Resolved
Decision Notice D180025CAB
Cabinet decided this item on Tuesday 20 March 2018. Below is the council's own wording, with the papers it was decided on.
Resolved
Decision Notice D180025CAB
1.1.1 A List C project for evaluation is currently in the Council’s Capital Plan for improved facility provision at Leybourne Lakes Country Park. The scheme identifies potential improvements to include the provision of an education room/facility, general improvements to the water sports facilities/area and the provision of a café. Developer contributions of just over £700,000 are currently held by this Council specifically to support onsite developments.
1.1.2 Highlighted within the Council’s Savings and Transformation Strategy, is the theme of ‘Income Generation and Cost Recovery’. With Leybourne Lakes Country Park being a discretionary service, this theme needs careful consideration in relation to the facility, with a long-term ambition for the Country Park to be financially more self-sufficient. Any such considerations need to be balanced with the nature of the Park and its core objectives, as reflected in the Park’s recently approved Management Plan.
1.1.3 Initial advice on the business case for facility development at the site was sought from a leading leisure and sport business consultant, Oaks Consultancy. The Oaks report supported the Council’s initial view that facility development is required and viable, and Members agreed that Oaks be appointed to assist the Council in the business/financial appraisal of options linked to capital investment. The Oaks report also clearly recognised that direct delivery by the Council in the future might not offer the best outcomes in terms of improvements, investment and financial return. Oaks strongly recommended that the Council should consider the external outsourcing of the management of Park in accordance with a clearly defined Management Agreement. Oaks believe this will be the best option to deliver an enhanced customer offer and financial saving to the Council.
Cabinet NKD - Part 1 Public 20 March 2018 2
1.1.4 At the meeting of the Communities & Housing Advisory Board on the 13 November 2017 Members agreed to further explore the external management of the Park through a formal procurement process. This report brings forward details of this process for Members consideration and approval specifically focusing on the following:
Procurement
Heads of Terms
Evaluation Criteria
Timeframe
1.2Procurement
1.2.1 The Council’s Contract Procedure Rules will need to be adhered to and liaison has been undertaken with the Director of Central Services in this regard. It has been confirmed that a full EU Tender will be required and that this opportunity would be tendered as a ‘Concession’.
1.2.2 It is worthy of note that progressing with a procurement exercise will not commit this authority to a new way of managing and developing LLCP, but it will enable Members to consider and evaluate costed proposals from prospective partners, and compare these to other options.
1.3Heads of Terms
1.3.1 As highlighted at sub-section 1.1.3 it is proposed that any external management would be agreed and undertaken in accordance with a formal Management Agreement, similar to the approach already adopted for the Council’s Indoor Leisure Facilities. The Management Agreement would form a key part of the tender pack and will be guided by approved Heads of Terms. In order to inform the Heads of Terms, consultation has been undertaken with key stakeholders.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
18/28Appendix 1 | 49 KB | Download |
PDF |
18/28Appendix 2 | 65 KB | Download |
PDF |
18/28Appendix 3 | 409 KB | Download |
PDF |
Leybourne Lakes Country Park: Development OpportunitiesReport | 78 KB | DownloadRead as text |
Follow Cabinet at Tonbridge and Malling and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 1 Sep 2026 | MinutesThat the of the meeting of the Cabinet held on 30 June 2026 be approved as a correct record and signed by the Chairman. | Approved | Open |
| 1 Sep 2026 | Local Government Reorganisation - Establishment of West Kent Joint CommitteeRESOLVED : That (1) the Secretary of State’s decision to proceed with four unitary councils for Kent and Medway, as s... | Noted | Open |
| 1 Sep 2026 | Budgetary Control 2026/27 to July 2026RESOLVED : That (1) the net favourable variance of circa £66,093 as at the end of July 2026, when compared to the pro... | Noted | Open |
| 1 Sep 2026 | Risk ManagementRESOLVED : That (1) the updates to the Strategic Risk Register since the last iteration, with particular emphasis on ... | Noted | Open |
| 1 Sep 2026 | Artificial Intelligence Governance Framework PolicyRESOLVED : That (1) the , attached at Annex 1, be approved for adoption and implementation; (2) the establishment and... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.