1.1 That the Children’s Services Overview & Scrutiny Committee consider and recommend the following decisions to Cabinet. 1.2 To approve the commencement of the procurement process in accordance with Council & UK procurement procedures to appoint 1. A Design and multi discipline project Team, for the Tilbury Pioneer aspect of the School Capital Programme and 2. Following planning approval and the production of a full technical specification, undertake a further procurement exercise to appoint a Principal Contractor to take forward the proposed Tilbury Pioneer scheme. 1.3 To approve the commencement of the procurement process in accordance with Council & UK procurement procedures to appoint Designers and Project Teams, for the School Capital Programme and appoint the Principal Contractors to take forward the proposed scheme. 1.4 That authority be delegated to the Director of Children’s Services, in consultation with the relevant Portfolio Holder, to enter into any form of agreement following the award of the agreements arising from ... view the full minutes text for item 27.
Word for word from the decision Thurrock published for this meeting.Source: democracy.thurrock.gov.uk
Report to Children's Services Overview and Scrutiny Committee
Executive summary
The council’s school capital programme is developed following extensive pupil place planning to assess the potential likely demand for school places, this forms part of the council’s statutory duties around pupil place planning. The current programme aims to deliver sufficient pupil places for the 2022 and 2023 academic years. Cabinet approval will be sought to procure an architect led design team, as well as a principal contractor for the expansion of Tilbury Pioneer Academy from a 2FE to a form 3 FE Primary school which would provide an additional 210 school places plus the potential for an additional special need autism base. Design feasibility studies are already completed at the time of writing this report, with initial indications showing that depending on the option taken, this project will have an estimated provisional total value of up to £3.0M inclusive of Architects fees and all other disbursements. Additionally, this report provides an update on current capital projects managed by Thurrock Council which form part of the current school capital programme outlining the progress that has been achieved since the last report to Cabinet in January 2021.
Recommendations
1.1That the Children’s Services Overview & Scrutiny Committee consider and recommend the following decisions to Cabinet.
1.2To approve the commencement of the procurement process in accordance with Council & UK procurement procedures to appoint 1. A Design and multi discipline project Team, for the Tilbury Pioneer aspect of the School Capital Programme and 2. Following planning approval and the production of a full technical specification, undertake a further procurement exercise to appoint a Principal Contractor to take forward the proposed Tilbury Pioneer scheme.
1.3To approve the commencement of the procurement process in accordance with Council & UK procurement procedures to appoint Designers and Project Teams, for the School Capital Programme and appoint the Principal Contractors to take forward the proposed scheme.
1.4That authority be delegated to the Director of Children’s Services, in consultation with the relevant Portfolio Holder, to enter into any form of agreement following the award of the agreements arising from 1.2 above in compliance with the Council’s procurement regulations.
1.5Note the recent in-year accommodation works that have been commenced in order to ensure sufficient pupil places for 2022/2023 in- year applications.
2. Introduction and Background
2.1The local authority has a statutory responsibility to ensure that suitable and sufficient places are available in Thurrock for every child of school age whose parents wish them to take up a school place.
The 2022/23 school capital programme has progressed well and incorporated innovative partnership working, as well as utilising modern methods of construction to deliver the identified additional pupil places required.
2.2The demand for pupil places has increased significantly, over the last few years we have seen a large increase in ‘in year’ admissions from families moving into Thurrock. In the academic year 2021/22 (September to July), 1846 children moved into Thurrock. At the time of writing this report, 604 more children moved into Thurrock between September and December 2022. We are not seeing a decrease in the demand for school places, the level of demand continues to be unprecedented. To be in a position to accommodate this demand, we are building in additional places to support in-year growth across a number of year groups where it has been identified that we do not have sufficient school places.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Children's Services Overview and Scrutiny Committee at Thurrock and we tell you when its next papers are published, before the meeting rather than after it.
Families First Partnership ReportDecision Making (FGDM). It was noted that initial engagement with key partners is underway. However, significant regi...
School Capital Programme Update 2023/24The Committee supported the recommendation of 1.2 rather than 1.1. Cabinet to approve recommendation 1.2 set out belo...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.