Tonbridge and Malling Borough Council
Cabinet, Monday 8 July 2024 at 7.30pm

Decarbonising and Energy Efficiency Capital Plan Schemes

Approved Executive 4 papers

Cabinet approved this item on Monday 8 July 2024. Below is the council's own wording, with the papers it was decided on.

ItemCB 24/79

Resolved

RESOLVED : That quotations and tenders in respect of the following decarbonising and energy efficiency projects be sought and procurement routes be approved as required by paragraph 8.1 of the Borough Council’s Contract Procedure Rules, including the use of frameworks where appropriate, as set out below and detailed in 1.6 of the report: (1) in respect of the re-felt work at Larkfield Leisure Centre, the LHC RS4 Roofing Systems Framework be utilised; (2) in respect of the installation of solar PV at Larkfield Leisure Centre, the Laser Consult, Design, Install Framework be utilised; and (3) in respect of the installation of air source heat pumps at Larkfield Leisure Centre, an open tender exercise be undertaken. (Agreed by Cabinet under Decision Notice D240070CAB.) RECOMMENDED* : That (1) the List A capital plan scheme ‘Decarbonising the Council’s Estate’ be updated to include all of the projects as outlined in the report; (2) a revised figure of £1,644,799 attributable to external grant funding, be reflected in the updated Capital Plan Scheme; and (3) an increased contribution of £500,000 by the Borough Council to the Capital Plan Scheme, with £225,000 being funded from the Revenue Reserve ... view the full minutes text for item CB 24/79
Word for word from the decision Tonbridge and Malling published for this meeting. Source: democracy.tmbc.gov.uk

Follow this further

Built from Tonbridge and Malling's papers

What the report saysPro

Report to Cabinet

TONBRIDGE & MALLING BOROUGH COUNCIL

CABINET

08 July 2024

Report of the Interim Chief Executive Part 1- Public

Executive Non Key Decisions

Matters for Recommendation to Council

1 DECARBONISING AND ENERGY EFFICIENCY CAPITAL PLAN SCHEMES

Following the Councils successful applications for grant funding relating to several decarbonising and energy efficiency projects, this report brings forward several projects under the existing List A capital plan scheme ‘Decarbonising the Council’s Estate’ to enable the Council to progress those projects, as well as projects being funded directly by the Council, to help deliver our Climate Change Strategy.

1.1Introduction

1.1.1 One of the Council’s four key priorities set out in the Corporate Strategy 2023- 2027 is ‘Sustaining a borough which cares for the environment’, with one of the priorities being to ‘deliver climate change plans which focus on cutting emissions and increasing biodiversity’.

1.1.2 The Council’s Climate Change Strategy is a key document which helps support those priorities and one which we use to actively assess opportunities to reduce the carbon emissions from our estate as well as to improve energy efficiency and therefore reduce energy costs.

1.1.3 Members will be aware that the largest utility users within the Council’s estate are the leisure centres, due to both the size of the facilities and also the need to maintain high levels of air and water temperatures, meaning we have focused our efforts in assessing where improvements can be made to those facilities.

1.2External Grant Awards

1.2.1 Members will be aware that the Council was successful in its two recent applications for external grant funding.

1.2.2 The first was through the Government’s Swimming Pool Support Fund (SPSF) scheme in January 2024, which included an award of £393,000 for the installation of additional solar PV and £12,039 for the installation of LED lighting in pool related areas, both at Larkfield Leisure Centre.

Cabinet C - Part 1 Public 08 July 2024 2

1.2.3 The grant needs to have been spent by March 2025 and includes several conditions the Council must adhere to, including the regular reporting of progress and installation of sub-metering to be able to effectively monitor energy usage.

1.2.4 The second was through the Public Sector Decarbonisation Scheme in March 2024, which included an award of £1,164,760 for the installation of air source heat pumps to serve the fitness pool at Larkfield Leisure Centre.

1.2.5 The grant needs to have been spent by March 2026 and includes several requirements which the Council must meet, including the regular reporting of progress and a requirement to fund at least the like-for-like cost of replacing the current gas boilers, or 12% of the total project value, whichever is the higher. It is recommended the Council allocate £175,000 for this purpose.

1.2.6 It should be noted that the figures set out above are pre-tender estimates of costs.

1.2.7 Now that we know the fund amounts being awarded we have been able to assess which projects need to be progressed and therefore what capital plan schemes need to be established.

1.3Additional Projects

1.3.1 In addition to the projects for which external funding has been obtained, there are several other projects which are either linked to those set out above or had already been approved by the Council utilising its own funding. These projects are set out below:

Solar PV Installation at Tonbridge Swimming Pool

1.3.2 This project saw the installation of 150 solar PV panels on the roof at Tonbridge Pool, generating approximately 65,000 kWhs per annum, with an estimated CO2 saving of 12.7 tonnes per annum and a saving in electricity of approximately £15,000 per annum.

1.3.3 The installation was completed in March this year at a cost of £110,000.

LED Lighting Installation at Tonbridge Swimming Pool

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
24/79Appendix 1 220 KB Download
PDF
24/79Appendix 2 220 KB Download
PDF
24/79Appendix 3 219 KB Download
PDF
Decarbonising and Energy Efficiency Capital Plan SchemesReport 252 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

5 of 11 attended
MB
Councillor Matt BoughtonChair, apologies
RB
Councillor Robin Betts (Climate Change, Regeneration and Property)Committee Member, present
MC
Councillor Martin Coffin (Transformation and Infrastructure)Committee Member, present
DK
Councillor Des Keers (Community Services)Committee Member, present
KT
Councillor Kim Tanner (Finance and Housing)Committee Member, present
MT
Councillor Mike Taylor (Planning)Committee Member, present
MH
Councillor Mark HoodOther Member, in attendance
LA
Councillor Lee AthwalOther Member, in attendance
MA
Councillor Mrs Anita Oakley MA BA (Hons)Other Member, in attendance
WP
Councillor Wendy PalmerOther Member, in attendance
MR
Councillor Mark RhodesOther Member, in attendance

On this subject at Tonbridge and Malling

Search all
  1. Decarbonising and Energy Efficiency Capital Plan SchemesThis decision
  2. Decarbonising and Energy Efficiency Capital Plan SchemesApproved

More from Tonbridge and Malling Cabinet

All decisions
MeetingDecisionOutcome
1 Sep 2026 MinutesThat the of the meeting of the Cabinet held on 30 June 2026 be approved as a correct record and signed by the Chairman. Approved Open
1 Sep 2026 Local Government Reorganisation - Establishment of West Kent Joint CommitteeRESOLVED : That (1) the Secretary of State’s decision to proceed with four unitary councils for Kent and Medway, as s... Noted Open
1 Sep 2026 Budgetary Control 2026/27 to July 2026RESOLVED : That (1) the net favourable variance of circa £66,093 as at the end of July 2026, when compared to the pro... Noted Open
1 Sep 2026 Risk ManagementRESOLVED : That (1) the updates to the Strategic Risk Register since the last iteration, with particular emphasis on ... Noted Open
1 Sep 2026 Artificial Intelligence Governance Framework PolicyRESOLVED : That (1) the , attached at Annex 1, be approved for adoption and implementation; (2) the establishment and... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies