Decision Notice D180036MEM The report of the Director of Street Scene, Leisure and Technical Services set out details of the findings of the extensive and comprehensive review of the capacity of Tonbridge Cemetery and future availability of grave spaces. It was noted that, through the utilisation of existing grave spaces, capacity was greater than originally anticipated and that there would be adequate provision until 2087. RECOMMENDED: That (1) the outcome of the be noted; (2) the Council’s IT Service progress the development of software to assist in the future management of the Cemetery and to ensure the continuing updating of capacity information; and (3) liaison be undertaken with the Diocese of Rochester and Town and Parish Councils to progress the broader review of burial capacity within the Borough.
Word for word from the decision Tonbridge and Malling published for this meeting.Source: democracy.tmbc.gov.uk
1.1.1 This Council owns and manages one burial facility within the Borough, this being Tonbridge Cemetery. Members will be aware from my previous report to this Board that in 2017 a study was commissioned to provide a comprehensive update on capacity at the cemetery, to determine the future availability of grave spaces.
1.1.2 The capacity review was undertaken in liaison with the Council’s Internal Audit Team and with the support of the previous Cemetery Registrar.
1.2Capacity Review
1.2.1 The review has been both extensive and comprehensive incorporating data capture on over 14,000 individual graves spread over 44 plots within the cemetery. The review considered a range of elements for each grave space including number, size and restrictions such as headstones and trees. The review also took into consideration burial numbers and trends from the previous 10 years to assist in estimating future burial rates.
1.2.2 The study has now been completed and has concluded that through the utilisation of existing spaces grave spaces that have no restricting factors, it is estimated that there will be adequate provision through until 2087. This length of capacity was greater than originally anticipated and shows the value of undertaking such a comprehensive review.
1.3Future Reviews
1.3.1 The study recommends that the Council should review provision again in 30 years though. This future review will benefit from continuing monitoring to assist in the management of the cemetery and negate the need for such an in-depth study
Communities&HousingAB-NKD-Part 1 Public 29 May 2018 2
being needed in the future. To facilitate this it is suggested that the Council’s IT Service take the data spreadsheet provided within the report and develop software to assist in the day to day management of Tonbridge Cemetery, thus ensuring this information can be continually updated.
1.3.2 A broader review of burial capacity across the borough incorporating facilities provided by others including Parish/Town Councils was previously reported to Cabinet on the 31 January 2017. Following the completion of the review at Tonbridge Cemetery this broader review will be progressed in liaison with the Rochester Diocese.
Legal implications
1.4.1 None
1.5Financial and Value for Money Considerations
1.5.1 Future capacity availability is a factor that is taken into consideration when reviewing cemetery charges.
1.6Risk Assessment
1.6.1 The report commissioned aimed to assess the risk to the Council of future capacity issues at Tonbridge Cemetery. It has been concluded that in the short and medium term no issues are apparent, with a further review undertaken in 30 year’s time.
1.7Equality Impact Assessment
1.7.1 The decisions recommended through this paper have a remote or low relevance to the substance of the Equality Act. There is no perceived impact on end users.
1.8Policy Considerations
1.8.1 Business Continuity/Resilience and Asset Management.
Recommendation
1.9.1 It is, therefore, RECOMMENDED TO CABINET that:
1) the outcome of the Tonbridge Cemetery Capacity Review be noted;
2) the Council’s IT Service progress with the development of software to assist in the future management of the Cemetery and ensure the continuing updating of capacity information;
3) liaison be undertaken with the Diocese at Rochester and Parish/Town Council’s to progress the boarder review of burial capacity within the borough.
Communities&HousingAB-NKD-Part 1 Public 29 May 2018 3
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Communities and Housing Advisory Board at Tonbridge and Malling and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.