsCouncil budgets and reserves [6.1][P50]Service budgets and General Fund forecasts change [6.1][P50]

What was decided

The Council approved the revenue budget virements and £0.272m of supplementary estimates, and incorporated both into the three year medium term financial plan [D].

The Council noted £0.128m of revenue variances to be managed [D].

The Council approved capital budgets of £0.277m and incorporated them into the three year medium term financial plan [D].

Why

Budget virements align budgets with service activity and management, reflect grant income and planned reserve use, and must net to zero across the Council budget [P50]. Report P50

Supplementary estimates cover certain budget pressures that cannot be managed within a service area and are funded by an increase in the contribution from General Balances [P50]. The forecast revenue year end position is £16.376m against £15.976m, an unfavourable variance of £0.400m [P48]. Report P50, P48

The forecast capital year end position is £22.406m against a latest budget of £22.129m, producing the £0.277m variation approved by the Council [P61][D]. Report P61

What happens next

Amend the Council's budgets for 2026/27 and the medium term financial plan to include the approved changes [6.1]. Report 6.1

Manage the £0.128m of revenue variances [2.3][P51]. Report 2.3, P51

Update the General Fund reserves forecast to reflect the additional £0.272m contribution from General Balances [P50]. Report P50

The money

  • £0.272m Revenue budget supplementary estimates approved
  • £0.128m Revenue variances to be managed noted
  • £0.277m Capital budgets approved
  • £0.654m Net increase in expenditure budgets from virements, offset by lower expenditure or higher income Report P50
  • £15.976m Latest approved services budget, excluding corporate budgets Report P48
  • £16.376m Forecast revenue year end position Report P48
  • £22.129m Latest capital budget Report P61
  • £22.406m Forecast capital year end position Report P61

Options considered

  • Chosen: Approve revenue budget virements. They align budgets with service activity and management, reflect grant income and planned use of reserves, and net to zero [P50]. Report 2.1, P50
  • Chosen: Approve revenue budget supplementary estimates. They cover certain budget pressures that cannot be managed within the relevant service area [P50]. Report 2.2, P50
  • Chosen: Note revenue variances to be managed. Variances to be managed at Period 3 total £0.128m [P51]. Report 2.3, P51
  • Chosen: Approve a revised capital programme budget. The forecast is £22.406m against £22.129m, giving a £0.277m variation [P61]. Report 2.4, P61

Implications

  • Financial: The decisions amend the 2026/27 budgets and the medium term financial plan [6.1]. Report 6.1
  • Financial: The General Fund balance is forecast to remain above the £2.000m prudent minimum over the medium term [P55]. Unrestricted reserves are forecast at £3.763m as at 31 March 2029 [P57]. Report P55, P57
  • Financial: Period 3 capital spend was £2.735m, equal to 12.36% of the latest budget [P62]. Report P62
  • Risk: The 2026/27 pay award is not agreed, and the contingency may not cover it and other inflation, so some costs may fall against reserves [P66]. Report P66
  • Risk: Energy costs are expected to continue pressuring budgets, with services expected to absorb increased costs [P79]. Report P79
  • Legal: There are no legal implications directly arising from this report [8.1]. Report 8.1
  • Equalities: No full equality impact assessment was required [P108]. Report P108
  • Staffing: There were 16 vacancies at the end of June 2026, equal to 4.41% of 362 posts, and agency staff may cover some posts [P95][P96]. Report P95, P96

Who and where

  • Council service budgets Report P48
  • General Fund Reserve Report P50, P55
  • General Public Services and Community Engagement Committee Report P49
  • Climate Change and Leisure Committee Report P49
  • Policy and Resources Committee Report P49
  • Temporary accommodation provision Report P23
  • Waste Services Depot and Grounds Maintenance Vehicles Report P33, P34
  • Aquadrome Bridge Report P35

Timeline

  • 24 February 2026: The original 2026/27 revenue and capital budgets were approved. Report P8, P23
  • March 2026: Earlier budget variances were reported to the Policy and Resources Committee. Report P8, P23
  • 1 April 2026: Reserve balances were brought forward. Report P40
  • 30 June 2026: The Period 3 monitoring position was recorded. Report P8, P90
  • 14 July 2026: Earlier revenue variances were approved. Report P8, P23
  • 31 March: Closing General Fund balances were forecast across the medium term. Report P54
  • 31 March 2029: Unrestricted reserves were forecast at £3.763m. Report P57

Plain English for the jargon

  • Budget virement: A budget adjustment that must net to zero across the Council budget [P50].
  • Supplementary estimate: An approved budget addition for a certain pressure that a service area cannot manage [P50].
  • Variance to be managed: A reported budget difference identified for management [P49][P51].
  • Period 3: The third budget monitoring period, ending 30 June 2026 [P8][P90].
  • General Fund Reserve: The reserve whose forecast is compared with a prudent minimum balance [P55].
  • Unrestricted reserves: The General Fund and Economic Impact Reserve position used for risk assessment [P57].
  • MTFP: The Council's three year financial plan covering 2026/27 to 2028/29 [P54][P118].
  • Rephasing: Moving £14.831m of capital spending from 2025/26 into the 2026/27 forecast [P23][P27].
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item162b

Resolved

That: · The revenue budget virements as set out in Appendices 1 to 3 and noted in paragraph 4.1.4 be approved and incorporated into the three-year medium-term financial plan. · The revenue budget supplementary estimates of £0.272m as set out in appendices 1 to 3 and noted in paragraph 4.1.5 be approved and incorporated into the three-year medium-term financial plan. · The revenue variances to be managed of £0.128m as set out in appendices 1 to 3 and noted in paragraph 4.1.6 be noted. · The capital budgets of £0.277m as set out in appendices 1 to 3 and noted in paragraph 4.4.2 be approved and incorporated into the three-year medium-term financial plan
Word for word from the decision Three Rivers published for this meeting. Source: moderngov.threerivers.gov.uk

Follow this further

Built from Three Rivers's papers

What the report saysPro

Report to Full Council

Recommendation

That:

2.1The revenue budget virements as set out in Appendices 1 to 3 and noted in paragraph 4.1.4 be approved and incorporated into the three-year medium-term financial plan.

2.2The revenue budget supplementary estimates of £0.272m as set out in appendices 1 to 3 and noted in paragraph 4.1.5 be approved and incorporated into the three-year medium-term financial plan.

2.3The revenue variances to be managed of £0.128m as set out in appendices 1 to 3 and noted in paragraph 4.1.6 be noted.

2.4The capital budgets of £0.277m as set out in appendices 1 to 3 and noted in paragraph 4.4.2 be approved and incorporated into the three-year medium-term financial plan.

Report prepared by Sally Riley, Financial Business Partner

3.1Revenue Summary

3.1.1 The Original 2026/27 budget as approved by Council on 24 February 2026 was £15.243m. The latest budget which totals £15.976m includes the variances previously reported to Policy & Resources Committee in March 2026 (Period 10 Budget Monitoring) and approved at Full Council 14 July 2026 (2025/26 year end report). The forecast year end position for 2026/27 at Period 3 is estimated to be £16.376m giving an unfavourable variance of £0.400m.

1 3.1.2 The table below shows how the forecast year end position has been constructed:

Revenue Budget 2026/27 £000

Original Net Revenue Budget 15.243

Supplementary Estimates to budget reported at Period 10 2025/26 153 (March 2026)

Carry Forward from 2025/26 (Year end report July 2026) 580

Original Budget Plus Carry Forwards from 2025/26 15,976

Supplementary Estimates to budget reported at Period 3 (to be 272 approved)

Variances to budget reported at Period 3 (to be noted) 128

Forecast Total Net Expenditure 2026/27 16,376

3.1.3 The main variances are shown in the table below: 2026/27 Revenue Account - General Fund Summary (C) (A) (B) (B-A) (B-C) Original Budget Net Supplimentary Variation Committee Original Plus Latest Previous Latest Spend to Estimates and to Latest Budget 2025/26 Budget Forecast Forecast Date Variances Budget Carry Forwards £000 £000 £000 £000 £000 £000 £000 £000

General Public Services & 6,429 6,543 6,543 6,543 (267) 6,721 178 178 Community Engagement

Climate Change & 1,884 1,983 1,983 1,983 35 1,988 5 5 Leisure

Policy & 4,827 5,193 5,193 5,193 8,179 5,410 217 217 Resources Total Service 13,140 13,719 13,719 13,719 7,947 14,119 400 400 Budgets

Corporate Costs (Interest Earned/Paid) 2,257 2,257 2,257 2,257 1,413 2,257 0 0 and Parish Precepts Net General 15,397 15,977 15,977 15,977 9,360 16,376 400 400 Fund

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
BUDGET MONITORING REPORT TO 30 JUNE 2026Report 565 KB DownloadRead as text
PDF
Enc. 1 for Budget Monitoring Report to 30 June 2026Report 189 KB Download
PDF
Enc. 2 for Budget Monitoring Report to 30 June 2026Report 128 KB Download
PDF
Enc. 3 for Budget Monitoring Report to 30 June 2026Report 162 KB Download
PDF
Enc. 4 for Budget Monitoring Report to 30 June 2026Report 251 KB Download

At this meeting

Whole meeting

Who was there

0 of 41 attended
CA
Councillor Christopher AlleyCommittee Member, expected
AB
Councillor Aidan BentleyCommittee Member, expected
IC
Councillor Ian CampbellCommittee Member, expected
AC
Councillor Anaika ChopraCommittee Member, expected
OC
Councillor Oliver CooperCommittee Member, expected
SC
Councillor Stephen CoxCommittee Member, expected
HD
Councillor Harry DaviesCommittee Member, expected
SD
Councillor Steve DruryCommittee Member, expected
VE
Councillor Vicky EdwardsCommittee Member, expected
AF
Councillor Andrea FraserCommittee Member, expected
EG
Councillor Elinor GazzardCommittee Member, expected
SG
Councillor Stephen Giles-Medhurst OBECommittee Member, expected

All 41 on the meeting page

On this subject at Three Rivers

Search all
  1. BUDGET MONITORING REPORT TO 30 JUNE 2026This decision
  2. Budget Monitoring Report to 30 June 2026Noted
  3. Budget Monitoring Report to 31 January 2026Noted
  4. Budget Monitoring Report to 30 September 2025Noted
  5. Budget Monitoring Report to 30 June 2025Approved
  6. Budget Monitoring Report to 30 September 2024Approved

More from Three Rivers Full Council

All decisions
MeetingDecisionOutcome
20 Oct 2026 Building safety levyThat: · Hertfordshire Building Control limited be authorised to undertake the role of centralised collecting agent fo... Agreed Open
20 Oct 2026 Aquadrome project - match funding requestThat: · £165,000 of capital funds be allocated to be used as match funding towards the Aquadrome Project as detailed ... Decided Open
14 Jul 2026 Appointment to CommitteesThat the appointments to committees and named substitutes be approved as amended. Approved Open
14 Jul 2026 Minor Amendments to Chorleywood Neighbourhood PlanThat Council agrees the minor amendments and adopts the update Chorleywood Neighbourhood Plan in Appendix 2. Agreed Open
14 Jul 2026 Community Governance Review Mill End, Maple Cross, West HydeThat the current Community Governance Review commenced following the decision of the Policy and Resources Committee o... Decided Open