AI summaryPolicy and Resources Committee agreed the revised Strategic Risk Register, adding two new risks on local government reorganisation and the Green Belt, and delegated minor changes to the Associate Director.
Written from the decision and the officer reportPDF Pro
OutcomeAgreedIncluding two additional strategic risks identified
MoneyNoneWithin agreed policy and budgets, no specific cost
What happens nextRisk register updated with new risksMinor changes delegated to the Associate Director
Who it affectsCouncil strategic risk managementAligned to Corporate Framework 2023-2026 priorities
What was decided
The committee agreed the revised Strategic Risk Register, including the additional strategic risks identified, and delegated authority to the Associate Director of Corporate, Customer and Community to authorise minor changes such as terminology, clarification, or administrative corrections with no significant impact. Report 2.1, 2.2
Why
The Policy and Resources Committee is responsible for monitoring the treatment of strategic risks, and a strategic risk is one that would seriously prejudice the achievement of the Corporate Framework objectives. Report 3.2, 4.1
Two additional risks were proposed: the introduction of unitary local government by April 2028, and the risk of failing to protect the Green Belt following a recommendation from the Risk Management Strategy agreed at Full Council on 08 July 2025. Report 3.4, P12, P13, 3.1
What happens next
A risk owner and controls have been identified for the two new risks in the updated register, which is included as Appendix A. Report P14, P23
The Associate Director of Corporate, Customer and Community may make minor changes to the register, such as terminology, clarification, or administrative corrections with no significant impact. Report 2.2
Options considered
Chosen: Agree the revised Strategic Risk Register including new risks. The committee is responsible for monitoring strategic risks and the register aligns to the Corporate Framework 2023-2026. Report 3.2, 3.3, 4.1
Implications
Governance: The Risk Management Strategy was approved by Full Council on 08 July 2025 and sets the framework for which risks are treated as strategic. Report 3.1, 5.1
Risk: Two new strategic risks added: Local Government Reorganisation (unitary government by April 2028) and Failing to protect the Green Belt. Report 3.4, P12, P13
Other: No specific financial, legal, equal opportunities, staffing, environmental, community safety, public health, customer services, communications, or health and safety implications were identified. Report 6.1
Who and where
Policy and Resources Committee, as the body that determines which council risks are strategic and monitors their treatment Report 3.2, 4.1
Associate Director of Corporate, Customer and Community, given delegated authority for minor changes to the register Report 2.2
Timeline
08 July 2025: Risk Management Strategy approved by Full Council Report 3.1, 5.1
2025-12-01: Policy and Resources Committee meeting where the decision was taken
April 2028: Target date for the introduction of unitary local government, identified as a new strategic risk Report P12
Plain English for the jargon
Strategic risk: A risk that would seriously prejudice the achievement of the objectives of the Corporate Framework.
Corporate Framework 2023-2026: The council's plan setting out its four priorities: responsive local leadership, a great place to do business, sustainable communities, and net carbon zero and climate resilience.
Local Government Reorganisation: The introduction of unitary local government by April 2028, identified as a new strategic risk.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
ItemPR524
Resolved
That: Policy and Resources Committee agree the revised Strategic Risk Register (Appendix A), including the additional strategic risks identified. The Committee agrees to give delegated Authority to Associate Director of Corporate, Customer and Community to authorise minor changes to the register, such as terminology, clarification, or administrative corrections with no significant impact.
Word for word from the decision Three Rivers published for this meeting.Source: moderngov.threerivers.gov.uk
1.1This report gives details of progress against the Risk Treatment Plans for the Strategic Risks relating to the priorities identified in the Corporate Framework 2023-2026. It also provides recommendations for new strategic risks that have been identified.
Recommendation
That:
2.1Policy and Resources Committee agree the revised Strategic Risk Register (Appendix A), including the additional strategic risks identified.
2.2The Committee agrees to give delegated Authority to Associate Director of Corporate, Customer and Community to authorise minor changes to the register, such as terminology, clarification, or administrative corrections with no significant impact.
Report prepared by: Phil King, Data Protection and Resilience Manager
3 Details
3.1The Council’s Risk Management Strategy was approved by Full Council on 08 July 2025.
3.2In accordance with the Strategy, the Policy and Resources Committee determines which of the Council’s risks are ‘strategic’ and receives progress reports on their treatment. A strategic risk is defined as one that would seriously prejudice the achievement of the objectives of the Corporate Framework.
3.3The risks on the Strategic Risk Register are aligned to the Objectives of the Corporate Framework 2023-2026:
Provide responsive and responsible local leadership. Expand our position as a great place to do business. Support and enable sustainable communities. Achieve net carbon zero and be climate resilient.
3.4Two additional risks are proposed to be added to the Strategic Risk Register.
3.4.1 “Local Government Reorganisation”, introduction of unitary local government by April 2028.
3.4.2 “Failing to protect the Green Belt”, following a recommendation from the Risk Management Strategy being agreed at Full Council in 08 July 2025.
3.4.3 A risk owner and controls have been identified for both in the updated register. (Appendix A).
2 4 Options and Reasons for Recommendations
4.1The Policy and Resources Committee is responsible for monitoring the treatment of strategic risks.
5 Policy/Budget Reference and Implications
5.1The recommendations in this report are within the Council’s agreed policy and budgets. The relevant policy is entitled Risk Management Strategy and was agreed on 08 July 2025.
6 Financial, Legal, Equal Opportunities, Staffing, Environmental, Community Safety, Public Health, Customer Services Centre, Communications & Website, Risk Management and Health & Safety Implications
6.1None specific.
Data Quality Data sources: Strategic Risk Register Data checked by: Phil King Data rating: Tick
1 Poor 2 Sufficient 3 High
Background papers
APPENDICES / ATTACHMENTS Appendix A – Strategic Risk Register
3 4
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Budget Monitoring Report to 30 June 2026· That the revenue budget virements as set out in Appendices 1 to 3 and noted in paragraph 4. 1. 4 be approved and in...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.