RESOLVED that Cabinet: 1. Agree the proposed process for procurement of the works and services referred to above for a period of 4 (four) years under a framework agreement. 2. Approve delegation to award the contract to the Corporate Director of Adults, Housing and Health in consultation with the Portfolio holder in order to expedite the process for this critical provision. Reason for Decision - as stated in the report This decision is subject to call-in
Word for word from the decision Thurrock published for this meeting.Source: democracy.thurrock.gov.uk
1.1This report sets out the proposals to procure a contract to provide works and services in residents’ homes where disabled adaptations are required. Primarily the contract will be utilised for Thurrock Housing properties; however, in some instances where owner occupiers are eligible for adaptations funded by the Disabled Facilities Grant (DFG) and the individuals concerned are unable to manage the project themselves; then in these cases it is proposed the client role will be covered by the Council, using this contract.
1.2The contract will be divided into two elements (Lots) covering:
Supply, installation, maintenance and repair of mechanical aids (stairlifts, ceiling hoists, step and through floor lifts etc)
Major adaptations (building works) over £1,000 per home but outside of the scope of the Transforming Homes Programme
2. Recommendation(s)
Cabinet is recommended to:
2.1Agree the proposed process for procurement of the works and services referred to above for a period of 4 (four) years under a framework agreement. 2.2 Approve delegation to award the contract to the Corporate Director of Adults, Housing and Health in consultation with the Portfolio holder in order to expedite the process for this critical provision.
3. Introduction and Background
3.1The previous contract providing various elements of disabled adaptations work in Thurrock Council Housing properties expired over two years ago and during the recent past, officers have undertaken small projects by way of quotes or waivers where requests have been made.
3.2Up until now, owner occupiers in receipt of DFG funding have been required to get three quotes for their planned work, which has then been approved to an agreed level by the Council, subject to a “benchmark” set of rates. The funding amount was then paid by the Council to the recipient once the work was completed.
3.3The exception to the individually contracted arrangements set out in 3.1 is a term contract that Thurrock holds with one contractor for the testing and servicing of the mechanical installations (such as Ceiling Hoists), all of which have a range of statutory requirements the Council is required to meet. This contract is with Mountfield Services Ltd and expires on 31st March 2017. It is proposed that the new contract will take over this element of the service from that date.
3.4There are in addition, contracts already in place for the delivery of the Housing Transforming Homes programme which include undertaking any adaptations required to the areas where the programme is undertaking works. The new contract is to cover properties outside the Transforming Homes programme.
3.5As part of the arrangement with Essex County Council, the Essex Cares Service also currently provides minor adaptation work to a value up to £1,000.
4. Issues, Options and Analysis of Options
Spend/Cost
4.1Across the contractors currently used for individual Disabled Adaptation Projects, the identified cumulative spend is in the region of £250,000 per annum at current activity levels, which is above the EU threshold for supplies and services. Adding the DFG element will increase the spend further, but as each case differs, this is difficult to estimate.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Thurrock Transport Strategy Adoption2.1 Cabinet approved the Thurrock Transport Strategy given in Appendix 1 to be progressed to Full Council for adoptio...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.