CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Tonbridge and Malling Borough Council
Joint Transportation Board, Monday 21 September 2020 at 7.30pm

Quarry Rise, Tonbridge - Informal One Way Consultation

Decided Committee 1 paper

Joint Transportation Board decided this item on Monday 21 September 2020. Below is the council's own wording, with the papers it was decided on.

ItemJTB 20/17

Resolved

That a further letter be sent to those households who had not responded to the informal consultation and a report on a proposal to make Quarry Rise one way running be submitted to the next meeting of the Joint Transportation Board.
Word for word from the decision Tonbridge and Malling published for this meeting. Source: democracy.tmbc.gov.uk

Follow this further

Built from Tonbridge and Malling's papers

What the report saysPro

Report to Joint Transportation Board

To: Tonbridge and Malling Joint Transportation Board

By: KCC Highways, Transportation & Waste

Date: 3rd September 2020

Subject: Quarry Rise, Tonbridge - Informal One Way Consultation

Classification: For Decision

Summary: This report informs Members on the outcome of a recent informal consultation with residents of Quarry Rise, Tonbridge

1. Introduction

Following concerns raised by residents of Quarry Rise Tonbridge, regarding the road being used as a rat run when Quarry Hill Road is solid traffic, the KCC Cabinet Member [name removed] asked the KCC Schemes Planning and Delivery team to carry out an informal consultation with Quarry Rise residents. This consultation related to the proposal to make Quarry Rise one way running from north to south, away from the town centre.

Such a move would only adversely impact residents and visitors to Quarry Rise, so a consultation letter was sent to all 22 households in Quarry Rise. A copy of the letter is shown below.

Initially there were 11 responses to the letter, so it was re-sent to the 11 households that had not responded. This resulted in a further 3 responses being received.

Therefore of 22 households 15 have responded to the informal consultation. Of those, 9 have supported the proposed plan and 6 have objected.

Following further consultation with the KCC Cabinet Member this report is duly submitted to the Joint Transportation Board for a decision on supporting the proposal to make Quarry Rise one way running from north to south.

Should the board be minded to support this change KCC will proceed with a formal Traffic Regulation Order and go to formal consultation on the Traffic Regulation Order (TRO). It is highly likely that the formal consultation will receive at least the same number of objections as those provided to the informal consultation. Should this be the case then a further report will be submitted to the JTB asking the board to affirm or refuse its approval for this scheme to go ahead.

If the board choose not to support such a proposal, at this stage, then no further action will be taken. 2. Copy of Consultation Letter

Highway Schemes Planning and Delivery Team From: Kent County Council Highway Depot 4 Javelin Way Regarding: ASHFORD Proposed changes to Kent TN24 8AD Quarry Rise, Tonbridge Phone: Ask for: Email: [email protected] Date: 20th February 2020 Ref: Quarry Rise

Dear Resident

I am informed that several residents have been concerned by the issue of rat running in Quarry Rise, Tonbridge. A view has been expressed at the way some drivers speed along Quarry Rise and that it is only a matter of time before there is a serious accident. Consequently Michael Payne, Cabinet Member for Highways and Transport and a KCC Member for Tonbridge, has asked me to investigate.

I am of the view that rat running is likely to be more of an issue in the morning, than the afternoon, and so am proposing making Quarry Rise one way, from north to south, in order to prevent this issue. This would mean that vehicles heading into Tonbridge town centre, from the A21 and Southborough direction, will not be able to use Quarry Rise as a short cut.

I would be very grateful if you could please contact me, in writing, to let me know your view on implementing such a scheme?

Yours sincerely

Ian Grigor

Schemes Project Manager [email protected] Conclusion

1. This report is for a Member decision.

Contact Officer:

The following officer can be contacted on 03000 418181

Ian Grigor Schemes Project Manager

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Quarry Rise, Tonbridge: Informal One Way ConsultationReport 16 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

12 of 35 attended
MB
Matthew BalfourChairman, present
DL
Councillor David LettingtonVice-Chair, present
RB
Councillor Robin BettsCommittee Member, present
VB
Councillor Vivian BransonCommittee Member, present
DD
Councillor Dave Davis CEng FICECommittee Member, present
AK
Councillor Andrew KennedyCommittee Member, absent
NS
Councillor Nick StapletonCommittee Member, present
MT
Councillor Mike TaylorCommittee Member, present
TD
Trudy DeanCommittee Member, present
SH
Sarah HohlerCommittee Member, present
PH
Peter HomewoodCommittee Member, absent
RL
Richard LongCommittee Member, present

All 35 on the meeting page

More from Tonbridge and Malling Joint Transportation Board

All decisions
MeetingDecisionOutcome
2 Dec 2024 Parking UpdateThat the current progress and approach to the Parking Team’s work programme, be noted. Noted Open
2 Dec 2024 Parking Action Plan, Access Group 9That the decision of the Cabinet Member for Transformation and Infrastructure to set aside the objections attached at... Noted Open
17 Jun 2024 Scope of the Joint Transportation Board and local/public transportThat consideration be given to the scope of the Joint Transportation Board at the next meeting. Decided Open
21 Nov 2022 Proposed Single Yellow Line Waiting Restrictions - Oldbury LaneThat the Traffic Regulation Order for double yellow lines be implemented on Old Lane Only, as shown in the plan at Ap... Decided Open
6 Jun 2022 Proposed 40mph Speed Limit - B2016 Seven Mile Lane, MereworthThat the 40mph speed limit on the B2016, Seven Mile Lane, be implemented as shown on the plan at Appendix D to the re... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies