Resolved
1.1 That the Committee notes the proposed changes to the original programmes and the progress on delivering the Tilbury & Grays Towns Fund programmes.
Planning, Transport, Regeneration Overview and Scrutiny Committee decided this item on Wednesday 21 February 2024. Below is the council's own wording, with the papers it was decided on.
Resolved
1.1 That the Committee notes the proposed changes to the original programmes and the progress on delivering the Tilbury & Grays Towns Fund programmes.
This report is provided to update Members on progress on the delivery of the Tilbury Town Fund (TTF) and Grays Town Fund (GTF) programmes since the confirmation of funding from the Department of Levelling Up, Homes & Communities (DLUHC) in March 2023.
Commissioner Comment:
N/A
1. Recommendation(s)
That the Planning, Transport and Regeneration Overview and Scrutiny Committee:
1.1Notes the proposed changes to the original programmes and the progress on delivering the Tilbury & Grays Towns Fund programmes.
2. Introduction and Background
Tilbury
2.1Tilbury Town Investment Plan (TIP) has been developed as part of a wider strategic plan to revitalise Tilbury. The Plan focuses on creating a new Heart for Tilbury through the provision of a consolidated and inclusive Community Hub, new Education Zone and Youth Centre to provide first class facilities to address long standing calls for support for Thurrock’s residents, especially the younger population. The Station arrival experience and river frontage heritage
Version – Final assets will also be emphasised through improved connectivity through new signage, infrastructure, cycle ways and a new jetty is planned to open up new ferry passenger options. The Tilbury Towns Fund Board has been awarded a grant of £22.8m.
Grays Town Centre
2.2Grays Town Investment Plan (TIP) was developed as part of a wider strategic plan to realise the vision for Grays as an exciting, high-quality destination for communities to take pride, live, work, learn, shop and socialise. In essence, the Grays TIP aimed to create a high quality cultural and recreational amenity that reconnects the Thames riverfront with the town centre. The Grays Towns Fund Board has been awarded a grant of £19.9m.
3.0Programme Updates
3.1Details of the each of the Town Fund project programmes have been subject of Cabinet approval and previous reports to the PTR OS Committee.
3.2Business case summaries were submitted to the Department for Levelling Up Housing and Communities (DLUHC) in August 2022 (Tilbury) and October 2022 (Grays). There has been a significant delay in the confirmation of the business cases due for the need for further reassurance and assessment work on governance by the DLUHC and the Commissioners. Final approval was granted in March 2023.
3.3DLUHC released 5% of the respective funding allocations to allow Town Fund Boards to instruct the commencement of design work needed to bring forward the projects in both Town Fund Programmes. Projects are at varying stages of design which has been used to inform the production of business cases needed to secure the approval of the remaining funds from DLUHC.
3.4There has been significant cost price inflation since the submission of original Towns Fund applications for both Tilbury and Grays. The respective Town Boards have had to review the original programmes and where necessary make changes to ensure that projects can be delivered within the overall programme budget and not result in any financial liability falling to the Council as the Accountable Body.
Tilbury
3.5The Tilbury Towns Fund programme is making steady progress in delivery across a number of the projects, A summary of the main changes and milestones is provided below and a more detailed update of recent progress and future actions for the Tilbury Programme is set out in Appendix 1.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Tilbury Towns Fund presentation December 2023Appendix 1 | 8.8 MB | Download |
PDF |
Tilbury and Grays Towns Fund Update: to followReport | 115 KB | DownloadRead as text |
Follow Planning, Transport, Regeneration Overview and Scrutiny Committee at Thurrock and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 21 Feb 2024 | ITB Capital Programme 2024/251.1 That the Committee provide comments on the 2024/25 Integrated Transport Block capital programme allocations and p... | Agreed | Open |
| 21 Feb 2024 | Regeneration Projects Update - to follow1.1 That the committee notes the proposed changes to the original programmes and the progress on delivering the Regen... | Decided | Open |
| 17 Oct 2023 | Thurrock Scheduled Ancient Monuments: Assessment of Settings - April 2023That the Planning, Transportation and Regeneration Overview and Scrutiny Committee note and provide comment on the Th... | Decided | Open |
| 17 Oct 2023 | East Tilbury (Bata Village) & Corringham Conservation Areas Character Appraisal and Management Plans - April 2023That the Planning, Transport and Regeneration Overview and Scrutiny Committee notes and comments on the East Tilbury ... | Decided | Open |
| 17 Oct 2023 | Work ProgrammeThe following items be included on the work programme, briefing note on Coalhouse Fort, update on Stanford Le Hope Tr... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.