That it be noted the Housing Revenue Account (HRA) is estimated to generate a net surplus of £0.617m from operational and financing for the 2014/15 financial year. 2. That the projected movement on the HRA reserves (Para 3.2 Table 3) be noted. 3. That the provisional base estimates for 2015/16 for inclusion in the overall rent setting strategy for the HRA be noted. Reason for Decision - as stated in the report This decision is subject to call-in Councillor Fish left the meeting at 7.14pm during the consideration of the next item.
Word for word from the decision Thurrock published for this meeting.Source: democracy.thurrock.gov.uk
The report sets out the provisional assumptions regarding the 2015/16 base estimates.
1. Recommendation(s)
That Cabinet:
1.1Note that the Housing Revenue Account (HRA) is estimated to generate a net surplus of £0.617m from operational and financing for the 2014/15 financial year.
1.2Note projected movement on the HRA reserves (Para 3.2 Table 3)
1.3Note the provisional base estimates for 2015/16 for inclusion in the overall rent setting strategy for the HRA.
2. Introduction and Background
2.1The report sets out the base estimates for the Housing Revenue Account (HRA) for 2015/16. The key changes are discussed in the report.
2.2The report identifies changes within the base estimates between 2014/15 and 2015/16. Increases to the budget will need to be funded through savings or an increase to current rent levels. This will be addressed in detail in the rent setting report that is due to be presented to Cabinet on 11 February 2015, and that report will detail the final budget requirement and funding options for the next financial year. 2.3 The Housing Revenue Account base estimates have been compiled in accordance with the 30-year business plan. This takes into account the long term strategy for the financial viability of the service.
Background
What are the Base Estimates?
2.4The base estimates represent the cost to the Council of continuing to operate the existing level of service. Any options effecting the level of service will be included within the Housing Rents report to be considered by Cabinet in February 2015.
The major areas of income are:
Rents and Service Charges - Paid by tenants; and
Other Income - Income from residential and commercial leaseholder service charges and other miscellaneous sources.
2.5The major items of expenditure on the HRA are:
Capital Financing - this sum is used to finance the cost of major works as part of the HRA capital programme. This is calculated in accordance with 5 year HRA Capital programme.
Repairs and Maintenance - responsive repairs, planned maintenance and adaptations;
Salaries - the cost of employing staff; and
o Funding of further housing development and regeneration. This includes schemes to build 90 new properties which are on site this financial year
3. Issues, Options and Analysis of Options
3.1Forecast Out-turn 2014/15
3.1.1 Before considering the draft budget position in 2015/16, it is necessary to review the position in 2014/15. This will give an indication of the anticipated level of the HRA balance carried forward into 2015/16. This is detailed in the tables below: Table 1 – Service areas
Revised Forecast Forecast Total Service Area Budget Pressures Underspends Variance £000's £000's £000's £000's Rent and Income (49,046) 630 (391) 239 Financing 24,179 0 (550) (550) Repair and Maintenance 11,600 80 0 80 Supervision and Management 10,431 41 (339) (298) Development & Regeneration 2,603 0 0 0 Transformation 233 0 (88) (88) Grand Total 0 751 (1,368) (617)
Table 2 – Budget Variance
Forecast Forecast Total Budget Variances Pressures Underspend Variance £000s £000s £000s Dwelling rent and water rates 320 (47) 273 Voids loss on Dwellings (240) (240) Voids loss on Garages 303 303 Non dwelling rent income 7 (104) (97) Responsive housing maintenance 80 0 80 Prudential borrowing interest (550) (550) Landlord service management 0 (39) (39) Business management and IT 0 (143) (143) Grounds maintenance 0 (23) (23) Rent Collection 0 (54) (54) Sheltered Housing 0 (80) (80) Housing operations 41 0 41 Transformation savings 0 (88) (88) Total 751 (1,368) (617) Table 3 – New build schemes
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Thurrock Transport Strategy Adoption2.1 Cabinet approved the Thurrock Transport Strategy given in Appendix 1 to be progressed to Full Council for adoptio...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.