Three Rivers District Council
Audit Committee, Tuesday 24 March 2026 at 7.30pm

SIAS Progress report against Audit Plan 2025/26

Noted Finance 1 paper

AI summaryThree Rivers Audit Committee noted 91% delivery of the 2025/26 SIAS audit plan to 6 March 2026, approved that no plan changes be made since November 2025, and agreed removal of implemented recommendations.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedNo plan changes since November 2025; some recommendations removed
MoneyNot stated
What happens nextAnnual report to followPerformance against annual targets reported in 2025/26 Head of Assurance Annual Report
Who it affectsCouncil officers and servicesOfficers responsible for implementing outstanding audit recommendations

What was decided

Members noted the Internal Audit Progress Report for the period to 6 March 2026, covering five final audit reports and 91% plan delivery. Report P1, 2.1, P15, P16

Members approved the Internal Audit Plan changes, which on this occasion were that no changes had been made since the November 2025 report. Report P1, 2.6

Members agreed removal of implemented audit recommendations set out in Appendix C and noted the implementation status of all other recommendations in Appendix D. Report P1, 2.4, P20

Why

The 2025/26 Annual Audit Plan was approved by Audit Committee on 25 March 2025 and the Committee receives periodic progress updates; this is the third update. Report 1.3, 1.4

Internal audit work is reported to a Member Body so the Council can review and monitor corporate governance and gain assurance on its statutory obligations. Report 1.2

Performance indicators showed 91% of planned days delivered, 100% client satisfaction, and no Critical or High priority recommendations made in 2025/26. Report P27, P28, P29

What happens next

Officers will continue to implement outstanding recommendations; 3 from 2024/25 and 4 from 2025/26 remain open, with several revised deadlines in 2026. Report 2.4, P20, P85, P93, P97, P108

The Committee noted the briefing paper in Appendix 6 on the Audit Committee's duties and expectations under Domain III of the Global Internal Audit Standards. Report P8, P36

Performance against annual targets will be reported in the 2025/26 Head of Assurance's Annual Report at the first Audit Committee meeting of the civic year. Report 2.9, P31, P32, P33

Options considered

  • Chosen: Approve the Internal Audit Plan changes (no changes proposed). There have been no changes to the Audit Plan since the previous progress report issued in November 2025. Report 2.6
  • Chosen: Agree removal of implemented audit recommendations set out in Appendix C. Implemented recommendations are removed from the tracking list once verified. Report P1, 2.4

Implications

  • Risk: Officers report no risks to the delivery of the agreed audit plan or ability to provide an annual assurance opinion. Report 2.10
  • Other: No extension to implementation dates has been requested by action owners since the November 2025 Audit Committee. Report 2.5

Who and where

  • Three Rivers District Council officers responsible for implementing outstanding recommendations across Revenues, Waste and Environment, Property Services, and Council Tax services Report P20, P62, P82, P95, P110

Timeline

  • 25 March 2025: 2025/26 Annual Audit Plan approved by Audit Committee Report 1.3
  • November 2025: Previous SIAS progress report issued to Audit Committee Report 2.2, 2.5
  • 16/02/2026: Rent Deposit Guarantee Scheme final audit report issued (Reasonable assurance) Report P15
  • 26/02/2026: Geographic Information System and Risk Management final audit reports issued (Reasonable assurance) Report P16
  • 05/03/2026: Property Resilience final audit report issued (Reasonable assurance) Report P16
  • 6 March 2026: Date at which SIAS progress and performance are measured Report 2.1, 2.4, 2.8
  • 07/03/2026: Payroll 2025/26 final audit report issued (Reasonable assurance) Report P16
  • 17 March 2026: Public Health Funerals draft policy due at General Public Services Committee Report P85, P90
  • 29 June 2026: Public Health Funerals policy and procedure notes due at Policy and Resources Committee Report P85, P93

Plain English for the jargon

  • SIAS: Shared Internal Audit Service, the provider of internal audit to the Council and partner authorities.
  • GIAS: Global Internal Audit Standards, arranged into five Domains covering the practice of internal audit.
  • Domain III: The section of the Global Internal Audit Standards setting out essential requirements for the Board (Audit Committee) on authority, independence and oversight of internal audit.
  • CAE: Chief Audit Executive, the senior officer leading the internal audit function.
  • TRAMPS: The Council's property management system used to record lease events such as rent reviews and renewals.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
ItemAC48/26

Resolved

Members are recommended to: Note the Internal Audit Progress Report for the period to 6 March 2026 Approve the Internal Audit Plan changes Agree removal of implemented audit recommendations set out in Appendix C Note the implementation status of all other internal audit recommendations in Appendix D.
Word for word from the decision Three Rivers published for this meeting. Source: moderngov.threerivers.gov.uk

Follow this further

Built from Three Rivers's papers

What the report saysPro

Report to Audit Committee

Recommendations

Members are recommended to:  Note the Internal Audit Progress Report for the period to 6 March 2026  Approve the Internal Audit Plan changes  Agree removal of implemented audit recommendations set out in Appendix C  Note the implementation status of all other internal audit recommendations in Appendix D.

1 Contents

1 Introduction and Background 1.1 Purpose of Report 1.2 Background

2 Audit Plan Update 2.1 Delivery of Audit Plan and Key Findings 2.3 All Priority Audit Recommendations 2.6 Proposed Audit Plan Amendments 2.7 Audit Plan Delivery Progress

Appendices 1 Progress against the 2025/26 Audit Plan 2 2025/26 Audit Plan Projected Start Dates 3-4 Progress against Outstanding Internal Audit Recommendations 5 Assurance and Priority Levels 6 Briefing Paper Global Internal Audit Standards

2 1. Introduction and Background Purpose of Report

1.1This report details:

a) Progress made by the Shared Internal Audit Service (SIAS) in delivering the Council’s annual audit plan for 2025/26 as at 6 March 2026. b) Proposed amendments to the approved 2025/26 Annual Audit Plan. c) Implementation status of all previously agreed audit recommendations from 2024/25 onwards. d) An update on performance management information as at 6 March 2026. e) The GIAS briefing paper in Appendix 6 as to the Global Internal Audit Standards – Domain III.

Background

1.2The work of internal audit is required to be reported to a Member Body so that the Council has an opportunity to review and monitor an essential component of corporate governance and gain assurance that its internal audit provision is fulfilling its statutory obligations. It is considered good practice that progress reports also include proposed amendments to the agreed annual audit plan.

1.3The 2025/26 Annual Audit Plan was approved by Audit Committee on 25 March 2025.

1.4The Audit Committee receives periodic updates on progress against the Annual Audit Plan from SIAS. This is the third report giving an update on the delivery of the 2025/26 Internal Audit Plan.

2. Audit Plan Update Delivery of Audit Plan and Key Audit Findings

2.1At 6 March 2026, 91% of the 2025/26 Audit Plan days had been delivered. Appendix 1 provides a status update on each individual deliverable within the audit plan.

2.2There have been five final audit reports issued since the previous progress report issued in November 2025:

Audit Title of Issue Assurance Number and Priority Level of Recommendations Rent Deposit 16/02/2026 Reasonable 1 Medium and 2 Low Guarantee Scheme

3 Audit Title of Issue Assurance Number and Priority Level of Recommendations Geographic 26/02/2026 Reasonable 2 Low, 1 Advisory Information System Risk Management 26/02/2026 Reasonable 2 Low, 1 Advisory Property Resilience 05/03/2026 Reasonable 2 Medium, 2 Low Payroll 2025/26 07/03/2026 Reasonable 1 Medium, 1 Low

All Priority Audit Recommendations

2.3Audit Committee Members will be aware that a Final Audit Report is issued when agreed by Management. This includes an agreement to implement the recommendations made. It is SIAS’s responsibility to bring to Members’ attention the implementation status of recommendations; it is the responsibility of officers to implement the recommendations by the agreed date.

2.4The table below summarises progress in implementation of all outstanding internal audit recommendations as at 6 March 2026, with full details given in appendices 3 to 4

Year Number of Total Not Overdue No Percent Medium and Number of yet & a revised update age High Outstanding due implementation receive implem Recommendatio Recommend date provided d ented ns made ations % 2023/24 39 0 0 0 0 100% 2024/25 35 3 3 0 0 91% 2025/26 4 4 4 0 0 0%

2.5Since the November 2025 Audit Committee no extension to implementation dates have been requested by action owners.

Proposed 2025/26 Audit Plan Amendments

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
SIAS Progress report against Audit Plan 2025/26Report 680 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 13 attended
MH
Michelle HowellCouncil Staff, in attendance
TH
Councillor Tony HumphreysChair, present
KM
Councillor Keith MartinVice-Chair, present
HD
Councillor Harry DaviesCommittee Member, apologies
LH
Councillor Lisa HudsonCommittee Member, apologies
SK
Councillor Stephen KingCommittee Member, present
DM
Councillor David MajorCommittee Member, present
CR
Councillor Ciaran ReedCommittee Member, present
MS
Councillor Mike SimsCommittee Member, present
CS
Councillor Cheryl StungoCommittee Member, apologies, sent representative
CM
Councillor Chris MitchellCommittee Member, present as substitute
AH
Anita HibbsOfficer, in attendance

All 13 on the meeting page

On this subject at Three Rivers

Search all
  1. SIAS Progress report against Audit Plan 2025/26This decision
  2. TRDC SIAS Progress Report Against the 2025-2026 Audit PlanNoted
  3. TRDC SIAS Progress Report Against the 2024-25 Audit Plan for 26 September 2024Noted
  4. Trdc sias progress report against the 2023/24 audit planNoted
  5. Trdc sias progress against the 2022/23 audit planNoted

More from Three Rivers Audit Committee

All decisions
MeetingDecisionOutcome
25 Jun 2026 Annual Fraud Report 2025/26To note the contents of this report. Noted Open
25 Jun 2026 Audit plan updateMembers are recommended to: Note the position of the 2026/27 Audit Plan delivery Noted Open
28 May 2026 Internal Audit Annual Report 2025/26Recommendation Members are recommended to: Note the Annual Assurance Statement and Note the results of the self-asses... Noted Open
28 May 2026 Statement of Accounts Update 2025/26Recommendation To note the update in relation to the 2025/26 Statement of Accounts timeframes. To review the draft Ac... Noted Open
24 Mar 2026 Statement of Accounts Update 2025/26To note the update in relation to the 2025/26 Statement of Accounts timeframes. To review the draft Accounting Polici... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies