Resolved
That the report be received and noted.
Joint Transportation Board noted this item on Monday 25 September 2017. Below is the council's own wording, with the papers it was decided on.
Resolved
That the report be received and noted.
To: Tonbridge and Malling Joint Transportation Board
By: KCC Highways and Transportation
Date: 25th September 2017
Subject: Highway Works Programme 2017/18
Classification: Information Only
Summary: This report updates Members on the identified schemes approved for construction in 2017/18
1. Introduction
This report provides an update and summarises schemes that have been programmed for delivery in 2017/18
Footway and Carriageway Improvement Schemes – see Appendix A
Drainage Repairs & Improvements – see Appendix B
Street Lighting – see Appendix C
Transportation and Safety Schemes – see Appendix D
Casualty Reduction Measures – see Appendix D1 Integrated Transport Schemes – see Appendix D2 Local Growth Fund – see Appendix D3 Third Party Funded Schemes – see Appendix D4
Developer Funded Work – see Appendix E
Section 278 Works – see Appendix E1 Section 106 Works – see Appendix E2
Bridge Works – see Appendix F
Traffic Systems – see Appendix G
Combined Member Fund – see Appendix H
Conclusion
1. This report is for Members information. Contact Officers:
The following contact officers can be contacted on 03000 418181
Kirstie Williams Mid Kent Highway Manager Mark Simmons Tonbridge & Malling District Manager Alan Casson Senior Asset Manager Sue Kinsella Street Light Asset Manager Toby Butler Traffic & Network Solutions Asset Manager Katie Moreton Drainage & Structures Asset Manager Jamie Hare Development Agreement Manager Jamie Watson Senior Schemes Programme Manager Appendix A – Footway and Carriageway Improvement Schemes
The delivery of these schemes is weather dependent; should it prove not possible to carry out these works on the planned dates, new dates will be arranged and the residents will be informed by a letter drop to their homes.
Surface Treatments - Contact Officer Jonathan Dean
Micro Surfacing Road Name Parish Extent of Works Current Status
From the junction with Programmed to Woodgate Road Ryarsh Trottiscliffe Road to the commence on 05/10/17 junction with The Street. for 4 working days. The entire length, from the Programmed to junction with Woodgate Road The Street Ryarsh commence on 05/10/17 to the junction with Birling for 4 working days. Road. The entire length, from the Programmed to Birling Road Ryarsh junction with The Street to the commence on 05/10/17 junction with Ryarsh Road. for 4 working days. From the junction with Birling Programmed to Ryarsh Road Ryarsh Road to the junction with Bull commence on 05/10/17 Road. for 4 working days. From the reservoir to the Church Road Offham junction with Teston Road, Completed including North Meadow. From the junction with the Court Lane Hadlow A26 Maidstone Road to the Completed junction with Cemetery Lane. From the junction with A26 Hadlow Road Tonbridge Higham Lane to the junction Completed with Cannon Lane. From the junction with A26 Quarry Hill Road Tonbridge Pembury Road to the A21 Completed overbridge. From the junction with B2021 East Street Tonbridge Bordyke to the junction with Completed the High Street. From its junction withVale Programmed to Sovereign Way Tonbridge Road to the junction with commence on 03/10/17 Medway Wharf Road. for 2 days. From its junction with The Swanton Valley Lane West Peckham Hurst to the junction with Stan Completed lane. Entire Length, form its Programmed to Woodview Crescent Hildenborough junction with Brookmead to commence on 16/10/17 the junction with Elm Grove. for 1 day.
Martin Hardie Way Tonbridge Whole road To Be Programmed
Aldon Lane Addingon Whole Road To Be Programmed
Easterfields Lane East Malling From junction with Rocks To Be Programmed Road to Railway Bridge
Surface Dressing Entire Length of Hatches Lane to include Court Lane Hatches Lane East Peckham from its junction with Completed. Cemetery Road to Hatches Lane.
From its junction with South Ash Road Stansted Stansted Lane to the junction Completed with Pease Hill.
From the bus stop to the B245 North of Mill Lane to the Hildenborough Completed London Road junction with Noble Tree Road.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Tonbridge and Malling Highway Works ProgrammeReport | 145 KB | DownloadRead as text |
Follow Joint Transportation Board at Tonbridge and Malling and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 2 Dec 2024 | Parking UpdateThat the current progress and approach to the Parking Team’s work programme, be noted. | Noted | Open |
| 2 Dec 2024 | Parking Action Plan, Access Group 9That the decision of the Cabinet Member for Transformation and Infrastructure to set aside the objections attached at... | Noted | Open |
| 17 Jun 2024 | Scope of the Joint Transportation Board and local/public transportThat consideration be given to the scope of the Joint Transportation Board at the next meeting. | Decided | Open |
| 21 Nov 2022 | Proposed Single Yellow Line Waiting Restrictions - Oldbury LaneThat the Traffic Regulation Order for double yellow lines be implemented on Old Lane Only, as shown in the plan at Ap... | Decided | Open |
| 6 Jun 2022 | Proposed 40mph Speed Limit - B2016 Seven Mile Lane, MereworthThat the 40mph speed limit on the B2016, Seven Mile Lane, be implemented as shown on the plan at Appendix D to the re... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.