Resolved
That the report be received and noted.
Joint Transportation Board noted this item on Monday 11 June 2018. Below is the council's own wording, with the papers it was decided on.
Resolved
That the report be received and noted.
An update on project progress for the Tonbridge Station project.
1.0Introduction and Background
Funding of £500,000 has been allocated from the West Kent Local Growth Fund (LGF) to improve the Transport Interchange at Tonbridge Station. The aim is to improve interaction between users at the station, provide more space for pedestrian movements and to create an interchange suitable for one of the busiest stations outside of London.
2.0Body of the report
2.1Design
Since the JTB recommendation on the 12th March there has been a lot of work on the detailed design – which will be published before construction commences. Liaising with the anti-terrorism police, there will be anti-ram bollards placed near the station forecourt to protect users (exact locations to be determined) BT have approved removing 2 of the 3 phone boxes in the area (leaving 1 near Lidl). This will open up the area for pedestrians and remove street clutter. Barden Road – Southeastern’s proposed cycle hub on Barden Road has resulted in design work being required on the junction with Vale Roundabout. Separate works may be required to ensure cyclists remain safe while accessing the hub including a proposed contraflow cycle lane.
Materials
The intention is to use the Ketley Bricks used in the high street outside the station Other footway resurfacing will be new blacktop. Ketley bricks can be maintained and create a nice finish. Other paving options were considered and rejected due to maintenance liability and risk of units having to be replaced with black top in years to come. A meeting has taken place with TMBC officers to agree locations of street furniture (finger posts, monoliths etc) and to discuss aspects of the build.
Construction
It is intended that construction will begin at the start of the summer holidays 2018 (25th July) so as to minimise disruption to traffic flow. The majority of the difficult works would then take place over the 6 week holidays and then any works to finish will be managed throughout the following months. The works will be designed so as to keep traffic flowing as best as possible. A meeting has been held with the bus companies to help plan the works to mitigate impact on their customers accessing the bus stops. At this stage we do not have a fully realised programme for construction. A communication plan has been created to fully inform, members, the public and local businesses in advance of the works taking place.
Future Meeting if applicable: Future JTB for Date: 24th September, 2018 updates
Contact Officer: Tim Middleton, Principal Transport Planner, KCC Reporting to: Tim Read, Head of Transportation - KCC
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Tonbridge Interchange Improvements: Progress reportReport | 116 KB | DownloadRead as text |
Follow Joint Transportation Board at Tonbridge and Malling and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 2 Dec 2024 | Parking UpdateThat the current progress and approach to the Parking Team’s work programme, be noted. | Noted | Open |
| 2 Dec 2024 | Parking Action Plan, Access Group 9That the decision of the Cabinet Member for Transformation and Infrastructure to set aside the objections attached at... | Noted | Open |
| 17 Jun 2024 | Scope of the Joint Transportation Board and local/public transportThat consideration be given to the scope of the Joint Transportation Board at the next meeting. | Decided | Open |
| 21 Nov 2022 | Proposed Single Yellow Line Waiting Restrictions - Oldbury LaneThat the Traffic Regulation Order for double yellow lines be implemented on Old Lane Only, as shown in the plan at Ap... | Decided | Open |
| 6 Jun 2022 | Proposed 40mph Speed Limit - B2016 Seven Mile Lane, MereworthThat the 40mph speed limit on the B2016, Seven Mile Lane, be implemented as shown on the plan at Appendix D to the re... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.