Replacement of Shallows Bridge, Haysden Country Park
DecidedCommittee4 papers
AI summaryTonbridge and Malling Council has approved replacing condemned Shallows Bridge in Haysden Country Park this financial year, with £265k estimated and £112k from reserves.
Written from the decision and the officer reportPDF Pro
OutcomeDecidedScheme moved to List A of Capital Plan
Money£265k estimated, £112k from reservesDeveloper contributions cover just over half
What happens nextBuild in current financial yearSubject to assessment of existing abutments
Who it affectsHaysden Country Park usersDog walkers, visitors and volunteers
What was decided
The scheme to replace Shallows Bridge in Haysden Country Park is transferred to List A of the Capital Plan.
Subject to an assessment of the abutments, the replacement bridge will be constructed in the current financial year.
Why
The existing bridge has reached the end of its life, has been condemned by the structural engineer and cannot be repaired, and has been closed to the public. Report 4.3
The bridge is considered essential to the park, providing quick access from the car park and enabling circular walks, and its removal would extend emergency response times. Report P11
What happens next
Remove the existing bridge to allow the structural engineer to inspect and assess the existing abutments, with a view to reusing them. Report 7.2, 8.2
If the abutments are not fit for purpose, a further report will be brought back to members to determine whether the project is cost prohibitive. Report 7.2
Stakeholders will be updated through site notices and social media channels. Report 9.1
The money
£265k Estimated cost of replacing the bridge Report 7.1
£112k Balance to be provided from the Revenue Reserve for Capital Schemes Report 7.1
£40k Budgetary estimate for removing the existing structure and returning the riverbanks to a natural finish, if not replaced Report 6.1
£45,000 Potential additional cost if full reconstruction of the abutments is required Report 7.2
Options considered
Chosen: Remove and replace the bridge with a new, wider, Disability Discrimination Act compliant structure. The existing bridge cannot be repaired and the new design will be wider and meet accessibility requirements. Report 4.3, 5.1, 5.2
Rejected: Do not replace the bridge, only remove the existing structure and restore the riverbanks. The bridge is considered essential to the park and its loss would extend emergency response times and prohibit some users from crossing. Report 6.1, P11
Implications
Financial: Developer contributions are expected to meet just over half the £265k estimated cost, with the remaining £112k from the Revenue Reserve for Capital Schemes. Report 7.1
Financial: If the abutments cannot be reused, a further £45,000 could be required, potentially making the project cost prohibitive. Report 7.2
Risk: Construction near water can be prone to unforeseen costs and challenges, and more detailed design work may be required. Report 8.1, 8.2
Equalities: The new bridge will include longer ramps compliant with the Disability Discrimination Act and will be wider than the current narrow structure, with a positive impact on end users. Report 5.2
Climate: Adaptation and resilience have been considered, though specific climate change advice has not been sought for the recommendations.
Other: Procurement, business continuity, health and safety, and healthy lifestyles are identified as cross-cutting issues for the project. Report 10.3
Who and where
Visitors and regular users of Haysden Country Park, including dog walkers Report P11
Volunteers who carry out regular maintenance works in the park Report P11
Emergency services responding in the park Report P11
Timeline
Current financial year: Replacement bridge to be constructed, subject to abutment assessment
Every 2 years: Specialist independent structural assessments of council bridges are carried out Report 4.2, P6
Plain English for the jargon
List A of the Capital Plan: The council's approved list of capital schemes that are funded and can proceed.
List C Capital Plan Evaluation: An evaluation of a scheme being considered for inclusion in the capital plan, presented before being added to the approved list.
Revenue Reserve for Capital Schemes: Council reserves set aside to fund capital projects from revenue resources.
Developer contributions: Payments from developers, often under planning obligations, used to fund infrastructure or facilities.
Abutments: The structures at each end of a bridge that support its deck and connect it to the riverbanks.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
ItemC 25/94
Resolved
RESOLVED : That (1) the scheme to replace the Shallows Bridge, Haysden Country Park be transferred to List A of the Capital Plan; and (2) subject to an assessment of the abutments, the replacement bridge be constructed in the current financial year.
Word for word from the decision Tonbridge and Malling published for this meeting.Source: democracy.tmbc.gov.uk
3.1Cabinet is requested to consider the List C Capital Plan Evaluation for the replacement of Shallows Bridge at Haysden Country Park (Annex 1), recommend to Council that the scheme be transferred to List A of the Capital Plan and subject to an assessment of the abutments be constructed in the current financial year.
4 Introduction and Background
4.1The Council has a total of 28 Council bridges it owns.
4.2These bridges are inspected on a routine basis by the Engineering Manager in the Technical Services Team with specialist independent structural assessments by a
Cab - RTCou P1-Public 02 September 2025 2
consultant every 2 years. A number of bridges are now coming to end of life and are being closely monitored.
4.3Shallows Bridge in Haysden Country Park has reached the end of its life and has been condemned by the structural engineer. The bridge has subsequently been closed to the public. The existing bridge cannot be repaired and now needs removal and replacement.
5 Proposal
5.1The proposal is to remove the existing Shallows Bridge and replace it with a new bridge that meets the needs of park users.
5.2The new bridge will include longer ramps that will be compliant with the Disability Discrimination Act and will be wider as the current bridge is very narrow.
The Shallows bridge is considered essential to Haysden Country Park, as it provides quick access to the park from the car park and enables circular walks for dog walkers and other regular users /visitors. It is also frequently used by Volunteers to carry out regular maintenance works. The distance to an alternative means of crossing the river is excessive and is prohibitive for some users. It is a popular start point for walks that end at the catering facilities and also popular with visitors who may not wish to visit the catering area or Barden Lake. The removal of the bridge also increases the time required for emergency responses and access to popular areas of the park.
5.3The location of the bridge is shown on the plan at Annex 2.
6 Other Options
6.1The only other option is not to replace the bridge as a repair is not possible. The existing structure would still need to be removed as a minimum and additional work would be required to remove the abutments and return the riverbanks to a natural finish. The budgetary estimate for this is iro £40k.
7 Financial and Value for Money Considerations
7.1The replacement of the bridge has been estimated at £265k. Cabinet will see at Annex 1 the potential to utilise developer contributions to meet just over half these costs. The Head of Finance (Section 151 Officer) has advised that as the works are required for health and safety grounds the balance of £112k would need to be provided from the Revenue Reserve for Capital Schemes.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Local Code of Corporate GovernanceRESOLVED : That the updates and amendments to the Local Code of Corporate Governance (Annex 1) be approved and adopted.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.