RESOLVED : That (1) the project for riverside lighting between Vale Road and the northwest boundary of the former gasholder site be progressed through the tender and construction stages; (2) delegated authority be granted to the Director of Street Scene, Leisure and Technical Services, in consultation with the Cabinet Member for Communities and local Ward Members, to amend the design to take into account any findings from the ecological appraisal and any further comments from external bodies including the Environment Agency and Kent Wildlife Trust; and (3) a project budget as set out in the report and funded in full via developer contributions, be approved.
Word for word from the decision Tonbridge and Malling published for this meeting.Source: democracy.tmbc.gov.uk
3.1Cabinet is requested to consider the design report carried out by consultant Project Centre included at Annex 1 to the report and approve that the project for riverside lighting between Vale Road and the northwest boundary of the former gasholder site is progressed through the tender and construction stages.
Cab ENKD P1-Public 02 September 2025 2
3.2Cabinet is requested to grant delegated authority to the Director of Street Scene, Leisure and Technical Services in consultation with the Cabinet Member for Communities and local members, to amend the design to take into account any findings from the ecological appraisal and any further comments from external bodies including the Environment Agency and Kent Wildlife Trust.
3.3Approve a project budget of £94,000 funded in full from developer contributions.
4 Introduction and Background
4.1The Vale Road to Town Lock section of the Riverside Route is approximately 380m in length. The section between Vale Road and the northwest boundary of the former gasholder site, has a lack of lighting combined with a narrow path that is lined with trees and shrubbery and unprotected river edge, making this an uninviting section of the route.
4.2In order to assist the Council, a procurement process was undertaken, and external consultants Project Centre were appointed to undertake a feasibility study that was reviewed by members of the Finance, Regeneration and Scrutiny Select Committee at the meeting on 27th May 2025.
4.3At the Cabinet meeting on 3rd June 2025 it was resolved that the use of the Borough Council’s powers under s161 of the Public Health Act 1875 for the delivery of the project, with agreement from Kent County Councils Public Rights of Way Team, be authorised; and that arrangement be made for Members to have physical sight of the likely intended lighting columns by means of a demonstration in a low light at a future meeting or a site visit.
4.4At the Council meeting on 8th July 2025, it was resolved that the Scheme be transferred to List A of the Capital Plan
4.5Project Centre were then re-appointed, following a procurement process, to carry out the stage 4 design.
5 Proposal
5.1The proposal outlined in Project Centre’s design report at Annex 1 is to progress the tendering and construction of the project. Whilst Annex 1 includes the full report, any supporting documentation can be made available upon request. In order to be able to progress the project this will need to be subject to any findings from the ecological appraisal and any further comments from external bodies including the Environment Agency and Kent Wildlife Trust.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Budgetary Control 2026/27 to July 2026RESOLVED : That (1) the net favourable variance of circa £66,093 as at the end of July 2026, when compared to the pro...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.