AI summaryCabinet notes updates to the Strategic Risk Register, keeping failure to adopt a Local Plan and local government reorganisation in Kent as red risks, with development management decisions now considered reduced.
Written from the decision and the officer reportPDF Pro
OutcomeNotedTwo red risks retained, one reduced
MoneyNot stated
What happens nextOngoing risk management and monitoringService risks reported at each meeting
Who it affectsCouncil-wide risk managementAll services and major projects
What was decided
Cabinet noted the updates to the Strategic Risk Register, with emphasis on red risks shown in Annexes 1 and 1a. Report P8
Cabinet noted the service risks identified in Annex 2. Report P9
Why
The identification, evaluation and cost-effective control of risks is essential in safeguarding the Council's assets, employees, customers and service delivery. Report 2.2, 4.2
Risks are assessed using a 5x5 risk matrix adopted in October 2025, with red risks scoring 15 to 25 escalated to the Strategic Risk Register. Report 5.2, 5.4
Failure to adopt a Local Plan and Local Government Reorganisation in Kent remain at high or red risk despite mitigations in place. Report 6.7, P34, P35
What happens next
The Strategic Risk Register will continue to be updated as a live document by the Management Team. Report 6.1
Service Management Teams will continue to raise amber risks and consider red risks for escalation to the Strategic Risk Register. Report 5.3, 5.4
A schedule of ongoing and newly identified service risks will be reported to future meetings of this Committee. Report 7.1, 7.2
Options considered
Chosen: Retain failure to adopt a Local Plan as a red risk. Despite mitigations, risk remains high Report 6.7, P34
Chosen: Retain Local Government Reorganisation in Kent as a red risk. Despite mitigations, risk remains high Report 6.7, P35
Chosen: Reduce Development Management Decisions risk. The Director of Planning, Housing and Regulatory Services considers risk has reduced following clarification on determination matters Report 6.6
Chosen: Add risk of partner or contractor failure on major projects. Management Team felt external partner failure on major schemes could expose the council to reputational and financial risk Report 6.5
Implications
Legal: There is a Health and Safety requirement for effective risk management, and the Accounts and Audit Regulations require that risk is appropriately managed. Report 10.1, 10.2
Financial: Financial issues arising in mitigating risk will be managed within existing budget resources or reported to Members if this is not possible. Report 8.1
Risk: Red risks include failure to adopt a Local Plan and Local Government Reorganisation in Kent, while a new risk covering partner or contractor failure on major projects has been added. Report 6.5, 6.7, P34, P35
Equalities: The decisions recommended have a remote or low relevance to the Equality Act, with no perceived impact on end users. Report P50
Governance: The Council exercises a prudent approach to risk taking within the parameters of its internal control arrangements, including the Constitution and Procedural Rules. Report 2.3, 4.3
Who and where
Council assets, employees and customers Report 2.2, 4.2
Service Management Teams and Management Team Report 5.3, 5.4
Major project partners and contractors Report 6.5
Local community receiving council services Report 2.2
Timeline
September 2025: Risk Management Strategy endorsed by Cabinet Committee Report 4.4
28 October 2025: Risk Management Strategy adopted by Full Council; 5x5 risk matrix and new register format adopted Report 4.4, 5.2, 6.2
April 2026: Previous meeting of this Committee; failure to adopt a Local Plan, Local Government Reorganisation in Kent and Development Management Decisions were categorised as red Report 6.4, P28, P29, P30
1 September 2026: Cabinet considers this update to the Strategic Risk Register
Plain English for the jargon
Strategic Risk Register (SRR): A live document updated by the Management Team, containing risks escalated from Service Management Teams, with red risks scoring 15 to 25.
Red risk: A risk scoring 15 to 25 on the 5x5 likelihood/impact matrix, considered for inclusion on the Strategic Risk Register.
Amber risk: A risk scoring between 8 and 12, to be raised at Service Management Team and added to the Service Risks identified list.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
ItemCB 26/89
Resolved
RESOLVED : That (1) the updates to the Strategic Risk Register since the last iteration, with particular emphasis on those risks categorised as RED as shown in Annexes 1 and 1a, be noted; and (2) the service risks identified in Annex, 2 be noted.
Word for word from the decision Tonbridge and Malling published for this meeting.Source: democracy.tmbc.gov.uk
1.1The report of the Management Team provides an update on the risk management process and the Strategic Risk Register.
2 Corporate Strategy Priority Area
2.1Efficient services for all our residents, maintaining an effective council.
2.2The identification, evaluation, and cost-effective control of risks is essential in safeguarding the Council's assets, employees and customers and the delivery of services to the local community.
2.3The Council endeavours to pursue a forward-looking and dynamic approach to delivering services to the local community and will not be averse to taking a degree of commercial risk. However, it will always exercise a prudent approach to risk taking and decisions will be made within the parameters of the Council's internal control arrangements.
Recommendations
3.1Members are asked to:
1) NOTE the updates to the Strategic Risk Register since the last iteration with particular emphasis on those risks categorised as RED as shown in Annexes 1 and 1a; and
2) NOTE the service risks identified in Annex 2.
AC - RTCab P1-Public 20 July 2026 2
4 Introduction and Background
4.1The Risk Management Strategy sets out the Council's risk management objectives and details the roles and responsibilities of officers, Members and the Council's partners in the identification, evaluation and cost-effective control of risks.
4.2The Council's risk management arrangements are designed to ensure that risks are reduced to an acceptable level or, where reasonable, eliminated thereby safeguarding the Council's assets, employees and customers and the delivery of services to the local community. Examples of risk include budget deficit, cyber/data loss, environmental and reputational.
4.3The Council endeavours to pursue a forward-looking and dynamic approach to delivering services to the local community and will not be averse to taking a degree of commercial risk. However, it will always exercise a prudent approach to risk taking and decisions will be made within the parameters of the Council's internal control arrangements, i.e. Constitution, Procedural Rules, etc. These arrangements will serve to ensure that the Council does not expose itself to risks above an acceptable level.
4.4The current Risk Management Strategy was endorsed by this Committee in September 2025 and subsequently adopted by Full Council on 28 October 2025.
5 Risk Management Escalation Process
5.1Effectively risks are assessed/scored in terms of their likelihood/impact.
5.2Following the change to the Strategy in October 2025, the Council has now adopted the nation 5 x 5 risk matrix. This results in the following potential scoring of risks as detailed in the table below;
5.3Amber risks, those scoring between 8 and 12, should be raised at Service Management Team, added to the Service Risks identified list.
5.4Red risks, those scoring 15 to 25, should be considered by Service Management Teams for potential escalation to Corporate Management Team for inclusion onto the Strategic Risk Register (SRR), if agreed the Chief Officer raising the concern should add the details required to the SRR.
AC - RTCab P1-Public 20 July 2026 3
6 Strategic Risk Register
6.1The Strategic Risk Register (SRR) is a 'live' document and is updated, as often as is required, by the Management Team.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Budgetary Control 2026/27 to July 2026RESOLVED : That (1) the net favourable variance of circa £66,093 as at the end of July 2026, when compared to the pro...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.