1.1 That the Committee provide comments on the 2024/25 Integrated Transport Block capital programme allocations and proposed prioritisation for the agreed policy areas of Road Safety Engineering, Safer Routes to Schools, Area Intervention Programme and Electric Vehicle Charging programme (as detailed in Appendix A). 1.2 Note and comment on the 2024/25 Highways Maintenance Block Allocation and Pothole Fund Programme (as detailed in Appendix B). 1.3 Note and comment that delegated authority will be given to the Interim Director of Transformation (Public Realm), in consultation with the Cabinet Member for Regeneration and Highways, to make any required changes to the ITB programme and the Maintenance programme, for 2024/25, within the overall programme budget, as well as other government funding allocations that may arise within the year to ensure delivery of the programme and to ensure the efficient ... view the full minutes text for item 37.
Word for word from the decision Thurrock published for this meeting.Source: democracy.thurrock.gov.uk
Report to Planning, Transport, Regeneration Overview and Scrutiny Committee
Executive summary
This report sets out how the Transportation Services team will prioritise the annual funding allocation from the Department for Transport (DfT) Integrated Transport Block Capital Programme (ITB). This funding is allocated to enable Thurrock Council to deliver identified policy improvements, infrastructure, and service provision within Thurrock in the 2024/25 financial year.
The report also sets out how the Highways DfT Maintenance Block Allocation and Pothole Fund for 2024/25 for the Highways Maintenance Service will be prioritised in alignment with Thurrock Council’s Highways Asset Management Strategy and the DfT’s Highways Maintenance Efficiency Programme.
Commissioner Comment:
Not Applicable
1. Recommendation(s)
1.1That the Committee provide comments on the 2024/25 Integrated Transport Block capital programme allocations and proposed prioritisation for the agreed policy areas of Road Safety Engineering, Safer Routes to Schools, Area Intervention Programme and Electric Vehicle Charging programme (as detailed in Appendix A).
1.2Note and comment on the 2024/25 Highways Maintenance Block Allocation and Pothole Fund Programme (as detailed in Appendix B).
Version - Final 1.3 Note and comment that delegated authority will be given to the Interim Director of Transformation (Public Realm), in consultation with the Cabinet Member for Regeneration and Highways, to make any required changes to the ITB programme and the Maintenance programme, for 2024/25, within the overall programme budget, as well as other government funding allocations that may arise within the year to ensure delivery of the programme and to ensure the efficient expenditure of the grant allocations.
2. Introduction and Background
2.1The DfT annual grant funding settlement provides the allocation for ITB schemes for the financial year. Thurrock Council’s ITB capital allocation for 2024/25 is £979,000. This funding is allocated to the capital schemes within the programme and staff time required to design, manage, and deliver the programme.
2.2The ITB programme has the ability to deliver an extensive range of transport improvements which reflect the vision and aims set out within the Council’s long term Transport Strategy and Vision.
2.3Delivery of the ITB programme ensures focus on the authority’s statutory requirement to reduce accidents, tackling congestion, delivering improved accessibility, and improving air quality through transportation measures.
2.4It is important that the ITB programme is aligned with the emerging Local Plan and the Transport Vision and Thurrock Transport Strategy (currently being developed) to ensure the effective use of the funding available to deliver necessary improvements to the transport network.
2.5To achieve this, it is important for the programme to have a clear policy direction. Agreed approaches already exist to inform policy, priority, and budget allocation. The existing agreed policy areas are:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Planning, Transport, Regeneration Overview and Scrutiny Committee at Thurrock and we tell you when its next papers are published, before the meeting rather than after it.
Regeneration Projects Update - to follow1.1 That the committee notes the proposed changes to the original programmes and the progress on delivering the Regen...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.