That Cabinet: 1. Delegated authority to the Director of Place and the Director of Environment and Highways, in consultation with the Portfolio Holder for Highways and Transportation, to decide the appropriate procurement route for the delivery of the Transport and Highways services and schemes for the next five years, commencing 1 April 2021. 2. Approved the process to commence procurement of Transport and Highways services and schemes for a five-year period commencing 1 April 2021, which will be compliant with relevant EU Public Procurement Regulation, the Public Contracts Regulations 2015, and the Council’s Contract Procedure Rules. 3. Delegated authority to the Director of Environment and Highways, in consultation with the Portfolio Holder for Place and Environment and Highways, to award any contracts necessary for the delivery of transportation and highways services for a five-year period commencing 1 April 2021. Reason for decision: as outlined in the report This decision is subject to call-in
Word for word from the decision Thurrock published for this meeting.Source: democracy.thurrock.gov.uk
This report aims to gain delegated authority to procure and award a Works contract, a Professional Services contract and a Structures Consultancy contract necessary to deliver the Transport and Highways capital works programmes for the next five years, commencing 1 April 2021.
Recommendations
That Cabinet:
1.1Delegate authority to the Director of Place and the Director of Environment and Highways, in consultation with the Portfolio Holder for Highways and Transportation to decide the appropriate procurement route for the delivery of the Transport & Highways services and schemes for the next five years commencing 1 April 2021.
1.2Approve the process to commence procurement of Transport & Highways services and schemes for a five-year period commencing 1st April 2021, which will be compliant with relevant EU Public Procurement Regulations, the Public Contracts Regulations 2015 and the Council’s Contract Procedure Rules.
1.3Delegate authority to the Director of Environment and Highways, in consultation with the Portfolio Holder for Place and Environment and Highways, to award any contracts necessary for the delivery of transportation and highways services for a five year period commencing 1 April 2021.
2. Introduction and Background
2.1In June 2015 Cabinet gave delegated authority to the Director of Planning and Transportation, in conjunction with the Portfolio Holder for Highways and Transportation, to decide the appropriate procurement process and to award contracts necessary for the delivery of Transport and Highways services for the then next five years. That procurement route was through the Official Journal of the European Union (OJEU)
2.2This allowed the procurement of contracts as follows: a £40 million term maintenance and highway improvements contract for works, a £2 million engineering professional services and a £1.35 million structures consultancy contract.
2.3These contracts allowed transportation and highways teams to gain efficiencies through reduced administration and procurement costs. On previous occasions, a mini competition procurement process was necessary for each new project, many of which were of low value but still necessitated the undertaking of a procurement process to comply with the Council’s Contract Procedure Rules.
2.4This meant that the Transportation and Highway teams had an opportunity to concentrate on service delivery and were able to identify further service needs, which are processed through an internal capital bid process. Projects such as the full reconstruction of Stonehouse Lane and ‘Kerb it’ are funded this way.
2.5In the first two years of the term contract, the works procured amounted to £17 million. This means that the estimated average spending used to procure £40 million contract (1 April 2017 – 31 March 2023) increased form £6.67 million to £8.5 million in the past two years and a further increase to £10.75 million is projected for 2019-20. If the spending through the term maintenance and highway improvements contract remains at the latter value, the total expenditure by year six would rise to around £60 million, 50% over the value of tendered contract.
2.6Any further expenditure over 50% of the original contact sum is not permitted under Public Contract Regulations 2015 (Regulation 72) and there is therefore a requirement to undertake a new procurement process.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Thurrock Transport Strategy Adoption2.1 Cabinet approved the Thurrock Transport Strategy given in Appendix 1 to be progressed to Full Council for adoptio...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.