Resolved
1.1 That the Standards and Audit Committee considered the reports issued and the work being carried out by the Internal Audit in relation to the 2017/18 audit plan.
Standards and Audit Committee decided this item on Thursday 19 July 2018. Below is the council's own wording, with the papers it was decided on.
Resolved
1.1 That the Standards and Audit Committee considered the reports issued and the work being carried out by the Internal Audit in relation to the 2017/18 audit plan.
The Internal Audit Plan 2017/18 was discussed by the Standards & Audit Committee at their meeting of 28 February 2017. This progress report covers work undertaken since the last report issued on 6 March 2018.
1. Recommendation(s)
1.1That the Standards & Audit Committee: Consider reports issued and the work being carried out by Internal Audit in relation to the 2017/18 audit plan.
2. Introduction and Background
2.1The Accounts and Audit Regulations 2015 require that a relevant authority must undertake an effective internal audit to evaluate the effectiveness of its risk management, control and governance processes, taking into account public sector internal auditing standards or guidance.
2.2The Internal Audit Service carries out the work to satisfy this legislative requirement and part of this is reporting the outcome of its work to the Standards & Audit Committee.
2.3The Standards & Audit Committee has a responsibility for reviewing the Council’s corporate governance arrangements, including internal control and formally approving the Annual Governance Statement. The audit work carried out by the Internal Audit Service is a key source of assurance to the Standards & Audit Committee about the operation of the internal control environment. 2.4 The audits contained in the Internal Audit Plan 2017/18 are based on an assessment of risk for each system or operational area. The assessment of risk includes elements such as the level of corporate importance, materiality, service delivery/importance and sensitivity.
3. Issues, Options and Analysis of Options
3.1The reports issued by Internal Audit provide 4 levels of assurance opinion. The 4 opinions use a Red/Amber/Green (RAG) assurance level and reports are now categorised as:
Green; Amber/Green (positive assurance opinions); Amber/Red (negative assurance opinion that provides some assurance but a number of weaknesses were identified); and Red (negative assurance opinion).
3.2During the period being reported on, we have finalised 9 reports. These cover the following areas: Section 17 Payments; Better Care Fund; Children’s Care Packages; General Data Protection Regulations; Register of Gifts, Interests and Hospitality; IR35; Responsive Repairs and Maintenance (Housing); Insurance and Waste Disposal Contracts.
3.3Of the 9 reports issued, 6 received a Green assurance opinion and 3 an Amber/Green opinion. Therefore, all of these reports received positive assurance opinions and further details of the headline findings are shown in Appendix 1.
3.4The purpose of this progress report for 2017/18 is to highlight reports issued as final by the end of the year. Any draft reports will be carried forward and reported as part of the 2018/19 progress reporting arrangements.
4.1To assist the Standards & Audit Committee in satisfying itself that progress against the Internal Audit Plan is sufficient as one of the means of assuring itself of the effective operation of internal controls. 5. Consultation (including Overview and Scrutiny, if applicable)
5.1The audit risk assessment and the plan are periodically discussed with the Chief Executive, Corporate Directors, Directors and Heads of Service before being reported to Directors Board and the Standards & Audit Committee. 5.2 All terms of reference and draft reports are discussed and agreed with the relevant Corporate Directors, Directors, Heads of Service and/or management before being finalised. 5.3 The Internal Audit Service also consults with the council’s External Auditors to ensure that respective audit plans provide full coverage whilst avoiding duplication. 6. Impact on corporate policies, priorities, performance and community impact
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Internal Audit Progress ReportAppendix 1 | 304 KB | Download |
PDF |
Internal Audit Progress Report 2017/18Report | 66 KB | DownloadRead as text |
Follow Standards and Audit Committee at Thurrock and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 21 Mar 2024 | Internal Audit Charter 20241.1 That the Standards and Audit Committee approve the (Appendix 1) and the Chair of the Standards and Audit Committe... | Approved | Open |
| 21 Mar 2024 | Internal Audit Protocol- Item to follow1.1 That the Standards and Audit Committee agree that the Internal Audit Protocol provides the Council and the Intern... | Agreed | Open |
| 21 Mar 2024 | Committee on Standards in Public Life Update1.1 Note the content of report of the Committee on Public Life’s report Leading in Practice (Appendix 1), and conside... | Noted | Open |
| 29 Feb 2024 | Internal Audit Progress Report1.1 Note the progress to 11 January 2024 against the Audit Plan 2023/24 as documented in Appendix 1. 1.2 Consider the... | Noted | Open |
| 29 Feb 2024 | Future Arrangements for the Standards and Audit Committee1.1 To consider the options set out in this report and recommend a preferred option for inclusion in the Annual Counc... | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.