Q3 Forecast Revenue and Capital Outturn Report- Place Directorate Services
NotedScrutiny3 papers
Place Overview and Scrutiny Committee noted this item on Thursday 20 March 2025. Below is the council's own wording, with the papers it was decided on.
RESOLVED That the Place Overview and Scrutiny Committee: 1. Noted and comment on the Place Directorate’s projected overspend position of £0.764m at Quarter 3, as per Section 4.1.1. 2. Noted and comment on the Place Directorate’s savings delivery for 2024/25 against the target, as per section 4.1.5. 3. Noted and comment on the General Fund Capital position at Quarter 3, as per Section 4.4 and Appendix 1 of this report, which shows anticipated slippage of £6.031m against a budget of £21.913m. 4. Noted and comment on the HRA Capital position at Quarter 3 which shows the anticipated release of funding from schemes of £5.5m against a budget of £44.099m, as per Section and Appendix 2 of this report.
Word for word from the decision Thurrock published for this meeting.Source: democracy.thurrock.gov.uk
Report to Place Overview and Scrutiny Committee Report Title Q3 Forecast Revenue and Capital Outturn Report- Place Directorate Services Date of Meeting 20th March 2025
Report Author Sima Khiroya, Assistant Director Financial Management & Procurement Corporate Director Dawn Calvert, Chief Financial Officer S151
Lead Cabinet Member(s) Cabinet Member for Resources
Wards Affected (All Wards);
Identify exempt Choose an item. information and exemption category n/a
Appendices (if any) 1. General Fund Capital Monitoring 2024/25 – Quarter 3 (Place Services) 2. HRA Capital Monitoring 2024/25 Quarter 3
1. Executive Summary 1.1 This report sets out the estimated forecast revenue outturn position for 2024/25 for the Place Directorate, including the Housing Revenue Account (HRA) at Quarter 3.
1.2The report provides an update on delivery against the savings targets for 2024/25 for the Place Directorate at Quarter 3.
1.3An update on progress against the General Fund and HRA Capital Budgets for 2024/25 at quarter 3 are provided.
2. Recommendations For the reasons set out in this report, the Committee is recommended to: 2.1 Note and comment on the Place Directorate’s projected overspend position of £0.764m at Quarter 3, as per Section 4.1.1. 2.2 Note and comment on the Place Directorate’s savings delivery for 2024/25 against the target, as per section 4.1.5. 2.3 Note and comment on the General Fund Capital position at Quarter 3, as per Section 4.4 and Appendix 1 of this report, which shows anticipated slippage of £6.031m against a budget of £21.913m. 2.4 Note and comment on the HRA Capital position at Quarter 3 which shows the anticipated release of funding from schemes of £5.5m against a budget of £44.099m, as per Section and Appendix 2 of this report.
3. Commissioner’s Comments 3.1 Commissioners’ comments will be included in the full quarter 3 report to Cabinet on 19th March 2025.
4. Proposals – the rationale and evidence for the recommendations
4.1Revenue Position at Quarter 3 Place 4.1.1 The Place Directorate position at quarter 3 is forecast expenditure of £45.384m against a budget of £42.848m, and after transfer from reserves of £1.772m, is reporting an overspend position of £0.764m (1.8%). This is a reduction of £1.155m on the quarter 2 position, as shown in Table 12.
4.1.2 The reduction between quarter 2 and 3 has been achieved by a detailed review of all forecasts across all service areas in the Place Directorate and a restatement to reflect the position anticipated at the financial year-end, including reductions in projected expenditure and increases in projected income to align to actual expenditure and taking into account known changes during quarter 4.
Table 1: Place Directorate Summary Revenue Position Quarter 3 4.1.3 The main adjustments are being driven by forecast underspends in staffing costs (£0.512m), increased income generation (£0.270m), reduced transport related costs across the directorate (£0.153m), reduced Waste contract disposal spend (£0.095m) and various underspends across the service (£0.124m).
4.1.4 Temporary Accommodation is the most significant budget pressure on the Homelessness Service within the Place Directorate. The pressure at quarter 3 is £2.485m before transfers from earmarked reserves of £0.293m. The revision of forecast increases in the net number of new households per month, which was made during quarter 2, has transpired in actual numbers being tracked, as shown in Figure 1.
4.1.5 To offset the pressures in Homelessness, a transfer from the Public Health Contain Outbreak Management Fund (COMF) Grant will be utilised at the year-end from reserves in the amount of £0.965m. This is being shown separately within the Council’s overall revenue position, and outside the Place service pressures in Table 1 above. Despite being projected at the full value, the actual use of this reserve will be dependent upon the final outturn position of the Place directorate.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.