Decision Notice D190036MEM The report sought permission to consult on the draft Innovation Park Medway Local Development Order (LDO), which set out principles for development to ultimately allow developers and businesses to bring forward high quality development in the high-value technology, engineering, manufacturing and knowledge-intensive sectors. It was reported that the development had been identified as requiring an Environmental Impact Assessment. In order to satisfy this requirement an Environmental Statement would be finalised to support the LDO. Members referred to infrastructure funding and whether this development offered an opportunity to consider local issues such as traffic movements and congestion in the area. In response, it was indicated that funding might be available for economic development in the Borough which could potentially be used for local transport initiatives. However, this was not guaranteed. RECOMMENDED : That: (1) the content of the report be noted; (2) delegated authority be granted to the Director of Planning, Housing and Environmental Health and the Director of Central Services, in consultation with the Leader and the Cabinet Member for Strategic Planning and Infrastructure, to: - finalise and approve the Environmental Statement prior to public consultation in the interest of satisfying Environmental Impact Assessment requirements; and - approve any necessary minor amendments to the draft Local Development Order prior to the public consultation for the purposes of presentation and clarity.
Word for word from the decision Tonbridge and Malling published for this meeting.Source: democracy.tmbc.gov.uk
Report to Planning and Transportation Advisory Board
Background
1.1Since being established in 2012, Enterprise Zones (EZ) have attracted over £2.4 billion pounds of private sector investment, building world class business facilities and transport links and attracting nearly 24,000 jobs. By April 2017, 48 Enterprise Zones were in place, including the ‘North Kent Enterprise Zone’ a multi-site Enterprise Zone comprising sites in three locations – Kent Medical Campus (Maidstone), Ebbsfleet Garden City and Rochester Airfield, also known as Innovation Park Medway (IPM). 1.2 Businesses that locate on an Enterprise Zone can access a number of benefits, including up to 100% business rate discount worth up to £275,000 per business over a 5-year period and a simplified local authority planning, for example, through Local Development Orders (LDO) that grant automatic planning permission for certain development (such as new industrial buildings or changing how existing buildings are used) within specified areas 1.3 The IPM site is a key priority for Medway Council, who are leading the project, and own the majority of the site. However, approximately 3.7 hectares of the site fall within Tonbridge & Malling Borough (see Appendix A), in both Burham and Wouldham ward and North Aylesford and Walderslade ward. 1.4 In March 2019, Cabinet adopted the Innovation Park Medway (IPM) masterplan for economic development and marketing purposes. The masterplan outlines a scheme that will deliver a high quality innovation park, with flexible plots to encourage a wide range of high-value technology, engineering, manufacturing and knowledge-intensive businesses.
EconRegenAB-NKD-Part 1 Public 04 June 2019 2
1.1.1 Medway Council’s preferred option for taking forward development of the site has been the adoption of the masterplan as a Supplementary Planning Document along with a Local Development Order covering the entirety of the site. The main reason for this is that it allows plots to come forward with speed and ease for developers and/or businesses. In achieving full LDO coverage for the IPM site, two separate but identical LDOs will need to be adopted – one by Medway Council and one by the Borough Council.
1.1.2 The LDO is reinforced by a Design Code which sets out the key principles to which development on the site must adhere. Flexibility has been allowed for to ensure that this is not discouraging.
1.1.3 EIA screening has been undertaken and the development has been identified as requiring an Environmental Impact Assessment. As such, an Environmental Statement will support the LDO. A number of technical studies have already been undertaken, although some additional studies are still to be completed. In order to satisfy the EIA requirements, it is recommended that delegated authority be given to the Director of Planning, Housing and Environmental Health and Director of Central Services in consultation with the Leader/Cabinet Member for Economic Regeneration and the Cabinet Member for Strategic Planning and Infrastructure to finalise and approve the Environmental Statement for consultation. This will be resolved prior to consultation to ensure that consultees have the full suite of documentation.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Planning and Transportation Advisory Board at Tonbridge and Malling and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.