The Committee supported the recommendation of 1.2 rather than 1.1. Cabinet to approve recommendation 1.2 set out below: 1.2 To approve a budget of £4.75M budget for the new build works to allow for the expansion of Tilbury Pioneer Academy to be funded from the School’s Basic Need capital funding 2023/24 Recommendations 1.3, 1.4, 1.5, and 1.6 were agreed and supported by the Committee. 1.3 To approve the commencement of the procurement process in accordance with Council & UK procurement procedures to vary the appointment and scope of works to be undertaken by the Multi Discipline design team for the Tilbury Pioneer Expansion Project and appoint the Principal Contractors to take forward the proposed desired scheme. 1.4 That authority be delegated to the Director of Children’s Services, in consultation with the Education ... view the full minutes text for item 48.
Word for word from the decision Thurrock published for this meeting.Source: democracy.thurrock.gov.uk
Report to Children's Services Overview and Scrutiny Committee
Executive summary
Cabinet approval will be sought on one of the options proposed within this report including the approval of additional spend that is required for the expansion of Tilbury Pioneer Academy. On 15th March 2023, Cabinet approved a budget of £3M along with the procurement process to appoint a design and multi-disciplinary project team to undertake required surveys and develop a detailed cost plan for the refurbishment of the part of the old block that was on the Tilbury Pioneer site and was due to be demolished. Following this detailed work and the increase in cost it is clear that Cabinet needs to reconsider whether new build is more feasible than refurbishment. The expansion works for Tilbury Pioneer Academy will be funded from the DfE basic need grant (not Council general fund), which has sufficient funds available to cover either option presented within the report. Cabinet approval will be also be sought for the approval of £1M to proceed with works to convert a council owned building in Northview Avenue , Tilbury to a secondary SEMH (Social, Emotional, Mental Health provision, which will be run by Olive Academy. The works will be funded from the DfE SEN Capital Grant (not Council general fund), which has sufficient funds available. Additionally, this report provides an update on current capital projects managed by Thurrock Council which form part of the current school capital programme outlining the progress that has been achieved since the last report to Cabinet in March 2023. The current programme aims to deliver sufficient pupil places for 2024/25 academic years in mainstream and SEN provision.
Commissioner Comment:
Commissioners have been consulted on the content of this report and agree with the recommendations made.
Version: Committee Recommendation(s)
That the Children’s Services Overview & Scrutiny Committee consider and recommend the following decisions to Cabinet. Cabinet to approve recommendation 1.1 or 1.2 set out below:
1.1To approve a £3.85M budget for refurbishment works to allow for the expansion of Tilbury Pioneer Academy to be funded from the School’s Basic Need capital funding 2023/24.
1.2To approve a budget of £4.75M budget for the new build works to allow for the expansion of Tilbury Pioneer Academy to be funded from the School’s Basic Need capital funding 2023/24.
1.3To approve the commencement of the procurement process in accordance with Council & UK procurement procedures to vary the appointment and scope of works to be undertaken by the Multi Discipline design team for the Tilbury Pioneer Expansion Project and appoint the Principal Contractors to take forward the proposed desired scheme.
1.3That authority be delegated to the Director of Children’s Services, in consultation with the Education Portfolio Holder, to enter into any form of agreement following the award of the agreements arising from 1.1 or 1.2 above in compliance with the Council’s procurement regulations.
1.4To approve a £1M budget for alternation works at Northview Avenue , Tilbury to allow for a secondary SEMH provision to be funded from SEN Capital government grant 2023/24.
1.5Note the recent in-year accommodation works that have commenced and completed in order to ensure sufficient pupil places for 2023/2024.
2. Introduction and Background
2.1The Council has a statutory responsibility to ensure that suitable and sufficient places are available in Thurrock for every child of school age whose parents wish them to take up a school place.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Children's Services Overview and Scrutiny Committee at Thurrock and we tell you when its next papers are published, before the meeting rather than after it.
Families First Partnership ReportDecision Making (FGDM). It was noted that initial engagement with key partners is underway. However, significant regi...
Educational Attainment Data 2022-20231.1 Children’s Overview & Scrutiny receive the provisional outcomes of the summer 2023 tests and examinations and com...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.