Resolved
That the report be received and noted.
Joint Transportation Board noted this item on Monday 21 September 2020. Below is the council's own wording, with the papers it was decided on.
Resolved
That the report be received and noted.
To: Tonbridge and Malling Joint Transportation Board
By: KCC Highways, Transportation & Waste
Date: 21st September 2020
Subject: Highway Forward Works Programme – 2020/21 onwards
Classification: Information Only
Summary: This report updates Members on the identified schemes approved for construction
1. Introduction
This report provides an update and summarises schemes that have been programmed for delivery in 2020/21.
Kent County Council has agreed a substantial increase in the budget for planned highway works over the next three years, and as a result we are still in the process of identifying and designing schemes for inclusion in our full Year One to Two (2020/21 and 2021/22) and Year Three to Five (2022/23 to 2024/25) programmes. Because of this, we have decided to publish an interim programme, and to publish the full programmes later this year. For some assets this interim programme covers approximately the first six months of 2020/21, whilst for others it includes most of the works planned for the whole year.
This programme is subject to regular review and may change for several reasons including budget allocation, contract rate changes, and to reflect KCC’s changing priorities. The programme and extent of individual sites within the programme may also be revised following engineering assessment during the design phase.
Road, Footway & Cycleway Renewal and Preservation Schemes – see Appendix A
Drainage Repairs & Improvements – see Appendix B
Street Lighting – see Appendix C
Transportation and Safety Schemes – see Appendix D Casualty Reduction Measures Externally funded schemes Local Growth Fund
Developer Funded Works – see Appendix E
Bridge Works – see Appendix F
Traffic Systems – see Appendix G
Combined Member Fund – see Appendix H
Conclusion 1. This report is for Members’ information.
Contact Officers:
The following contact officers can be contacted on 03000 418181
Kirstie Williams Highway Manager Mid Kent Mark Simmons Tonbridge and Malling District Manager Alan Casson Strategic Asset Manager Earl Bourner Drainage & Structures Asset Manager Sue Kinsella Street Light Asset Manager Toby Butler Traffic & Network Solutions Asset Manager Jamie Hare Development Agreements Manager Jamie Watson Schemes Programme Manager Appendix A – Road, Footway and Cycleway Renewal and Preservation Scheme
The delivery of these schemes is weather dependent; should it prove not possible to carry out these works on the planned dates, new dates will be arranged and the residents will be informed by a letter drop to their homes.
Surface Treatments - Contact Officer Jonathan Dean
Micro Surfacing
Road Name Parish Extent of Works Current Status Programmed for 23rd September From Long Mill Lane to 2020 for 3 days Comp Lane Platt Windmill Hill This scheme was programmed for March 2020. However, the road is very narrow and the works will require ‘hand laying’. Works are intended to be complete on the second tranche 21st – 30th Forest Grove Tonbridge Whole Road September 2020. Programmed for 22nd September From Leigh Road to 30mph 2020 for 2 days Stocks Green Road Hildenborough Markers Programmed for Three Elm Lane A26 junction to 540 metres east 28th September 2020 for 2 days Hadlow
Hartlake Road to 340 Completed Tonbridge Road Tonbridge Road East Peckham Programmed for Yardley Park Road Throughout 29th September 2020 for 3 days Tonbridge
Completed A227 Shipbourne From Higham Lane Road Tonbridge Hildenborough Road
Completed From Swallow Road to Plover Plover Road Larkfield Road Due to the scale of these works and Common Road (Back From A25 to A227 (included disruption to the Lane) Ightham Bank Lane) programme earlier in the year, it will now not be possible to complete the works this season. Therefore, the scheme is being carried over to the 2021/22 season.
Completed Hadlow Road (Service Road East) Tonbridge From Main A26 to Main A26 Ashes Lane Hadlow From A26 Hadlow Road to Higham Lane
Completed
Surface Dressing Road Name Parish Extent of Works Current Status
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Highway Forward Works Programme: 2020/21 onwardsReport | 437 KB | DownloadRead as text |
Follow Joint Transportation Board at Tonbridge and Malling and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 2 Dec 2024 | Parking UpdateThat the current progress and approach to the Parking Team’s work programme, be noted. | Noted | Open |
| 2 Dec 2024 | Parking Action Plan, Access Group 9That the decision of the Cabinet Member for Transformation and Infrastructure to set aside the objections attached at... | Noted | Open |
| 17 Jun 2024 | Scope of the Joint Transportation Board and local/public transportThat consideration be given to the scope of the Joint Transportation Board at the next meeting. | Decided | Open |
| 21 Nov 2022 | Proposed Single Yellow Line Waiting Restrictions - Oldbury LaneThat the Traffic Regulation Order for double yellow lines be implemented on Old Lane Only, as shown in the plan at Ap... | Decided | Open |
| 6 Jun 2022 | Proposed 40mph Speed Limit - B2016 Seven Mile Lane, MereworthThat the 40mph speed limit on the B2016, Seven Mile Lane, be implemented as shown on the plan at Appendix D to the re... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.