RESOLVED That Council approved: (a) the revised capital programme and 5-year capital programme for 2024/25 to 2028/29 as set out in this report (b) that the capital projects: currently “on hold” totalling £119.0m were not included in the Capital Programme and the associated borrowing of £62.9m was not required; the capital schemes that have not started totalling £3.3m were also formally confirmed as removed from the capital programme and the associated borrowing of £3.3m was not required and those schemes assessed and considered no longer necessary totalling £60.1m were confirmed as removed from the capital programme and the associated borrowing of £56.5m was not required (c) the proposed financing of the capital programme (d) delegation to the Interim Director of Finance s151, in consultation with Commissioners, all decisions surrounding the financing of expenditure within the revised capital programme, in a manner which achieves the most effective use of Council’s resources (e) that any future changes to the capital programme should be approved by Council, whilst ensuring that external funding was able to be used in a timely manner, with any new borrowing requirements subject to Commissioner approval (f) that the Capital Programme Board review and receive updates on the action plans put in place to address the further improvements identified and to note progress on continued delivery of these improvements.
Word for word from the decision Thurrock published for this meeting.Source: democracy.thurrock.gov.uk
This report sets out proposed changes to the Council’s capital programme from 2024/25 to 2028/29.
Capital investment plans are an integral part of the budget framework and of the financial planning process. The programme has been put together taking account of the Council’s financial position, the Government Directions and the Improvement and Recovery Plan (IRP) all underpinned by the need to reduce borrowing and the cost of borrowing on revenue budgets, especially the General Fund.
The preparation of the capital programme has included:
➢ a review of the previously approved programme to establish the base line
➢ reviews of the then current programme to establish what should no longer be included in the programme
➢ an extension of the programme to cover a 5 rather than 3 year period
➢ the identification of areas for improvement in the management of the programme
The capital programme approved by Full Council on 3 March 2023 envisaged capital spending totalling £202m over three years between 2023/24 and 2025/26. This budget had increased to £276m by the end of the first quarter of 2023/24, of which £155m was to be funded from borrowing and a further £121m from external funding. This increase is made up of capital budget carry forwards, capital budget deletions and new capital projects financed from external funding, informed by the outturn position for 2022/23. Appendix 1 provides a summary of the then revised capital programme.
In addition to the above previously approved bids totalling £119m were put “on hold” before March 2023 and not included in the capital programme of £202m. The funding of the £119m capital projects included £62.9m borrowing, £51.5m grants and £4.5m capital receipts. These are set out in Appendix 2, had these been included in the capital programme they would have added a further £119m to the £202m capital programme that was approved and to the £275m that it became.
The capital programme has been reviewed, formally removing £101.4m from the capital budgets, see Appendix 3, to:
➢ reduce capital expenditure to focus on existing contractual commitments, fulfilling statutory services and public safety requirement in line with the s.114 Notice
➢ reduce reliance on borrowing from £40.1m to £4.9m for the General Fund and from £115m to £96.2m for the HRA;
➢ formally remove the capital projects on hold of £119m with the associated borrowing of £62.9m
➢ formally remove the capital projects not yet started and deemed to be not required of £3.3m wholly funded from borrowing
Details of these proposed changes are set out in Appendix 4 showing capital schemes totalling £3.3m, and wholly funded from borrowing, not yet started and now considered not to be required and Appendix 5 showing schemes to be removed from the programme. Unaffected schemes i.e. those externally funded are shown in Appendix 6
To bring the Council’/s budget setting arrangements into line with CIPFA recommended practice, the current 3-year capital programme has been extended to 5 years as set out in Appendix 3.
In summary it is proposed that:
➢ total General Fund capital spending between 2024/25 and 2028/29 is limited to £115.8m, funded by £4.9m borrowing, £10.5m capital receipts, £100.4m external funding, and
➢ total HRA capital spending between 2024/25 and 2028/29 is set at £175.1m funded by £96.2m borrowing, £21.7m Right-to-Buy receipts and £57.2m from the use of Revenue Contributions to Capital.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.