That the School Capital Programme budget of £5.5 million funded as set out in this report be approved. 2. That the invitation of tenders be approved in accordance with Council & EU procurement procedures for a one year agreement for providing Specialist Project Teams, for a JCT (Joint Contracts Tribunal) form of contract School Improvement Programme, and principal contractors to take forward the proposed schemes. 3. That authority be delegated to the Director of Children’s Services, in consultation with Group Leaders, to enter into a contract following the selection procedure results in compliance with procurement regulations.
Word for word from the decision Thurrock published for this meeting.Source: democracy.thurrock.gov.uk
1.1That the School Capital Programme budget of £5.5 million funded as set out in this report be approved.
1.1.1 That the invitation of tenders be approved in accordance with Council & EU procurement procedures for a one year agreement for providing Specialist Project Teams, for a JCT (Joint Contracts Tribunal) form of contract School Improvement Programme, and principal contractors to take forward the proposed schemes.
1.2That authority be delegated to the Director of Children’s Services, in consultation with the relevant Portfolio Holder, to enter into a contract following the selection procedure results in compliance with procurement regulations.
2. Introduction and Background:
2.1The local authority has a statutory responsibility to ensure that suitable and sufficient school places are available in Thurrock for every child of school age whose parents wish them to have one
2.2The 2013/14 school capital programme consisted of six projects in Thurrock schools. The extensive programme is now at its conclusion, but for the provision of an additional double demountable classroom at Woodside Academy which is in progress at the time of writing this report.
2.3The 2013/14 school capital programme progressed well and incorporated innovative partnership working to deliver the identified additional pupil places required
2.4The provision of additional accommodation to meet the predicted increase in pupil numbers has generated positive feedback from schools, particularly in relation to the impact on learning through improvements to the built environment.
2.5The demand for pupil places has increased significantly, over the last few months we have seen a large increase in ‘in term’ admissions from families moving into the Authority. In 2013/14, 209 children moved into Thurrock from outside of the UK, and 590 from elsewhere within the UK. For the first five months of this year, 199 more children have moved into Thurrock from outside of the UK, and there have been 493 new arrivals from within the UK. The demand does not appear to be slowing, and this level of demand has not been seen before. This is putting greater pressures on places, and steps need to be taken now to further increase capacity within schools.
2.6The contract for providing a specialist programme/project management multi- disciplinary design team to oversee the Schools Capital Programme has expired. A stopgap contract for carrying out feasibility studies in relation to the possible expansion of Woodside Academy and Thameside Primary due to the predicted increase in pupil numbers has been undertaken, in the short term, individual contracts are currently being utilised for any immediate urgent remodelling works, and the provision of demountable modular buildings.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.