Cabinet to note the progress of the Housing Development Programme being funded by Department of Communities and Local Government (DCLG) and Homes and Communities Agency (HCA) through the programmes under the Local Growth Fund and approve the feasibility studies for these potential developments. 2. Cabinet to endorse the exploration of potential additional Growth Fund Bids with HCA to support the housing estate regeneration plans within the borough. 3. Cabinet to approve the consideration being given to the use of sites identified within the Council’s emerging Grays Town Centre master plan to facilitate the development of new, high quality housing and the wider housing regeneration proposals for the Seabrooke Rise Estate. 4. Cabinet to approve, subject to consultation with residents, the development of the extended Tops Club site in South Grays and re-location of community play area to support the on-going regeneration of the Seabrooke Rise estate. 5. Cabinet to note the progress in relation to the potential joint development of the Riverside/ Rippleside site on Argent Street, South Grays and approve for the inclusion of the Council-owned part of the site within the Seabrooke Rise estate regeneration plans if a joint development with the adjacent owners is not deliverable. 6. Cabinet to note the progress that has been achieved on the Housing Estate Regeneration programme and the publication of the Prior Information Notice (PIN) in relation to the proposed housing regeneration opportunity. 7. Cabinet to note the HRA’s acquisition of the former Prince of Wales public house in South Ockendon as a strategically important development site to facilitate the wider estate regeneration plans for the Flowers estate. Reason for Decision - as stated in the report This decision is subject to call-in
Word for word from the decision Thurrock published for this meeting.Source: democracy.thurrock.gov.uk
Reports to Cabinet in December 2014 and June 2015 updated Members on the progress that had been made on the housing estate regeneration programme, obtained approval for the vision and objectives for the programme, and the next steps required to prepare for and facilitate the procurement of a regeneration partner or partners to assist in the programme’s delivery.
This report provides an update of progress and seeks the necessary approvals to progress the programme’s delivery.
Recommendations
1.1Cabinet to note the progress of the Housing Development Programme being funded by Department of Communities and Local Government (DCLG) and Homes and Communities Agency (HCA) through the programmes under the Local Growth Fund and approve the feasibility studies for these potential developments.
1.2Cabinet to endorse the exploration of potential additional Growth Fund Bids with HCA to support the housing estate regeneration plans within the borough.
1.3Cabinet to approve the consideration being given to the use of sites identified within the Council’s emerging Grays Town Centre master plan to facilitate the development of new, high quality housing and the wider housing regeneration proposals for the Seabrooke Rise Estate. 1.4 Cabinet to approve, subject to consultation with residents, the development of the extended Tops Club site in South Grays and re- location of community play area to support the on-going regeneration of the Seabrooke Rise estate.
1.5Cabinet to note the progress in relation to the potential joint development of the Riverside/Rippleside site on Argent Street, South Grays and approve for the inclusion of the Council-owned part of the site within the Seabrooke Rise estate regeneration plans if a joint development with the adjacent owners is not deliverable.
1.6Cabinet to note the progress that has been achieved on the Housing Estate Regeneration programme and the publication of the Prior Information Notice (PIN) in relation to the proposed housing regeneration opportunity.
1.7Cabinet to note the HRA’s acquisition of the former Prince of Wales public house in South Ockendon as a strategically important development site to facilitate the wider estate regeneration plans for the Flowers estate.
2. Introduction and Background
2.1Since 2013, Cabinet have approved key objectives and programmes designed to improve the quality homes within the borough and in June 2015, approved the vision and strategic objectives associated with a broader programme of regeneration on our key housing estates. Estates where the cost of meeting the Transforming Homes standards are very high, will not provide comparable benefits in terms of regeneration and on estates that were built to very low- density standards with under used and poor quality garage and open space provision.
2.2Adopting a wider regeneration approach, the Council will be able to provide better quality housing for existing residents and better meet future housing needs of the borough by providing much needed additional housing within the footprint of the existing housing estates and adjacent opportunity sites.
2.3The Housing Department was successful in securing additional borrowing and HCA grant for a number of potential developments across the borough. Further feasibility, coupled with further discussions with planning and further exploration on the scope and phasing of any potential estate regeneration programme has required us to re-evaluate individual developments and make amendments to our programme.
3. Issues, Options and Analysis of Options
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Thurrock Transport Strategy Adoption2.1 Cabinet approved the Thurrock Transport Strategy given in Appendix 1 to be progressed to Full Council for adoptio...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.