Final Capital Programme 2026/27-2028/29 (including Capital Strategy)

Agreed Committee 6 papers

AI summaryThurrock Council has approved its final Capital Programme for 2026/27 to 2028/29, totalling £144.876m, with no new borrowing. Members backed the plan unanimously while calling for tighter accountability and removal of vanity projects.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeAgreedFinal Capital Programme 2026/27 to 2028/29
Money£144.876mTotal proposed programme for the three years
What happens nextQuarterly monitoring and reviewFurther tightening to remove vanity projects
Who it affectsCouncil assets and servicesInfrastructure, maintenance, health and safety works

What was decided

The Council unanimously approved the final updated and refreshed Capital Programme 2026/27 to 2028/29, summarised in Table 6 with full detail in Appendix D.

Members agreed the programme required further tightening and stripping back to remove vanity projects, and that improvements were needed on accountability and decision making.

Members stated the next administration must take responsibility for capital programme delivery more seriously, and that the community should be more involved and listened to.

Why

The Council is required by statute and the CIPFA Prudential Code to agree a capital programme and capital strategy that is prudent and sustainable. Report 6.1, P20

The programme is needed to maintain existing infrastructure, deliver health and safety benefits and compliance, and invest where it avoids higher revenue costs. Report P1, 5.11, P3

Existing budgets are based on the reported position at quarter 2 of 2025/26 and reflect the rationalisation carried out in the 2024/25 capital programme review. Report 8.2, P1

What happens next

Capital budgets will be reviewed as part of quarterly monitoring, with future adjustments including year-end carry forwards reported to Cabinet in the Revenue and Capital out-turn reports. Report 8.2

Each individual scheme will be approved in line with the Council's constitution, Contract Procedure Rules and Financial Regulations, and will be subject to a Community and Equality Impact Assessment. Report 11.2, P20

Procurement will only commence once funding is in place, and conditions attached to any funding must be strictly complied with to avoid repayment. Report P18, P20

The money

  • £144.876m Proposed total capital programme for 2026/27 to 2028/29 Report P10
  • £0.435m New capital bids (paragraph 5.2.1, Table 2) Report P11
  • £144.441m Net existing project expenditure rolling forward into the updated programme Report P11

Options considered

  • Chosen: Approve the final Capital Programme 2026/27 to 2028/29 and associated Capital Strategy. Required by statute and the CIPFA Prudential Code; no viable alternatives identified Report 6.1, P20
  • Rejected: Reject or amend the programme. No alternative options considered viable, as statute and the Prudential Code require agreement Report 6.1

Implications

  • Financial: No new borrowing, therefore no additional revenue costs; existing agreed capital budgets are based on the quarter 2 2025/26 position. Report 8.1, 8.2
  • Legal: The Council must have regard to the CIPFA Code of Practice on Treasury Management and the Prudential Code, and any conditions on funding must be strictly complied with to avoid repayment. Report P20
  • Risk: Key risks include programme slippage, affordability under the improvement and recovery plan, health and safety, maintenance backlogs, cost of borrowing and availability of funding, with mitigations set out in the report. Report 9.1, P15, P16, P17, P18
  • Equalities: No direct diversity implications noted; revisions will maintain essential services and public safety, with individual projects subject to Community and Equality Impact Assessments. Report 11.1, 11.2
  • Other: Procurement implications will be considered when approval is sought for particular schemes. Report 12.1

Who and where

  • Thurrock Council, as the body responsible for maintaining its capital base and delivering the programme Report P1, 8.1
  • Residents and the local community, in terms of services, infrastructure and future involvement Report 5.11, P3
  • The NHS and the Integrated Care Board, in respect of their use of Section 106 allocations
  • Executive Directors, their teams and commissioners, who have been consulted on the proposals Report 7.1, 7.2

Timeline

  • 27 November 2025: Risk implications verified by Janki Patel, Risk Manager Report P18
  • 4 December 2025: Equality and Diversity implications verified by Natalie Smith, Head of Community Development Report P25
  • 5 December 2025: Legal and Governance implications verified by Helen Nicol, Assistant Director Legal and Governance Report P21
  • 23 January 2026: Financial implications verified by Mark Terry, Capital Finance Manager Report P13
  • 25 February 2026: Council meeting at which the final Capital Programme was approved unanimously

Plain English for the jargon

  • CIPFA Prudential Code: The Chartered Institute of Public Finance and Accountancy's Code governing local authority capital finance, requiring a prudent and sustainable capital strategy.
  • Section 106 funds: Planning obligation payments from developers towards infrastructure and services, secured under Section 106 of the Town and Country Planning Act 1990.
  • ICB: Integrated Care Board, the NHS body responsible for planning and funding local health services in an area.
  • Capital Overview Board: A monthly monitoring and challenge forum set up to strengthen oversight of the capital programme.
  • Improvement and recovery plan: The commissioners' approved framework under which the Council is managing its finances and operations.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item60

Resolved

Agreed that to support as capital programme was necessary, improvements must be made on accountability and decision?making. · Stated the next administration must take this responsibility far more seriously and ensure we do better. · No proper representation on the board so local voices can be heard and working to get it into a position where the community can support. · One positive step taken by this administration was unlocking long?held Section 106 funds. · Thanked officers for the work undertaken, the council now had funding to begin delivering projects, hold the NHS and ICB to account for failing to use their own Section 106 allocations. · Acknowledged lots more to do done. · Community to be more involved and listened to. · Agreed there was still much more to do with the programme requiring further tightening and stripping back to remove vanity projects. · Portfolio Holder stated she was pleased with the progress made so far and fully supported the need for continued improvement. Members voted unanimously in favour of the recommendation. RESOLVED Approved the final updated and refreshed Capital Programme, 2026/27 to 2028/29, summarised in Table 6 with full detail in Appendix D.
Word for word from the decision Thurrock published for this meeting. Source: democracy.thurrock.gov.uk

Follow this further

Built from Thurrock's papers

What the report saysPro

Report to Council

Report to Council Report Title Final Capital Programme 2026/27 to 2028/29

Date of Meeting 25 February 2026

Report Author John Chance, Chief Accountant

Corporate Director Dawn Calvert, Chief Finance Officer (S151 Officer)

Lead Cabinet Member(s) Cllr Valerie Morris-Cook, Cabinet Member for Resources Why is this a key 1. Expenditure over £500K decision? 2. Significant impact on 2 or more wards

Wards Affected (All Wards);

Identify exempt Choose an item. information and exemption category N/A

Is report Urgent? No

Reasons for urgency (only where applicable)

Appendices (if any) Appendix A – Current Capital Programme and Funding to 2028/29 Appendix B – Projects removed from the Capital Programme Appendix C – Capital Schemes requiring alternative funding from Capital Receipts 2025/26 Appendix D – Final 3-year programme and funding 2026/27 to 2028/29 Appendix E – Capital Strategy 2026/27

1 1. Executive Summary

1.1Cabinet reviewed the Final Capital Programme 2026/27 to 2028/29 at its meeting on 18 February 2026, recommending the report be considered by Council for approval. Any changes made at the Cabinet meeting, will be reported via a supplementary report to Full Council. 1.2 This report sets out proposed changes to the Council’s Capital Programme. The Capital Programme is aligned to the medium-term financial plan, acknowledging that the last year, 2028/29, falls within the first year of the unitary arrangements under Local Government Reorganisation, if current timelines are adhered to. 1.3 The report also covers additions to the Capital Programme and the funding sources associated with them and highlights a number of changes proposed as a result of the refresh exercise carried out, including financing alterations and project removals. 1.4 The Capital Strategy sets out the strategic framework underpinning capital expenditure and the associated financing of the Capital Programme (Appendix E). 1.5 During the refresh process additions to the Capital Programme were limited to the following four categories:

• Health and Safety: to enhance safety standards or mitigate potential health and safety risks. • Return on investment proposals linked to MTFS savings. • Essential and non-avoidable maintenance and replacement of assets linked to cost avoidance. • Other additions that demonstrate benefits may be approved on a case-by- case basis. 1.6 The following table highlights the changes from the current year, 2025/26, to the final year of the current programme, 2028/29, and summarises the changes for the general fund, the details of which are covered within this report:

2 Table 1 Capital Programme with agreed changes 2025/26 - 2028/29 2025/26 2026/27 2027/28 2028/29

£m £m £m £m General Fund 120.120 30.339 10.423 8.370 Housing Revenue Account 60.968 29.060 29.911 22.259 Total 181.088 59.399 40.334 30.629

Proposed Adjustments to the Programme: Update to DFT Grants 2.891 5.107 6.406 New projects added (funded by external borrowing) 0.435 Removal - projects funded by capital receipts (0.124) (0.225) (0.050) (0.050) Removal - projects funded by external borrowing (0.286) Removal - projects funded by government grants (1.229) Sub-total (1.639) 3.101 5.057 6.356

Revised Draft Capital Programme: General Fund 118.481 33.440 15.480 14.726 Housing Revenue Account 60.968 29.060 29.911 22.259 Total 179.449 62.500 45.391 36.985

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Current Capital Programme and Funding to 2028-29Appendix A 82 KB Download
PDF
Projects Removed from the Capital ProgrammeAppendix B 6 KB Download
PDF
Capital Schemes requiring alternative funding from Capital Receipts 202526Appendix C 6 KB Download
PDF
Final 3-year Programme and Funding 2026-27 to 2028-29Appendix D 21 KB Download
PDF
Capital Strategy 2026-27Appendix E 70 KB Download
PDF
Final Capital Programme 2026/27-2028/29 (including Capital Strategy)Report 204 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

42 of 63 attended
SS
Councillor Sue ShinnickMayor, present
SL
Councillor Steve LiddiardDeputy Mayor, present
QA
Councillor Qaisar AbbasCommittee Member, present
NA
Councillor Ngozi AlikeCommittee Member, present
JA
Councillor John AllenCommittee Member, present
AA
Councillor Alex AndersonCommittee Member, present
DA
Councillor Deborah ArnoldCommittee Member, apologies
PA
Councillor Paul ArnoldCommittee Member, apologies
AB
Councillor Alan BensonCommittee Member, present
GB
Councillor Gary ByrneCommittee Member, present
RB
Councillor Ross ByrneCommittee Member, apologies
JC
Councillor John CecilCommittee Member, present

All 63 on the meeting page

On this subject at Thurrock

Search all
  1. Final Capital Programme 2026/27-2028/29 (including Capital Strategy)This decision
  2. Final Capital Programme 2026/27 to 2028/29Approved
  3. Final Capital Programme Report 2025-2026 to 2029-2030Approved
  4. Final Capital Programme 2025-26Noted

More from Thurrock Council

All decisions
MeetingDecisionOutcome
30 Sep 2026 Revised Political BalanceRESOLVED Agreed the political balance and allocation of seats, as set out in Appendix 1. Agreed Open
30 Sep 2026 Councillors’ Code of Conduct - Appointment of Independent Persons under s.28 of the Localism Act 2011RESOLVED Authorised the monitoring officer to commence the recruitment of up to three independent persons under s.28 ... Noted Open
30 Sep 2026 Corporate Parenting Committee Annual Report 2025-2026RESOLVED That the contents of the Corporate Parenting Annual Report 2025/2026 were noted. Noted Open
30 Sep 2026 Constitution Review: Key Decision ThresholdRESOLVED For the reasons set out in this report, Full Council is recommended to agree: 2.1 To adopt the amendments to... Agreed Open
30 Sep 2026 Constitution Review: Council and Executive Rules and ProceduresRESOLVED 2.1 For the reasons set out in this report, Full Council is recommended to approve the following re-drafted ... Approved Open