Corporate Overview and Scrutiny Committee, Tuesday 3 February 2015 at 7.00pm

Shaping the Council and Budget Progress Update

Noted Scrutiny 1 paper

Corporate Overview and Scrutiny Committee noted this item on Tuesday 3 February 2015. Below is the council's own wording, with the papers it was decided on.

Item25

Resolved

That the Committee note the report, including the recommendations set out below agreed by Cabinet on 14 January 2015. · That the Cabinet note the impact of the Local Government Draft Finance Settlement and the subsequent budget forecasts; · That the Cabinet agree to the funding recommendations as follows: o As explained in the report, the government top slices New Homes Bonus (NHB) funding from the overall pot available for local government finance. The amount taken is always in excess of the amount distributed and is distributed in a later announcement. Considering past allocations, it is recommended to budget for an additional grant of £0.200m: o Further to paragraph 2.5, the remaining £0.800m of brought forward pressures be utilised; o As stated in previous reports, there remains a £0.500m contingency in 2015/16 for demographic pressures. The balance of £0.168m should be met from this sum; and o That officers be instructed to identify those savings required for the remainder of the Medium Term Financial Strategy (MTFS) and implement as many as possible in 2015/16 to increase resilience.
Word for word from the decision Thurrock published for this meeting. Source: democracy.thurrock.gov.uk

Follow this further

Built from Thurrock's papers

What the report saysPro

Report to Corporate Overview and Scrutiny Committee

Executive summary

There have been a number of reports presented to Cabinet since July 2014 on the budget pressures and progress in meeting those pressures covering the financial years 2015/16 through to 2017/18.

The report considered by Cabinet on 17 December 2014 reported a balanced budget for 2015/16 but a budget gap of £9.5m for the period 2016/17 – 2017/18. These forecasts were based on all proposals being accepted, a Council Tax increase and assumptions around government grant being correct.

This report provides an update on those factors, especially in terms of the draft government finance settlement, and revised budget forecasts.

1. Recommendation(s):

That Corporate Overview and Scrutiny Committee note and comment on the report, including the recommendations set out below agreed by Cabinet on 14 January 2015.

1.1That the Cabinet note the impact of the Local Government Draft Finance Settlement and the subsequent budget forecasts;

1.2That the Cabinet agree to the funding recommendations as follows:

1.2.1 As explained in the report, the government top slices New Homes Bonus (NHB) funding from the overall pot available for local government finance. The amount taken is always in excess of the amount distributed and is distributed in a later announcement. Considering past allocations, it is recommended to budget for an additional grant of £0.200m;

1.2.2 Further to paragraph 2.5, the remaining £0.800m of brought forward pressures be utilised;

1.2.3 As stated in previous reports, there remains a £0.500m contingency in 2015/16 for demographic pressures. The balance of £0.168m should be met from this sum; and

1.2.4 That officers be instructed to identify those savings required for the remainder of the Medium Term Financial Strategy (MTFS) and implement as many as possible in 2015/16 to increase resilience.

2 Introduction and Background

2.1Cabinet have considered detailed reports at each of its meetings in this municipal year that have followed on from the Council budget report in February 2014.

2.2Each report has tracked changes from that budget report explaining changes to assumptions, identifying further pressures and offsetting the deficit by a number of savings proposals.

2.3The report to Cabinet in December 2014 recommended an approach that, subject to all proposals being accepted and assumptions around grant funding being correct, would deliver a balanced budget for 2015/16.

2.4However, at that meeting, Cabinet did agree to remove the targeted saving in 2015/16 of £0.2m relating to the Thameside Theatre. The impact was to defer the saving into 2016/17.

2.5This created an additional pressure in 2015/16. Cabinet will recall that to add resilience to this unprecedented savings challenge, pressures from 2017/18 were brought forward to 2015/16 artificially increasing the budget gap for that year. The report in December 2014 used a significant element of this to balance the budget for 2015/16 but left a balance of £1m. A further £0.2m of this will now be used and forecasts are revised as follows:

2015/16 2016/17 2017/18 Total £m £m £m £m As per December Cabinet Report - 8.185 1.343 9.528 Deferment of Thameside proposal 0.200 (0.200) - - Use of brought forward pressures (0.200) 0.200 - - Revised Total - 8.185 1.343 9.528

3 Draft Local Government Finance Settlement 3.1 The draft Local Government Finance Settlement (LGFS) was announced on 18 December 2014.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Shaping the Council and Budget Progress UpdateReport 93 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

3 of 15 attended
YG
Councillor Yash Gupta MBEChair, present
SH
Councillor Shane HebbVice-Chair, present
CK
Councillor Charlie KeyCommittee Member, expected
VM
Councillor Val Morris-CookCommittee Member, expected
RR
Councillor Robert RayCommittee Member, expected
TB
Councillor Terry BrookesCommittee Member, present
RG
Councillor Robert GledhillSubstitute
BJ
Councillor Barry JohnsonSubstitute
GS
Councillor Graham SnellSubstitute
JK
Councillor John KentGuest, in attendance
SC
Steve CoxOfficer, in attendance
ME
Matthew EssexOfficer, in attendance

All 15 on the meeting page

On this subject at Thurrock

Search all
  1. Shaping the Council and Budget Progress UpdateThis decision
  2. Shaping the Council and Budget Proposals (Decision 01104354)Noted
  3. Shaping the Council and Budget Update (Decision 01104338)Noted
  4. Shaping the Council and Budget Update (Decision: 01104428)Noted
  5. Shaping the Council and Budget Update (Decision: 01104416)Noted
  6. Shaping the Council and Budget Progress Update (Decision: 01104408)Noted

More from Thurrock Corporate Overview and Scrutiny Committee

All decisions
MeetingDecisionOutcome
5 Mar 2026 Members’ App Pilot UpdateRESOLVED This item be deferred until the new municipal year due to upcoming elections and the possibility of a high t... Deferred Open
5 Mar 2026 Corporate and Improvement Plan – 2025/26 Q3 Corporate Performance ReportRESOLVED for the reasons set out in this report, the Corporate Overview and Scrutiny: Note and make recommendations t... Decided Open
5 Mar 2026 Local Government Reorganisation & Devolution UpdateRESOLVED The Corporate Overview and Scrutiny Committee note the briefing note on Local Government Reorganisation & De... Noted Open
20 Jan 2026 Q2 Financial Outturn 2025/26 and Draft Revenue Budget 2026/27 & Medium-Term Financial Strategy 2026/27-2028/29It was agreed to take both items at the same time. The reports were presented by the Cabinet Member for Resources who... Agreed Open
9 Oct 2025 Q1 2025/26 Finance ReportCorporate Overview and Scrutiny are to note the following: Note: The Qtr 1 forecast position for the general fund, Ho... Noted Open