Resolved
That the report be received and noted.
Joint Transportation Board noted this item on Monday 11 March 2019. Below is the council's own wording, with the papers it was decided on.
Resolved
That the report be received and noted.
To: Tonbridge and Malling Joint Transportation Board
By: KCC Highways and Transportation
Date: 11th March 2019
Subject: Highway Works Programme 2018/19
Classification: Information Only
Summary: This report updates Members on the identified schemes approved for construction in 2018/19
1. Introduction
This report provides an update and summarises schemes that have been programmed for delivery in 2018/19
Footway and Carriageway Improvement Schemes – see Appendix A
Drainage Repairs & Improvements – see Appendix B
Street Lighting – see Appendix C
Transportation and Safety Schemes – see Appendix D
Casualty Reduction Measures – see Appendix D1 Integrated Transport Schemes – see Appendix D2 Local Growth Fund – see Appendix D3 Third Party Funded Schemes – see Appendix D4
Developer Funded Work – see Appendix E
Section 278 Works – see Appendix E1 Section 106 Works – see Appendix E2
Bridge Works – see Appendix F
Traffic Systems – see Appendix G
Combined Member Fund – see Appendix H
Tonbridge Interchange Improvements - Progress Report
Conclusion
1. This report is for Members information. Contact Officers:
The following contact officers can be contacted on 03000 418181
Kirstie Williams Mid Kent Highway Manager Mark Simmons Tonbridge & Malling District Manager Alan Casson Senior Asset Manager Sue Kinsella Street Light Asset Manager Toby Butler Traffic & Network Solutions Asset Manager Katie Moreton Drainage & Structures Asset Manager Jamie Hare Development Agreement Manager Jamie Watson Senior Schemes Programme Manager
Appendix A – Footway and Carriageway Improvement Schemes
The delivery of these schemes is weather dependent; should it prove not possible to carry out these works on the planned dates, new dates will be arranged and the residents will be informed by a letter drop to their homes.
Surface Treatments - Contact Officer Clive Lambourne
Machine Resurfacing – Contact Officer [name removed] Name Parish Extent of Works Current Status Programmed between A229 Bluebell Hill Aylesford Various sections 18th January to 22nd March 2019 Between Brook Street A26 Quarry Hill Road Tonbridge Roundabout to A2014 Pembury To be programmed Road Roundabout
From Robin Hood Lane to Kent / Tunbury Road Aylesford To be programmed Medway Border
A228 Ham Hill Roundabout circulation area + To be programmed April Snodland Roundabout both HFS approaches 2019
From Hadlow Road to Tudeley A26 Cannon Lane Hadlow To be programmed Lane Appendix B – Drainage
Drainage Repairs & Improvements - Contact Officer Earl Bourner Road Name Parish Description of Works Current Status On hold in discussions New system being installed in two phases with Queens Estates as London road Aylesford on hold awaiting final consent from the private land required to Queens Estate complete this job
Appendix C – Street Lighting
Structural testing of KCC owned street lights has identified the following as requiring. A status of complete identifies that the column replacement has been carried out. Programme dates are identified for those still requiring replacement.
Street Lighting Column Replacement – Contact Officer Sue Kinsella
Road Name Parish Description of Works Status
Sheraton Court UKPN cable issue resolved. Walderslade STRUCTURAL JSEN001 REPLACEMENT Awaiting programme date
JNAJ001 COMPLETE New Road STRUCTURAL Ditton REPLACEMENT JNAJ003 OBSTRUCTED BY JNAJ001 & JNAJ003 CARS
Station Road JSDI005 Ditton STRUCTURAL In progress REPLACEMENT Re-raised – awaiting utility plans Waveney Road Replacement of 1no streetlight Tonbridge JWAR014 complete with LED lantern
To be removed as a street lighting Nepicar Roundabout Replacement of 1no sign post Nepicar/Wro asset – will be unlit complete with LED Downflood JUAQ518 tham following RTC Awaiting removal following UKPN Higham Lane Replacement of 2no disconnection Tonbridge streetlights complete with LED JHBZ010 lantern
Lilliburn JLBF501/502 Leybourne Structural replacement Completion by March2019
Old Orchard Lane Leybourne Structural replacement Completion by March2019 JOBF501
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Highway Works Programme 2018/19Report | 345 KB | DownloadRead as text |
Follow Joint Transportation Board at Tonbridge and Malling and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 2 Dec 2024 | Parking UpdateThat the current progress and approach to the Parking Team’s work programme, be noted. | Noted | Open |
| 2 Dec 2024 | Parking Action Plan, Access Group 9That the decision of the Cabinet Member for Transformation and Infrastructure to set aside the objections attached at... | Noted | Open |
| 17 Jun 2024 | Scope of the Joint Transportation Board and local/public transportThat consideration be given to the scope of the Joint Transportation Board at the next meeting. | Decided | Open |
| 21 Nov 2022 | Proposed Single Yellow Line Waiting Restrictions - Oldbury LaneThat the Traffic Regulation Order for double yellow lines be implemented on Old Lane Only, as shown in the plan at Ap... | Decided | Open |
| 6 Jun 2022 | Proposed 40mph Speed Limit - B2016 Seven Mile Lane, MereworthThat the 40mph speed limit on the B2016, Seven Mile Lane, be implemented as shown on the plan at Appendix D to the re... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.