Decision Notice D170063MEM The report of the Director of Street Scene, Leisure and Technical Services set out details of the content of Phase 9 of the Parking Action Plan. The report highlighted a proposal to change the current procedure for changes to parking restrictions to follow the process adopted for Traffic Regulation Order consultations. Details of the consultation process for the Phase 9 Parking Action Plan were set out in Annex 1 to the report while Annex 2 contained details of the locations for future phases. Additionally, it was noted that parking reviews in respect of Kings Hill, Hildenborough and Hadlow would be progressed separately to the Phase 9 sites. RECOMMENDED: That (1) the list of locations identified in Annex 1 to the report be taken forward for investigation and informal consultation as Phase 9 of the Parking Action Plan; (2) the Parking Action Plan be extended to incorporate the locations included in Annex 2 to the report and funding be sought in the review of the Borough Council’s Capital Plan; (3) the revised process for considering changes to parking restrictions as outlined in the report be adopted; and (4) the Parking Reviews for Kings Hill, Hildenborough and Hadlow be progressed.
Word for word from the decision Tonbridge and Malling published for this meeting.Source: democracy.tmbc.gov.uk
Report of the Director of Street Scene, Leisure & Technical Services Part 1- Public
Matter for Recommendation to Borough Cabinet - Non-Key Decision (Decision may be taken by the Cabinet Member)
1 PARKING ACTION PLAN
Summary The Borough Council has for many years divided requests for changes to parking restrictions into separate Phases of the “Parking Action Plan”.
This report covers the content of the next Phase (Phase 9) of the Action Plan and also reports on the future extension of the Parking Action Plan to enable further Phases.
1.1Current/Future Phases
1.1.1 The list of locations recommended for consideration in Phase 9 (2017/18) of the Parking Action Plan is shown in Annex 1. A further list of requests is shown in Annex 2, for consideration in future plans.
1.1.2 The process for dealing with the future locations in Annex 2 needs to be considered. These requests for parking restrictions and changes to existing controls will require an extension to the Parking Action Plan and associated funding will be sought through the forthcoming review of the Capital Plan.
1.2Current Procedure
1.2.1 The current procedure for promoting changes to parking restrictions is as follows
Request received and added to waiting list. Sites collated into manageable phases Approval for the next phase reported to Joint Transportation Board with recommendation to move to informal consultation. Report to Joint Transportation Board on the outcome of informal consultation with recommendation to alter/adjust proposals and to move to formal consultation. Report to Joint Transportation Board following formal consultation with recommendations to approve/abandon proposals. Install approved schemes. As required the review of proposals after 12 months.
JTB - Part 1 Public 25 September 2017 2
1.3Proposed Change to Procedure
1.3.1 Kent County Council has adopted a different approach to Traffic Regulation Order consultations. Its process differs in that when less than 5 objections to proposals are received during a formal consultation process; the consideration of those objections can be done by the County’s Cabinet Member for Highways, rather than be reported for consideration to the relevant Highways Advisory Board.
1.3.2 Where there are no objections, the proposal proceeds for implementation.
1.3.3 This has helped streamline the processes involved in making changes to Traffic Regulation Orders.
1.3.4 It is suggested that the Borough Council look to adopt a similar process when considering the following specific circumstances and where proposals have received less than 5 valid objections at the formal consultation stage.
Introduction and removal of Disabled Persons Parking Facilities Amendments to restrictions following the installation of driveways Amendments to restrictions following changes to highway layout.
1.3.5 This consultation and decision could be then considered by the Chair of the Joint Transportation Board, in conjunction with the appropriate local Borough and County Member(s). Any decisions made by the Chair would be reported as an “information” item to the following Board.
1.3.6 Where a proposal attracts 5 or more objections then the matter would remain for the Board to consider in the normal manner.
1.3.7 Where a proposal receives no objections, the proposals should again proceed, but be reported as an information item to the next Board.
1.4Phase 9 Consultation
1.4.1 Subject to Member comment it is proposed that the 27 sites and associated proposals in Annex 1 should now be taken forward for investigation and then to informal consultation.
1.4.2 The response to the informal consultation will be reported back to the November meeting of the Board, prior to progressing to formal consultation.
1.5Parking Reviews
1.5.1 Separate to the Phased approach taken for some sites, we will be progressing the following areas as parking reviews.
Kings Hill Hildenbough Hadlow
JTB - Part 1 Public 25 September 2017 3
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Joint Transportation Board at Tonbridge and Malling and we tell you when its next papers are published, before the meeting rather than after it.
Parking Action Plan, Access Group 9That the decision of the Cabinet Member for Transformation and Infrastructure to set aside the objections attached at...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.