1.1 Cabinet approved the procurement approach via the Procurement for Housing framework to source a supplier for the Gas Servicing Contract for a maximum period of two years. 1.2 Cabinet approved Delegated Authority to the S151 Officer and Executive Director of Place, in consultation with the Portfolio Holder for Health and Wellbeing, for the direct award of the contract to Aaron Services Ltd. 1.3 Cabinet is requested to approve expenditure of up to £4.4 million Plus VAT over the term of the contract. Reason for the decision: as outlined in the report The decision is subject to call-in
Word for word from the decision Thurrock published for this meeting.Source: democracy.thurrock.gov.uk
Report to Cabinet Report Title Procurement and Award of Contract for Gas Servicing, Breakdown and Repair for Housing Date of Meeting Wednesday, 13 November 2024
Report Author Head of Assets, Repair and Compliance – Alastair Wood Corporate Director Executive Director Place – Claire Demmel
Lead Cabinet Member(s) Cabinet member for Health and Wellbeing
Why is this a key 1. Expenditure over £500K yes decision? 2. Significant impact on 2 or more wards yes
Wards Affected (All Wards);
Is report Urgent? No
Appendices (if any) N/A
1. Executive Summary The Domestic Gas Servicing, Breakdown, and Repair Contract will expire on 28th February 2025. To ensure the Council continues to meet its regulatory obligations regarding gas servicing and to address breakdowns and repairs, a new procurement and contract award is required. This report recommends a direct award via a housing sector procurement framework to mitigate any service and regulatory risks to Thurrock Council and to ensure there is no disruption to service provision from 1st March 2025. This recommendation is made in view of the change in approach regarding how these services were to be delivered under the previously proposed Housing Strategic Delivery Partner model. Following the termination of the procurement exercise the Council must ensure it continues to deliver works and services to maintain residents’ homes for their safety and well-being. Therefore, this approach for a direct award is viewed as an essential interim arrangement while the Council further evaluates future service delivery models. The proposed contract duration for this commission is a maximum of 2 years on a 1+1-year basis, starting from 1st March 2025. This approach will give the Council the necessary time to select, procure, and mobilise a longer-term service delivery approach covering these essential services. The proposed contract is considered an interim arrangement for a maximum period of two years, providing the Council with additional time to consider, evaluate, and procure a future service delivery model for housing service. The Council is aiming to start the new tendering exercise early next calendar. This future model will include the servicing, repairs, and installation of gas-fired systems, covering both domestic and commercial heating and hot water system for the social housing portfolio and other commercial Council assets. This additional time will help ensure that the future service delivery approach aligns with the needs and priorities of the Council and its residents. The duration of the contract will remain solely at the Council's discretion. Recommendations For the reasons set out in this report, the Cabinet is recommended to: 1.1 Cabinet is requested to approve the procurement approach via the Procurement for Housing framework to source a supplier for the Gas Servicing Contract for a maximum period of two years. 1.2 Cabinet is requested to approve Delegated Authority to the S151 Officer and Executive Director of Place, in consultation with the Portfolio Holder for Health and Wellbeing, for the direct award of the contract to Aaron Services Ltd. 1.3 Cabinet is requested to approve expenditure of up to £4.4 million Plus VAT over the term of the contract.
Commissioner’s Comments 1.4 The Commissioners have seen the report and made no comments.
2.0Introduction and Background
2.1The current domestic Gas Servicing, Breakdown and Repair contract was procured and awarded in 2019 to Aaron Services Ltd following a restricted tender process in accordance with Public Contracts Regulations 2015 (PCR 2015). The Council utilised the contractual extension options to extend the contract in 2022 by two years to run to March 2024. The contract was further extended for a year to 28th February 2025 whilst Thurrock Council pursued the procurement of a Partnership Delivery Model for Housing works. The last extension was permissible under Public Contract Regulations 2015 regulation 72.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Thurrock Transport Strategy Adoption2.1 Cabinet approved the Thurrock Transport Strategy given in Appendix 1 to be progressed to Full Council for adoptio...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.