RESOLVED : That quotations and tenders in respect of the following decarbonising and energy efficiency projects be sought and procurement routes be approved as required by paragraph 8.1 of the Borough Council’s Contract Procedure Rules, including the use of frameworks where appropriate, as set out below and detailed in 1.6 of the report: (1) in respect of the re-felt work at Larkfield Leisure Centre, the LHC RS4 Roofing Systems Framework be utilised; (2) in respect of the installation of solar PV at Larkfield Leisure Centre, the Laser Consult, Design, Install Framework be utilised; and (3) in respect of the installation of air source heat pumps at Larkfield Leisure Centre, an open tender exercise be undertaken. (Agreed by Cabinet under Decision Notice D240070CAB.) RECOMMENDED* : That (1) the List A capital plan scheme ‘Decarbonising the Council’s Estate’ be updated to include all of the projects as outlined in the report; (2) a revised figure of £1,644,799 attributable to external grant funding, be reflected in the updated Capital Plan Scheme; and (3) an increased contribution of £500,000 by the Borough Council to the Capital Plan Scheme, with £225,000 being funded from the Revenue Reserve ... view the full minutes text for item CB 24/79
Word for word from the decision Tonbridge and Malling published for this meeting.Source: democracy.tmbc.gov.uk
Report of the Interim Chief Executive Part 1- Public
Executive Non Key Decisions
Matters for Recommendation to Council
1 DECARBONISING AND ENERGY EFFICIENCY CAPITAL PLAN SCHEMES
Following the Councils successful applications for grant funding relating to several decarbonising and energy efficiency projects, this report brings forward several projects under the existing List A capital plan scheme ‘Decarbonising the Council’s Estate’ to enable the Council to progress those projects, as well as projects being funded directly by the Council, to help deliver our Climate Change Strategy.
1.1Introduction
1.1.1 One of the Council’s four key priorities set out in the Corporate Strategy 2023- 2027 is ‘Sustaining a borough which cares for the environment’, with one of the priorities being to ‘deliver climate change plans which focus on cutting emissions and increasing biodiversity’.
1.1.2 The Council’s Climate Change Strategy is a key document which helps support those priorities and one which we use to actively assess opportunities to reduce the carbon emissions from our estate as well as to improve energy efficiency and therefore reduce energy costs.
1.1.3 Members will be aware that the largest utility users within the Council’s estate are the leisure centres, due to both the size of the facilities and also the need to maintain high levels of air and water temperatures, meaning we have focused our efforts in assessing where improvements can be made to those facilities.
1.2External Grant Awards
1.2.1 Members will be aware that the Council was successful in its two recent applications for external grant funding.
1.2.2 The first was through the Government’s Swimming Pool Support Fund (SPSF) scheme in January 2024, which included an award of £393,000 for the installation of additional solar PV and £12,039 for the installation of LED lighting in pool related areas, both at Larkfield Leisure Centre.
Cabinet C - Part 1 Public 08 July 2024 2
1.2.3 The grant needs to have been spent by March 2025 and includes several conditions the Council must adhere to, including the regular reporting of progress and installation of sub-metering to be able to effectively monitor energy usage.
1.2.4 The second was through the Public Sector Decarbonisation Scheme in March 2024, which included an award of £1,164,760 for the installation of air source heat pumps to serve the fitness pool at Larkfield Leisure Centre.
1.2.5 The grant needs to have been spent by March 2026 and includes several requirements which the Council must meet, including the regular reporting of progress and a requirement to fund at least the like-for-like cost of replacing the current gas boilers, or 12% of the total project value, whichever is the higher. It is recommended the Council allocate £175,000 for this purpose.
1.2.6 It should be noted that the figures set out above are pre-tender estimates of costs.
1.2.7 Now that we know the fund amounts being awarded we have been able to assess which projects need to be progressed and therefore what capital plan schemes need to be established.
1.3Additional Projects
1.3.1 In addition to the projects for which external funding has been obtained, there are several other projects which are either linked to those set out above or had already been approved by the Council utilising its own funding. These projects are set out below:
Solar PV Installation at Tonbridge Swimming Pool
1.3.2 This project saw the installation of 150 solar PV panels on the roof at Tonbridge Pool, generating approximately 65,000 kWhs per annum, with an estimated CO2 saving of 12.7 tonnes per annum and a saving in electricity of approximately £15,000 per annum.
1.3.3 The installation was completed in March this year at a cost of £110,000.
LED Lighting Installation at Tonbridge Swimming Pool
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Budgetary Control 2026/27 to July 2026RESOLVED : That (1) the net favourable variance of circa £66,093 as at the end of July 2026, when compared to the pro...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.