Three Rivers District Council
Full Council, Tuesday 14 July 2026 at 7.30pm

Budget Outturn Report 2025/26

Approved Committee 2 papers

AI summaryThree Rivers District Council approved the 2025/26 budget outturn, noting a £0.461m revenue variance, carrying forward £0.580m of unspent service budgets, and rephasing £14.831m of capital projects into 2026/27.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedRevenue variance, capital position, and project rephasing noted
Money£0.461m revenue variance after carry forwardsPlus £14.831m of capital rephased into 2026/27
What happens next2025/26 accounts to be audited in 2026/27Pay award impact update due in September 2026
Who it affectsCouncil reserves and 2026/27 service budgetsGeneral Fund and Economic Impact Reserve balance affected

What was decided

The Council noted the revenue year end variance after carry forwards of £0.461m. Report P12

The Council noted the capital year end position, with £11.235m spent against a latest budget of £26.258m. Report P13, 3.11, 3.12

The Council approved carry forward of £0.580m of unspent service budgets from 2025/26 to 2026/27, and rephasing of capital projects as set out in Appendix 4. Report P14, P15, 3.3, 3.14

Why

Officers reported a net direct cost of services of £13.850m, a favourable variance of £0.119m against the latest revenue budget. Report 1.2, 3.2

Capital spending was £14.692m below the latest approved budget, mainly because £10.995m of Local Authority Housing Fund (LAHF) property delivery was rephased. Report 3.12, 3.15

Cost pressures from the pay award, utilities and supplier costs were reflected in in-year budget changes, with the latest budget £1.130m lower than the original. Report 1.3

What happens next

The 2025/26 accounts will be audited by Azets LLP during 2026/27; the figures are unaudited and may change. Report 1.8, P89

Officers will report on the estimated financial impact of the 2026/27 pay award in the September 2026 Budget Monitoring report. Report 16.4

A review of key financial and budgetary risks listed in Appendix 6 will continue as a standing item for the Audit Committee. Report 16.2

The money

  • £0.461m Revenue year end variance after carry forwards, to be drawn from reserves Report P12, 3.4
  • £0.580m Unspent service budgets requested for carry forward from 2025/26 to 2026/27 Report P14, 3.3
  • £0.119m Favourable revenue variance before carry forwards, to be returned to the General Fund Report 1.2, 3.2
  • £14.831m Capital programme to be rephased from 2025/26 to 2026/27 Report 3.12, P56
  • £10.995m Rephasing of Local Authority Housing Fund (LAHF) property delivery into 2026/27 Report 3.15
  • £11.235m Actual capital spend at 31 March 2026 Report 3.12
  • £26.258m Revised 2025/26 capital programme budget approved on 24 February 2026 Report 3.11
  • £14.677m Original 2025/26 revenue budget approved on 25 February 2025 Report 3.1
  • £15.109m Revised 2025/26 revenue budget including carry forwards from 2024/25 Report 3.1
  • £13.979m Latest approved 2025/26 revenue budget Report 3.1
  • £0.193m Contribution to the General Fund after carry forwards Report 1.4
  • £0.348m Contribution from the Economic Impact Reserve Report 1.5
  • £5.182m General Fund Reserve balance at 31 March 2026 Report 1.6, 4.1
  • £1.047m Economic Impact Reserve balance at 31 March 2026 Report 1.6, P62
  • £6.229m Total unearmarked reserves at 31st March 2026 Report 1.6, P63
  • £0.057m Benefit from high interest rate levels during the year Report P51
  • £31.035m Planned capital expenditure for 2026/27 to 2028/29 in the medium term financial plan Report 3.16

Options considered

  • Chosen: Approve the four recommendations: note the variances, carry forward £0.580m, and rephase capital projects. Enables Council to monitor budgets and complete projects in 2026/27 as required by the Local Government Act 2003. Report 5.1, 8.1

Implications

  • Financial: Total unearmarked reserves stand at £6.229m at 31 March 2026, with £5.182m in the General Fund and £1.047m in the Economic Impact Reserve. Report 1.6, P63
  • Financial: External audit fees rose because of build back work required following disclaimed audit opinions in prior years. Report P45
  • Legal: The Council has a statutory duty to monitor budgets and take remedial action under Section 28 of the Local Government Act 2003, overseen by the Section 151 officer. Report 8.1
  • Risk: The 2026/27 pay award is the most significant budget risk, with negotiations likely to be protracted and the final position remaining unknown well into the year. Report 16.4
  • Risk: Key financial and budgetary risks are listed in Appendix 7 and reviewed at each Audit Committee meeting. Report 16.2, P91
  • Equalities: No additional Equalities Impact Assessment is required because the report monitors performance against the already approved budget. Report P72
  • Climate: No additional climate change assessment is required because the report monitors performance against the already approved budget. Report P74
  • Staffing: No specific staffing implications arise from the report. Report 9.1

Who and where

  • Three Rivers District Council as a whole, through its General Fund and Economic Impact Reserve balances Report 1.6, P63
  • Services with projects being carried forward into 2026/27, including climate change and sustainability, grounds maintenance, parking enforcement, community development, asset management and the Chief Executive's office Report 3.7, 3.8, 3.9, P29, P32, P40, P47, P48
  • Capital projects including the Local Authority Housing Fund (LAHF) delivery of new housing on garage sites and purchased properties Report 3.15
  • Council taxpayers in Three Rivers, whose services and capital investment plans are funded through the approved budget Report 6.1

Timeline

  • 25 February 2025: Original 2025/26 revenue budget of £14.677m approved by Council Report 3.1
  • 24 February 2026: Revised 2025/26 capital programme of £26.258m approved by Council Report 3.11, P90
  • 9 March 2026: Period 10 (end of January) budget monitoring report presented showing £0.665m unfavourable variance Report 3.1, P90
  • 31 March 2026: Financial year end, with capital spend of £11.235m and General Fund balance of £5.182m Report 1.6, 3.12, 4.1
  • 14 July 2026: Full Council meeting approving the budget outturn, carry forwards and capital rephasing Report P11
  • During 2026/27: 2025/26 accounts to be audited by Azets LLP Report 1.8
  • September 2026: Update on the estimated financial impact of the 2026/27 pay award in the next Budget Monitoring report Report 16.4

Plain English for the jargon

  • LAHF: Local Authority Housing Fund, a government programme funding the delivery of new housing on garage sites and through property purchases.
  • General Fund: The Council's main revenue reserve, which stood at £5.182m at 31 March 2026.
  • Economic Impact Reserve: An unearmarked reserve set aside to manage economic shocks, which stood at £1.047m at 31 March 2026 after a £0.348m drawdown.
  • Carry forward: Unspent budget that is moved from one financial year to the next so that a planned project can be completed.
  • Rephasing: Moving the budget for a capital project from one year to a later year because the work will not finish in time.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item147a

Resolved

That Council approves the following: · That the revenue year end variance after carry forwards of £0.461m be noted. · That the capital year end position as summarised in paragraph 3.12 and Appendix 3 be noted. · To approve to carry forward the unspent service budgets from 2025/26 to 2026/27 which total £0.580m to enable completion of projects as detailed at Appendix 2. · To approve the rephasing of capital projects from 2025/26 to 2026/27 as detailed at Appendix 4.
Word for word from the decision Three Rivers published for this meeting. Source: moderngov.threerivers.gov.uk

Follow this further

Built from Three Rivers's papers

What the report saysPro

Report to Full Council

Summary

1.1This report sets out the financial position for the year ending 31 March 2026 for the Council’s revenue and capital budgets. The following recommendations are included in the report:

 to carry forward to 2026/27 certain unspent revenue budgets and;  to rephase those capital budgets that require completion in 2026/27

1.2The report focuses on the variation between the latest agreed budget and the final expenditure and income for the financial year. An underspend of £0.119m is reported before carry forward requests which will be returned to the Council’s General Fund. The updated Medium Term Financial Plan can be seen at Appendix 3.

1.3However, this underspend should be viewed in the context of budget changes agreed during the year. The latest agreed budget was £1.130m lower than the original budget agreed in January 2025, after allowing for carry forwards from 2024/25. During the year the budget was amended to reflect cost pressures primarily arising from the impact of persistently high inflation. This cost pressure included the agreed pay award and increased supplier costs for utilities. Further detail on the budget changes agreed during the year can be found in the Budget Monitoring Reports to Policy and Resources Committee (see background papers listed below).

1.4The original budget included a planned contribution from the General Fund of £0.391m. After allowing for carry forwards from 2024/25 of £0.432m, the contribution required was £0.823m. After allowing for carry forwards from 2025/26, the underspend against the latest budget allows for a contribution to the General Fund of £0.193m.

1.5In addition to the sum being returned to general reserves, there is a contribution from the Economic Impact Reserve at £0.348m as forecast in the budget monitoring throughout the year.

1.6As a result of the outturn, the General Fund Reserve balance stands at £5.182m at the end of the year with the balance on Economic Impact Reserve being £1.047m at year end. This gives total unearmarked reserves of £6.229m at 31st March 2026.

1.7The above position excludes the year end entries relating to the Collection Fund and Housing Benefit payments with the Housing Benefit Reserve and Collection Fund Reserve being used to manage timing differences between payments to and from government and the transactions recognised within the accounts.

1.8The Year End position presented in this report is unaudited and may be subject to change. The Council’s accounts for 2025/26 will be audited by Azets LLP during 2026/27.

2 2 Recommendation

That Council approves the following:

 That the revenue year end variance after carry forwards of £0.461m be noted.

 That the capital year end position as summarised in paragraph 3.12 and Appendix 3 be noted.

 To approve to carry forward the unspent service budgets from 2025/26 to 2026/27 which total £0.580m to enable completion of projects as detailed at Appendix 2.

 To approve the rephasing of capital projects from 2025/26 to 2026/27 as detailed at Appendix 4.

3 Details

Revenue

3.1The 2025/26 budget as approved by Council on 25 February 2025 was £14.677m. Following carry forwards from 2024/25, the revised budget including carry forwards was £15.109m. The period 10 (end of January) budget monitoring report was presented to this Committee at its meeting on 9 March 2026. The report showed an unfavourable variance of £0.665m when compared to budget, making the latest approved budget for 2025/26 £13.979m with a revised forecast of £14.644m. This report compares the year end position to the latest budget.

3.2The year end position is a net direct cost of services of £13.850m which represents a favourable variance of £0.119m when compared to the latest budget.

3.3Officers are requesting to carry forward £0.580m to enable projects to be completed in 2026/27. Appendix 2 details each carry forward request.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Budget Outturn Report 2025/26Report 380 KB DownloadRead as text
PDF
Enc. 1 for Budget Outturn Report 2025/26Report 516 KB Download

At this meeting

Whole meeting

Who was there

38 of 41 attended
CA
Councillor Christopher AlleyCommittee Member, present
AB
Councillor Aidan BentleyCommittee Member, present
IC
Councillor Ian CampbellCommittee Member, present
AC
Councillor Anaika ChopraCommittee Member, present
OC
Councillor Oliver CooperCommittee Member, present
SC
Councillor Stephen CoxCommittee Member, present
HD
Councillor Harry DaviesCommittee Member, present
SD
Councillor Steve DruryCommittee Member, present
VE
Councillor Vicky EdwardsCommittee Member, present
AF
Councillor Andrea FraserCommittee Member, present
EG
Councillor Elinor GazzardCommittee Member, present
SG
Councillor Stephen Giles-Medhurst OBECommittee Member, present

All 41 on the meeting page

On this subject at Three Rivers

Search all
  1. Budget Outturn Report 2025/26This decision
  2. Budget Outturn 2023/24Noted
  3. Budget Outturn 2023/24Noted

More from Three Rivers Full Council

All decisions
MeetingDecisionOutcome
20 Oct 2026 Building safety levyThat: · Hertfordshire Building Control limited be authorised to undertake the role of centralised collecting agent fo... Agreed Open
20 Oct 2026 Aquadrome project - match funding requestThat: · £165,000 of capital funds be allocated to be used as match funding towards the Aquadrome Project as detailed ... Decided Open
20 Oct 2026 Budget monitoring report to 30 june 2026That: · The revenue budget virements as set out in Appendices 1 to 3 and noted in paragraph 4.1.4 be approved and inc... Noted Open
14 Jul 2026 Appointment to CommitteesThat the appointments to committees and named substitutes be approved as amended. Approved Open
14 Jul 2026 Minor Amendments to Chorleywood Neighbourhood PlanThat Council agrees the minor amendments and adopts the update Chorleywood Neighbourhood Plan in Appendix 2. Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies