CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Thurrock Council
Lower Thames Crossing Task Force, Monday 19 February 2018 at 6.00pm

Lower Thames Crossing Task Force Priorities Update

Agreed Committee 1 paper

Lower Thames Crossing Task Force agreed this item on Monday 19 February 2018. Below is the council's own wording, with the papers it was decided on.

Item49

Resolved

It was agreed, at Councillor Jones’ request, that these priorities become a standing item as they may need to be reviewed as information emerged from Highways England.
Word for word from the decision Thurrock published for this meeting. Source: democracy.thurrock.gov.uk

Follow this further

Built from Thurrock's papers

What the report saysPro

Report to Lower Thames Crossing Task Force

Thurrock Lower Thames Crossing Task Force - Summary of Key Priorities

While Thurrock Council remains opposed to the proposed Lower Thames Crossing (LTC) being developed by Highways England in the Borough, as part of the response to the Preferred Route Announcement, Thurrock Council established a cross party ‘Lower Thames Crossing Task Force’ which included representation of local residents, the business community and the local action group opposing the scheme.

The following list captures some of the most frequently raised concerns, issues and priorities associated with the project to date. Thurrock Council and the Task Force remain opposed to the Highway England development of a crossing in this location. However the list below is intended to illustrate the real cost of the LTC on Thurrock and its communities and if Highways England take these seriously and factor the cost of remedy it will fundamentally affect the Business Case for the scheme. This can be read in conjunction with the Thurrock response to PINS.

It is without prejudice and those attending the Task Force will keep this list under review as and when HE provides additional information.

1. Business Case a. How much of this scheme is i. Time savings for trips already on the road network? ii. Real jobs and growth and how much of this will be in Thurrock? iii. Simply creating more journeys by car and longer trips? iv. If jobs was the highest priority (not a few minutes shaved off M25 journey times) how would this scheme compare to say a Crossing at Canvey? b. Who is to fund the entirety of the scheme? c. Tilbury Docks link road i. Is this confirmed as part of the core ‘funded’ project? ii. HE must design – for genuine consultation – a dual carriageway iii. There are notable views as to the relative merits of downgrading the A1089. What are HE proposals and how will HE manage this sensitivity. d. When can local contractors access all current and future HE contracts?

2. Involvement of Thurrock Council a. HE to commence full and detailed technical assessment with Thurrock Officers and how each and every scheme aspects is genuinely captured by HE and local harm fully mitigated and costed in their current understanding of their proposal. b. As a Nationally Significant Infrastructure Project HE must i. Accept that this scheme must be scrutinised in exactly the same manner as other NSIP’s such as Purfleet, Tilbury 2 etc. albeit the sheer scale, impact and potential lack of benefit to Thurrock makes this all the more concerning. ii. As developer, understand the full and significant impacts on Officer resources and democratic time and our ability to respond in advancing any Application of a DCO. 3. Alternatives to this proposal a. The Planning Inspectorate has demanded these be set out – when will HE share with Thurrock how they intend this respond? b. All the historic crossing capacity (1963, 1980, 1991). This crossing will last 120 years at least. Will there ever be anything other than more and more roads when there is a need to safeguard and future proof for alternatives modes.

4. What is the scheme and how will the network operate? a. When will we know the precise capacity of the crossing? This has already become 3 lanes through the tunnel, then up to the A13 but no detail thereafter. b. What is the capacity of the Tilbury Docks Link road and will the proposed design work? c. M25 / A2 Junction will be diversion point for the LTC; then back on to the M25. Can you prove that the entire network will be able to cope and that LTC does not simply create a new connection but with roads and junction either side at gridlock?

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Lower Thames Crossing Task Force Priorities UpdateReport 65 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

13 of 15 attended
PS
Councillor Peter SmithChair, present
GR
Councillor Gerard RiceVice-Chair, present
JA
Councillor John AllenCommittee Member, present
RJ
Councillor Roy JonesCommittee Member, present
TK
Councillor Tom KellyCommittee Member, present
SL
Councillor Steve LiddiardCommittee Member, present
BL
Councillor Brian LittleCommittee Member, present
BO
Councillor Bukky OkunadeCommittee Member, present
TP
Councillor Terry PiccoloCommittee Member, present
MJ
Matt JacksonCo-Optee, present
WM
Westley MercerCo-Optee, present
LM
Linda MulleyCo-Optee, present

All 15 on the meeting page

On this subject at Thurrock

Search all
  1. Lower Thames Crossing Task Force Priorities UpdateThis decision
  2. Lower Thames Crossing (LTC) Task Force ReportAgreed
  3. Lower Thames Crossing UpdateNoted
  4. Lower Thames Crossing Development Consent Order Update and Planning Performance Agreement (Decision: 110657)Approved
  5. Lower Thames Crossing Task Force Update Report (Decision: 110633)Noted
  6. Lower Thames Crossing - Delegation of Authority to Respond (Decision: 110622)Decided

More from Thurrock Lower Thames Crossing Task Force

All decisions
MeetingDecisionOutcome
22 Jan 2024 Final Update on DCO ExaminationDecision expected 20th June 2024, construction start 2026, completion 2032 at the earliest. · Cllr Speight noted ther... Noted Open
15 Oct 2018 Work ProgrammeIt was agreed that the mitigation schedule would be added to November’s Task Force meeting. Agreed Open
22 Jan 2018 Work ProgrammeIt was agreed that the Task Force Priorities would be added to the agenda for the next meeting, as previously suggest... Agreed Open
18 Dec 2017 Work ProgrammeIt was agreed that the Democratic Services Officer would request any additions Members wished to see, in addition to ... Agreed Open
16 Oct 2017 Work ProgrammeIt was agreed that 6pm was ideal for all Members and Co- Optees . The Task Force discussed the need for Highways Engl... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies