RESOLVED 1. Noted the progress made so far on LDO2 and the future actions and processes necessary to bring LDO2 to a position where is it ready to be adopted. 2. Delegated authority on the decision whether or not to adopt LDO2 to the Planning Committee. 3. Delegated authority on the decision whether or not to adopt LDO1.5 to the Planning Committee. Councillor Kelly returned to the chamber at 7.55pm.
Word for word from the decision Thurrock published for this meeting.Source: democracy.thurrock.gov.uk
This report is concerned with the planning consenting regime for securing the delivery of strategic employment development at London Gateway logistics park. The report details how, in order to ensure that the recent economic growth, jobs and investment at the park continue to be delivered in an efficient and sustainable manner a new Local Development Order is required.
The report explains that development on the logistics park site has been subject to the provisions of a Local Development Order (LDO) since 2013. As this Order is time-limited for a period of 10 years, the report explains the work undertaken so far in preparing a new Order (referred to as ‘LDO2’). This report also provides an update on progress with LDO2 since the matter was reported to the Planning Committee in July 2021 and February 2023. This report asks that the final decision on whether to adopt LDO2 is delegated to the Planning Committee.
The report also notes that DP World London Gateway (DPWLG) have recently approached Officers regarding potential development of up to 85,000 sq. m. of commercial floorspace on land within the logistics park site and the planning mechanism for securing planning consent to enable this development. The report considers this particular development plot in the context of the existing LDO), the emerging LDO2 and other planning mechanisms for delivery i.e. a limited, stand- alone Local Development Order for this Plot (LDO1.5).
Version – Final 1. Recommendations
1.1To note this report, the progress made so far on LDO2 and the future actions and processes necessary to bring LDO2 to a position where is it ready to be adopted.
1.2To delegate authority on the decision whether or not to adopt LDO2 to the Planning Committee.
1.3To delegate authority on the decision whether or not to adopt LDO1.5 to the Planning Committee
2. Introduction and background
2.1A planning application for the redevelopment of the former Shell Haven oil refinery site was submitted to the Council in January 2002 (application reference 02/00084/OUT). The application was subsequently “called-in” by the Secretary of State in June 2002 and a public inquiry was held during 2003. This inquiry also considered an application for a Transport and Works Act Order for works to various railways adjoining the site and a proposed Harbour Empowerment Order, for the construction and operation of a new port adjacent to the River Thames. Outline planning permission (OPC) was granted by the Secretary of State on 30th May 2007.
2.2The London Gateway Logistics and Commercial Centre Order 2007, issued pursuant to the Transport and Works Act, came into force on 28th September 2007. The London Gateway Port Harbour Empowerment Order 2008 (HEO) came into force on 16th May 2008 and the dredging operations necessary to create the new port commenced in March 2010. The first berth at London Gateway Port came into operational use in November 2013. Currently three berths are in use at the Port, with a fourth berth currently under construction and due for completion in 2024.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.