London Gateway Logistics Park Local Development Orders (Decision: 110677)

Noted Executive 1 paper

Cabinet noted this item on Wednesday 8 November 2023. Below is the council's own wording, with the papers it was decided on.

Item198

Resolved

1.1 To note this report, the progress made so far on LDO2 and the future actions and processes necessary to bring LDO2 to a position where is it ready to be adopted. 1.2 To recommend to the Council meeting on 29 November 2023 that it delegates authority on the decision whether or not to adopt LDO2 to the Planning Committee. 1.3 To recommend to the Council meeting on 29 November 2023 that it delegates authority on the decision whether or not to adopt ‘LDO1.5’ to the Planning Committee. Reason for the decision: as outlined in the report This decision is subject to call-in
Word for word from the decision Thurrock published for this meeting. Source: democracy.thurrock.gov.uk

Follow this further

Built from Thurrock's papers

What the report saysPro

Report to Cabinet

Executive summary

This report is concerned with the planning consenting regime for securing the delivery of strategic employment development at London Gateway logistics park. The report details how, in order to ensure that the recent economic growth, jobs and investment at the park continue to be delivered in an efficient and sustainable manner a new Local Development Order is required.

The report explains that development on the logistics park site has been subject to the provisions of a Local Development Order (LDO) since 2013. As this Order is time-limited for a period of 10 years, the report explains the work undertaken so far in preparing a new Order (referred to as ‘LDO2’) This report also provides an update on progress with LDO2 since the matter was reported to the Planning Committee in July 2021 and February 2023. This report asks that the final decision on whether to adopt LDO2 is delegated to the Planning Committee.

The report also notes that DP World London Gateway (DPWLG) have recently approached Officers regarding potential development of up to 85,000 sq. m. of commercial floorspace on land within the logistics park site and the planning mechanism for securing planning consent to enable this development. The report considers this particular development plot in the context of the existing LDO, the emerging LDO2 and other planning mechanisms for delivery i.e. a limited, stand- alone Local Development Order for this Plot (LDO1.5).

1. Recommendations 1.1 To note this report, the progress made so far on LDO2 and the future actions and processes necessary to bring LDO2 to a position where is it ready to be adopted.

1.2To recommend to the Council meeting on 29 November 2023 that it delegates authority on the decision whether or not to adopt LDO2 to the Planning Committee.

1.3To recommend to the Council meeting on 29 November 2023 that it delegates authority on the decision whether or not to adopt ‘LDO1.5’ to the Planning Committee.

2 Introduction and background

2.1A planning application for the redevelopment of the former Shell Haven oil refinery site was submitted to the Council in January 2002 (application reference 02/00084/OUT). The application was subsequently “called-in” by the Secretary of State in June 2002 and a public inquiry was held during 2003. This inquiry also considered an application for a Transport and Works Act Order for works to various railways adjoining the site and a proposed Harbour Empowerment Order, for the construction and operation of a new port adjacent to the River Thames. Outline planning permission (OPC) was granted by the Secretary of State on 30th May 2007.

2.2The London Gateway Logistics and Commercial Centre Order 2007, issued pursuant to the Transport and Works Act, came into force on 28th September 2007. The London Gateway Port Harbour Empowerment Order 2008 (HEO) came into force on 16th May 2008 and the dredging operations necessary to create the new port commenced in March 2010. The first berth at London Gateway Port came into operational use in November 2013. Currently three berths are in use at the Port, with a fourth berth currently under construction and due for completion in 2024.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
London Gateway Logistics Park Local Development Orders (Decision: 110677)Decisions 126 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

7 of 13 attended
AJ
Councillor Andrew JefferiesChair, present
DA
Councillor Deborah ArnoldDeputy Chair, present
AC
Councillor Adam CarterCommittee Member, present
GC
Councillor George CoxshallCommittee Member, present
BJ
Councillor Barry JohnsonCommittee Member, present
BM
Councillor Ben ManeyCommittee Member, present
GS
Councillor Graham SnellCommittee Member, present
MB
Mark BradburyOfficer, in attendance
AH
Asmat HussainOfficer, in attendance
SM
Steven MairOfficer, in attendance
SM
Sheila MurphyOfficer, expected
DS
Dr Dave SmithPublic, in attendance

All 13 on the meeting page

On this subject at Thurrock

Search all
  1. London Gateway Logistics Park Local Development Orders (Decision: 110677)This decision
  2. London Gateway Logistics Park: Consideration of Habitat Regulation Assessment (HRA) for Local Development Order 1.5Noted
  3. London Gateway Logistics Park Local Development OrderNoted
  4. London Gateway Logistics Park Local Development Order (Plot 2050)Noted
  5. London Gateway Logistics Park Local Development OrderNoted
  6. London Gateway Logistics Park Local Development OrderNoted

More from Thurrock Cabinet

All decisions
MeetingDecisionOutcome
16 Sep 2026 Corporate and Improvement Plan - 2025/26 Quarter 4 and End of Year Performance Report and Annual Report3.1 Cabinet Noted the quarterly Corporate Performance Report at Appendix 1 and consider which performance issues Cabi... Noted Open
16 Sep 2026 Thurrock Transport Strategy Adoption2.1 Cabinet approved the Thurrock Transport Strategy given in Appendix 1 to be progressed to Full Council for adoptio... Approved Open
16 Sep 2026 Proposed Changes to the Essex Coast Recreational Disturbance Avoidance and Mitigation Strategy (RAMS) and Tariff2.1 Cabinet approved the £476 RAMS tariff, as set out in section 9.1 of the Cabinet report; 2.2 Cabinet agreed to wit... Approved Open
16 Sep 2026 High Priority Housing Policies - Housing Adaptations Policy2.1 Cabinet agreed the Council’s Housing Adaptations Policy in Appendix 1 to commence with effect from 1 October 2026... Agreed Open
16 Sep 2026 Matrix Agency Worker 1 year contract extension2.1 Cabinet agreed to utilise the one-year extension option contained within the current contract and extend the exis... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies