Resolved
That the Standards & Audit Committee: 1. Consider reports issued by Internal Audit in relation to the 2014/15 audit plan. 2. Note progress against the Internal Audit Plan for 2014/15.
Standards and Audit Committee decided this item on Tuesday 17 March 2015. Below is the council's own wording, with the papers it was decided on.
Resolved
That the Standards & Audit Committee: 1. Consider reports issued by Internal Audit in relation to the 2014/15 audit plan. 2. Note progress against the Internal Audit Plan for 2014/15.
The Internal Audit Plan 2014/15 was discussed and noted by the Standards & Audit Committee at their meeting of 5th March 2014. This report sets out progress against the Internal Audit Plan 2014/15 and is the third progress report presented to the Standards & Audit Committee. It details reports finalised since the last progress report presented to the Committee on the 9th December 2014.
1. Recommendation(s)
That the Standards & Audit Committee: 1.1 Consider reports issued by Internal Audit in relation to the 2014/15 audit plan.
1.2Note progress against the Internal Audit Plan for 2014/15.
2. Introduction and Background
2.1The Accounts and Audit (England) Regulations 2011 require that a relevant body must undertake an adequate and effective internal audit of its accounting records and of its system of internal control in accordance with the proper practices in relation to internal control.
2.2The Internal Audit Service carries out the work to satisfy this legislative requirement and part of this is reporting the outcome of its work to the Standards & Audit Committee.
2.3The Standards & Audit Committee has a responsibility for reviewing the Council’s corporate governance arrangements, including internal control and formally approving the Annual Governance Statement. The audit work carried out by the Internal Audit Service is a key source of assurance to the Standards & Audit Committee about the operation of the internal control environment.
2.4The audits contained in the Internal Audit Plan 2014/15 are based on an assessment of risk for each system or operational area. The assessment of risk includes elements such as the level of corporate importance, materiality, service delivery/importance and sensitivity.
3. Issues, Options and Analysis of Options
3.1Following widespread consultation with clients across all service sectors, the reports issued by Internal Audit now provide 4 levels of assurance opinion. The 4 opinions use a Red/Amber/Green assurance level and reports are now categorised as: Green; Amber/Green (positive assurance opinions); Amber/Red (some assurance but a number of weaknesses) and Red (negative assurance opinion).
3.2In the year to date, we have issued 24 reports as final, have 8 reports at draft or debrief stage and have 5 reviews that are work in progress. We have summarised below (3.3 to 3.5), those reports that have been issued as final since the last meeting of the Committee. The key findings of these reports are shown at Appendix 1.
3.3The following reports received a Green assurance rating for the control frameworks in their area: Leaseholder Charges Thurrock Registrar’s Office Environmental Health (Pollution Control) Charges for Non-Residential Services Community Hubs Housing Rents NNDR (National Non Domestic Rates)
3.5The following report received an Amber/Red assurance rating for the control framework in its area: Change Controls (Serco) A full copy of the exception report is included at the end of Appendix 1.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Internal Audit Progress Report 2014-2015Appendix 1 | 401 KB | Download |
PDF |
Internal Audit Progress Report 2014-2015Report | 71 KB | DownloadRead as text |
Follow Standards and Audit Committee at Thurrock and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 21 Mar 2024 | Internal Audit Charter 20241.1 That the Standards and Audit Committee approve the (Appendix 1) and the Chair of the Standards and Audit Committe... | Approved | Open |
| 21 Mar 2024 | Internal Audit Protocol- Item to follow1.1 That the Standards and Audit Committee agree that the Internal Audit Protocol provides the Council and the Intern... | Agreed | Open |
| 21 Mar 2024 | Committee on Standards in Public Life Update1.1 Note the content of report of the Committee on Public Life’s report Leading in Practice (Appendix 1), and conside... | Noted | Open |
| 29 Feb 2024 | Internal Audit Progress Report1.1 Note the progress to 11 January 2024 against the Audit Plan 2023/24 as documented in Appendix 1. 1.2 Consider the... | Noted | Open |
| 29 Feb 2024 | Future Arrangements for the Standards and Audit Committee1.1 To consider the options set out in this report and recommend a preferred option for inclusion in the Annual Counc... | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.