That the Standards and Audit Committee approved that, following ICT transformation completion (3 months following transfer back), officers carry out a new Business Impact Analysis (BIA) across Directorate Services to establish realistic Recovery Time Objectives (RTO) for each Service and report back in March 2016. 2. That officers, post transfer, correlate the Recovery Time Objective (RTO*) information from the Services and determine the appropriate DR solution required in order to meet them and report back in March 2016. * The RTO is the maximum sustainable time possible without critical ICT availability before a Service reaches an unacceptable level of risk towards: • Endangering human life / well-being • The Council suffering significant financial loss 3. Officers complete an appropriate DR solution that better suits the Council’s modern technology, way of working and increased freedom to collaborate with other Local Authorities and report back in March 2016.
Word for word from the decision Thurrock published for this meeting.Source: democracy.thurrock.gov.uk
For clarity, it would be beneficial for the Committee to understand the context in which this report has been constructed relating to Business Continuity Planning (BCP) and Disaster Recovery (DR) interpretations:
Business Continuity Plan – means an overarching plan pertaining to each Service delivered by the Council. The BCP outlines how that particular Service / Services will continue to be delivered in the event that one of these four events disrupts it: o People - Loss of staff e.g. as a result of pandemic flu o Premises - Denial of access to buildings e.g. in the event of a fire or flood o Resources - Loss of access to data e.g. failure of one or more of the council’s servers o Suppliers - Products and services supplied by third parties e.g. loss of utilities including gas, water, electricity or telecommunications.
Disaster Recovery – means a separate BCP in its own right that outlines how the Council will recover in the event that one of the four events above specifically affects the primary data centre at Civic Offices in Grays, Essex.
This report sets out the position at Thurrock Council regarding the following requirements identified at previous committee meetings:
It outlines the progress with updating non-Serco Disaster Recovery (DR) plans It outlines the availability of an offsite location in the event of DR invocation The results of Thurrock Council’s DR Test It gives a summary of the ongoing activity to future proof Business Continuity for Thurrock Council.
1. Recommendation(s)
1.1Standards and Audit Committee approve that, following ICT transformation completion (3 months following transfer back), officers carry out a new Business Impact Analysis (BIA) across Directorate Services to establish realistic Recovery Time Objectives (RTO) for each Service and report back in March 2016.
1.2That officers, post transfer, correlate the Recovery Time Objective (RTO*) information from the Services and determine the appropriate DR solution required in order to meet them and report back in March 2016.
*The RTO is the maximum sustainable time possible without critical ICT availability before a Service reaches an unacceptable level of risk towards: Endangering human life / well-being The Council suffering significant financial loss
1.3Officers complete an appropriate DR solution that better suits the Council’s modern technology, way of working and increased freedom to collaborate with other Local Authorities and report back in March 2016.
2. Introduction and Background
For the past eleven years Thurrock Council has outsourced, amongst other services, its ICT service to Serco and has had very limited control over how the service has been delivered in order to meet the stipulations outlined in the agreement (the SSPA) that was made by the two parties in 2005.
Recently it has been agreed that the contract between the two parties no longer reflects both parties’ requirements and a mutual termination has been agreed.
DR Plan update – Whilst the Serco ICT DR plan is quite comprehensive with regards to the detail it contains, it was found to still have a number of areas that require further review and updating. This is primarily to bring it in line with current staff positions; for example the ICT Commercial Manager is not included as a key Council staff member in the plan since the role didn’t exist back in March 2015 when the plan was last reviewed. The plan was also found to have a different list of Critical Council Services to those that the Council felt needed to be prioritised in the event of invoking DR.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Internal Audit Protocol- Item to follow1.1 That the Standards and Audit Committee agree that the Internal Audit Protocol provides the Council and the Intern...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.