That Cabinet note the financial pressures still being faced in Children’s Services; 2. That Cabinet note the need to identify £18.5m through a combination of additional income and cost reduction over the period 2017/18 to 2019/20; and 3. That Cabinet note the assumptions set out in the Medium Term Financial Strategy forecasts as set out in paragraph 4.2. Reason for Decision - as stated in the report This decision is subject to call-in
Word for word from the decision Thurrock published for this meeting.Source: democracy.thurrock.gov.uk
On 24 February 2016, the Council set the budget for 2016/17 and agreed Council Tax increases of 2% for Adult Social Care and 1.99% as a general increase. These increases, in addition to more stretching income targets, support the need for the Council to become financially self-sustainable by 2019/20.
This report provides a short update on the Council’s current and medium term financial position.
1 Recommendation(s):
1.1That Cabinet note the financial pressures still being faced in Children’s Services;
1.2That Cabinet note the need to identify £18.5m through a combination of additional income and cost reduction over the period 2017/18 to 2019/20; and
1.3That Cabinet note the assumptions set out in the Medium Term Financial Strategy forecasts as set out in paragraph 4.2.
2 2015/16
2.1Previous reports have set out to Cabinet significant over spends in Children’s Services (gross pressures of £4m).
2.2The most recent analysis has identified that these pressures are increasing for three main reasons: a) Unaccompanied Asylum Seekers (UASC), including recognising assumed levels of reimbursement from government for the 2014/15 financial year;
b) The cost of placements; and
c) The cost of interim staff over and above establishment to meet acceptable social worker to child ratios.
2.3The current estimate of these additional pressures is £1.9m but further work is taking place on confirming this figure and what mitigation is available.
2.4Members will recall that the Council has an outstanding liability relating to pension costs from the Serco termination. The figure should have been provided by Essex County Council (ECC) Pension Section by now to give the Council certainty over the liability.
2.5An update from ECC on 18 February 2016 reported that they were still waiting, some three months after the termination date, for 80 case files and a number of queries to be answered by Serco. ECC’s current estimate is that it could be late April or even May before a figure can be provided.
2.6This puts the Council in difficulty in terms of closing the accounts for 2015/16 and we even need to recognise the impact on ECC doing this additional work at a year end, traditionally one of the busier times of the year. The likelihood is that the Council will have to close the accounts on an estimate.
3 2016/17
3.1The Council agreed a balanced budget at their meeting on 24 February 2016 that included a small budget to aid transition towards financial self- sustainability.
3.2There are three pressures that are already clear for 2016/17 that will be further considered and defined by Directors’ Board throughout March:
a) £2.5m of additional budget has been provisionally earmarked for Children’s Services. Directors’ Board will be considering the ongoing impact of current caseloads, numbers of Unaccompanied Asylum Seekers and the related impact of both of these areas on staffing levels and whether they will be contained within the additional budget provision. If this cannot be achieved, officers will bring back mitigating proposals;
b) The Public Health Grant (PHG) has been reduced by £0.924m. The combination of late notification of the grant and the fact that the majority of spend is subject to contracts, there is likely to be a pressure that cannot be mitigated within the PHG itself; and c) There has been a recognition that cuts in Environmental Services have been too drastic in recent years. A number of options to build on the current levels of service are currently being considered.
3.3All of the above will be kept within the agreed budget envelope.
4 Medium Term Financial Strategy (MTFS)
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Thurrock Transport Strategy Adoption2.1 Cabinet approved the Thurrock Transport Strategy given in Appendix 1 to be progressed to Full Council for adoptio...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.