Decarbonising and Energy Efficiency Capital Plan Schemes

Approved Committee 6 papers

Council approved this item on Tuesday 9 July 2024. Below is the council's own wording, with the papers it was decided on.

ItemC 24/67

Resolved

RESOLVED : That (1) the List A Capital Plan Scheme ‘Decarbonising the Council’s Estate’ be updated to include all of the projects as outlined in the report considered by Cabinet on 8 July 2024; (2) a revised figure of £1,644,799 attributable to external grant funding be reflected in the updated Capital Plan Scheme; and (3) an increased contribution of £500,000 by the Borough Council to the Capital Plan Scheme be approved and divided as set out below: · £225,000 funded from the Revenue Reserve for Capital Schemes; · £275,000 funded from the Climate Change Reserve.
Word for word from the decision Tonbridge and Malling published for this meeting. Source: democracy.tmbc.gov.uk

Follow this further

Built from Tonbridge and Malling's papers

What the report saysPro

Report to Council

DECARBONISING AND ENERGY EFFICIENCY CAPITAL PLAN SCHEMES

Item CB 24/79 referred from Cabinet of 8 July 2024

Consideration was given to an updated ‘Decarbonising the Council’s Estate’ List A Capital Plan scheme to cover all of the projects as outlined in the report, including a number of decarbonising and energy efficiency projects for which grant funding applications had been successful and several other projects being funded directly by the Borough Council, with a view to supporting delivery of the Climate Change Strategy.

Members welcomed the positive outcomes in relation to the external grant awards, details of which were set out in 1.2 of the report. In addition to the projects for which external funding had been obtained, a number of other projects which were either linked to those or had already received approval by the Council utilising its own funding were set out in 1.3 of the report.

It was noted that the capital plan scheme ‘Decarbonising the Council’s Estate (P06AM)’ was previously approved based on an estimate of an external funding of £800,000 and a Council contribution of £430,000, which figures now required updating following confirmation of the grant awards. A revised set of allocations to individual projects to be covered by the updated capital scheme were suggested in 1.4.3 of the report, with a total of £930,000 from TMBC funding and £1,644,799 from external grant funding.

Individual project evaluations for the new schemes were attached at Annexes 1 to 3 for information.

Although slight concern was expressed over the uncertainty around the noise level of the air source heat pumps to be installed at the Larkfield Leisure Centre, Members were assured that the level of noise would be taken into account as part of the planning process with due consideration given to mitigation measures if necessary.

In addition, particular reference was made to 1.6 of the report where the proposed procurement routes for the projects were set out and duly considered by Members.

RESOLVED: That quotations and tenders in respect of the following decarbonising and energy efficiency projects be sought and procurement routes be approved as required by paragraph 8.1 of the Borough Council’s Contract Procedure Rules, including the use of frameworks where appropriate, as set out below and detailed in 1.6 of the report:

(1) in respect of the re-felt work at Larkfield Leisure Centre, the LHC RS4 Roofing Systems Framework be utilised;

(2) in respect of the installation of solar PV at Larkfield Leisure Centre, the Laser Consult, Design, Install Framework be utilised; and

(3) in respect of the installation of air source heat pumps at Larkfield Leisure Centre, an open tender exercise be undertaken. (Agreed by Cabinet in accordance with Part 3 of the Constitution.)

RECOMMENDED*: That

(1) the List A capital plan scheme ‘Decarbonising the Council’s Estate’ be updated to include all of the projects as outlined in the report;

(2) a revised figure of £1,644,799 attributable to external grant funding, be reflected in the updated Capital Plan Scheme; and

(3) an increased contribution of £500,000 by the Borough Council to the Capital Plan Scheme, with £225,000 being funded from the Revenue Reserve for Capital Schemes and £275,000 being funded from the Climate Change Reserve, be approved.

*Recommended to Council

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
24/67Appendix 1 220 KB Download
PDF
24/67Appendix 2 220 KB Download
PDF
24/67Appendix 3 219 KB Download
PDF
Decarbonising and Energy Efficiency Capital Plan SchemesReport 112 KB DownloadRead as text
PDF
Recommendations of Cabinet: To follow 24/67Report 3 KB Download
PDF
Report of Interim Chief Executive 24/67Report 252 KB Download

At this meeting

Whole meeting

Who was there

38 of 43 attended
SH
Councillor Steve HammondChair, present
CB
Councillor Christopher BrownVice-Chair, present
LA
Councillor Lee AthwalCommittee Member, present
BB
Councillor Bill BanksCommittee Member, present
KB
Councillor Kath BartonCommittee Member, apologies
MS
Councillor Mrs Sue BellCommittee Member, present
AB
Councillor Angus BennisonCommittee Member, present
RB
Councillor Robin BettsCommittee Member, present
TB
Councillor Timothy BishopCommittee Member, present
MB
Councillor Matt BoughtonCommittee Member, present
PB
Councillor Paul BoxallCommittee Member, present
GB
Councillor Garry BridgeCommittee Member, present

All 43 on the meeting page

On this subject at Tonbridge and Malling

Search all
  1. Decarbonising and Energy Efficiency Capital Plan SchemesThis decision
  2. Decarbonising and Energy Efficiency Capital Plan SchemesApproved

More from Tonbridge and Malling Council

All decisions
MeetingDecisionOutcome
3 Sep 2026 MinutesThat the of the proceedings of the meeting of the Council held on 14 July 2026 be approved as a correct record and si... Approved Open
3 Sep 2026 Scheme of Allowances - Special Responsibility Allowances for Chair/Vice-Chair of Planning CommitteeRESOLVED : That (1) the Special Responsibility Allowance payable to the Chair of the Planning Committee be set at £5,... Agreed Open
3 Sep 2026 Changes to Committee Appointments 2026/27RESOLVED : That Cllr L Chapman replace Cllr R Dalton as a Conservative appointment to the Planning Committee for the ... Decided Open
3 Sep 2026 Local Code of Corporate GovernanceRESOLVED : That the updates and amendments to the Local Code of Corporate Governance (Annex 1) be approved and adopted. Approved Open
3 Sep 2026 Treasury Management Performance Update and Annual Report for 2025/26RESOLVED : That (1) the action taken by Officers in respect of Treasury Management activity for April to May 2026 be ... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies