Decision expected 20th June 2024, construction start 2026, completion 2032 at the earliest. · Cllr Speight noted there was not a date for the building of the pedestrian crossing. o Officers informed the Task Force that the document stated the pedestrian crossing would be constructed no later than 2026, there was nothing to suggest it could not be delivered sooner. · The Chair asked for an explanation on inadequate legacy provisions. o Of 22/23 items on legacy proposed by the Council only 5/6 were agreed by National Highways. · The Chair asked if there was any new information regarding emergency services. o All material before the Examining Authority. · The officers informed the committee the recommendations on the 20th March is not published until the Secretary of State’s decision. · Cllr Speight asked what would happen if a General Election was called in mid-2024. o If an election would be called a decision would be made after the election. · Co-Opted member Robert Quick noted there was a lot of work to do for the Local Authority to be ... view the full minutes text for item 18.
Word for word from the decision Thurrock published for this meeting.Source: democracy.thurrock.gov.uk
Accountable Director: Mark Bradbury – Interim Director of Place
This report is Public
Update
1.1The following sets out the key activities, events and submissions and the Council’s involvement in the DCO Examination, which began on 20 June 2023, following a Programming and Preliminary meeting on 16 May and 6 June 2023 respectively, which the Council attended, made submissions to and was represented. As a context, the Council made a number of submissions prior to the June Task Force meeting, which are set out below with weblinks.
1.2The Planning Inspectorate (PINS) website is the single source of truth for all DCO application documents and there are two important links: Main LTC Website showing all information and updates – Lower Thames Crossing | National Infrastructure Planning (planninginspectorate.gov.uk) PINS Examination Library containing all documents (updated regularly) – TR010032-001818-C - LTC Examination Library.pdf (planninginspectorate.gov.uk)
1.3The Submissions for the Programming and Preliminary meetings can be found on the Planning Inspectorate’s (PINS) website, as follows: Programming Meeting (16 May) – PDA-007
Preliminary Meeting (two submissions) (6 June) – PDB-009 and PDC-007
1.4In addition, the Council made submissions for Procedural Deadlines A, B and C on 5 and 26 May and 13 June 2023, which also can be found on the Planning Inspectorate’s (PINS) website, as follows:
Procedural Deadline A (PDA) (5 May) – as for the Programming Meeting above. Procedural Deadline B (PDB) (26 May) – as for the Preliminary Meeting above. Procedural Deadline C (PDC) (13 June) – PDC-008
1.5In addition, the Council also made two important submissions on 4 May 2023, prior to the Examination commencing – its Relevant Representation (PDA-009) and its Principal Areas of Disagreement Summary Statement (PADs) (PDA-008). 1.6 Finally, following the commencement by National Highways (NH) of its ‘Minor Refinement Consultation’ (MRC) (after acceptance by the Examining Authority (ExA) on 21 March 2023) on 17 May until 19 June 2023, the Council made its formal submission to NH on 19 June 2023, which were not published by PINS or NH.
1.7It should be noted that there were 12 Deadlines for written submissions from the commencement of the Examination on 20 June 2023 until its close on 20 December 2023. These deadlines were not missed but were regular and challenging.
19 June – 17 July 2023 (ISH 1 and 2 and Examination Commenced)
1.8The Council attended two Issue Specific Hearings (ISH1 and ISH2) on 21 and 22 June 2023, just after the commencement of the Examination, each lasting most of each day. The Council then made written submissions for each ISH at Deadline 1 (D1) on 18 July 2023, which summarised all its points for each ISH and which are set out below.
1.9The Examination commenced on 20 June 2023 and then the publication of the amended Rule 8 Letter was issued on 3 July 2023 by the ExA (TR010032-002408- LTC Rule 8 Letter and Annexes Amended APPROVED.pdf (planninginspectorate.gov.uk).
18 July – 14 August 2023 (Deadlines 1 and 2)
1.10Deadline 1 (D1) on 18 July 2023 was a major ExA deadline and the Council made four written submissions, which are set out below:
Local Impact Report (LIR) of 250 pages and its 13 Appendices – REP1-281 and REP1-282 – REP1-294 (the weblinks to which can be found in the Examination Library: TR010032-001818-C - LTC Examination Library.pdf (planninginspectorate.gov.uk)
ISH1 Submission – REP1-296
ISH2 Submission – REP1-295
Procedural Deadline D (PDD) – PDD-001
1.11It should be noted that NH made 216 written submissions at D1 and there were a total of 438 written submissions, including the Council’s submissions.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies