That Cabinet: 1. Approved the extended School Capital programme budget of £6,900,000 for St Clere’s and bulge classes for the new Orsett Heath Free School. 2. Approved the invitation of tenders in accordance with EU procurement procedures for a one year agreement for providing a Specialist Project Team, and Principal Contractor for a school capital programme. 3. That, following a selection procedure compliant with EU procurement regulations, the subsequent decision to enter into the contract be delegated to the Accountable Director reporting ... view the full minutes text for item 62.
Word for word from the decision Thurrock published for this meeting.Source: democracy.thurrock.gov.uk
Thurrock Council and partners has acquired significant additional resources through the free school programme, council funds and 106 monies, and is investing over £70m to deliver over 3,500 new good school places in Thurrock.
In addition, we are going to use our capital power to enable the building of quality new services from special needs units to sports facilities. This is to help us further renovate and build a more inclusive system and develop more planned use of alternative provision with the support of our schools.
Our policy is to build big and to support the growth, closer cooperation and healthy competition between our family of MAT’s.
This paper details the release of funds to complete already committed projects such as the St Clere’s expansion in Stanford, ensure delivery of the new Orsett Health Academy School, as well as the emerging schemes to support expansion in Ockendon and improvement works in Corringham and Purfleet.
Recommendations
1.1That Cabinet approves the extended School Capital programme budget of £6,900,000 for St Clere’s and bulge classes for the new Orsett Heath Free School. 1.2 That Cabinet approves the invitation of tenders in accordance with EU procurement procedures for a one year agreement for providing a Specialist Project Team, and Principal Contractor for a school capital programme.
1.3That, following a selection procedure compliant with the EU procurement regulations, the subsequent decision to enter into the contract be delegated to the Accountable Director reporting back to the Portfolio Holder, such report to detail the selection procedure results, and compliance with the EU procurement regulations.
1.4Cabinet endorses the forward work and feasibility studies coming forward for the expansions and or improvement works at Corringham Primary, Harris Riverside and Benyon Primary, and the works to continue to deliver inclusion units across Thurrock and their associated costs.
2. Introduction and Background:
2.1The local authority has a statutory responsibility to ensure that suitable and sufficient school places are available in Thurrock for every child of school age whose parents wish them to have one.
2.2The 2017/18 school capital programme consisted of three projects in Thurrock schools. The extensive programme is now well underway and upon completion will have provided one form entry expansions at The Ockendon Academy, St Clere’s and East Tilbury Primary, a total of 510 additional school places.
2.3The 2017/18 school capital programme progressed well and incorporated innovative partnership working to deliver the identified additional pupil places required. The provision of additional accommodation to meet the predicted increase in pupil numbers has generated positive feedback from schools, particularly in relation to the impact on learning through improvements to the built environment.
2.4The conclusion of the feasibility study undertaken at St Clere’s during May 2018 recommended the use of a framework agreement to procure via a 2- stage tender process. This will require the appointment of a consultant to produce the outline design and submit the planning application before preparing stage one tender documentation.
2.5Contractors are then invited to submit tenders for the construction of the project on competitive basis – submitting a completed quality questionnaire and fee rates (based on Overheads and Profit figures as well as fully priced preliminaries).
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Thurrock Transport Strategy Adoption2.1 Cabinet approved the Thurrock Transport Strategy given in Appendix 1 to be progressed to Full Council for adoptio...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.