AI summaryTonbridge and Malling Borough Council adopts updated Risk Management Strategy and Guidance, with a new risk matrix to be used for reporting from January 2026.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedRisk Management Strategy and accompanying Guidance
MoneyNot stated
What happens nextNew risk matrix from January 2026To be used for reporting if approved
Who it affectsCouncil risk reportingStrategic Risk Register and service risk reporting

What was decided

The Council adopted the Risk Management Strategy and accompanying Guidance, subject to any amendments required. Report P12

Why

The Strategy and Guidance are subject to annual review, and changes had been considered by the Risk Champions Group. Report P7

Three risks remained categorised as RED in July 2025: Savings and Transformation Strategy, Local Plan failure, and the Agile System exit. Report P3, P4

Members challenged the AMBER rating for the Carbon Neutral 2030 Aspiration risk, though it was expected to stay AMBER due to reduced future grant funding. Report P8

What happens next

The new risk matrix format, if approved, would be used for reporting from January 2026. Report P7

Ongoing risk assessment for Devolution and Local Government Reorganisation would be informed by work with Kent authorities and an appointed strategic partner. Report P5

Implications

  • Risk: Devolution and Local Government Reorganisation risk remained AMBER, with assessment continuing. Report P5
  • Risk: Three RED risks unchanged since July 2025, covering savings, Local Plan, and the Agile System exit. Report P3, P4
  • Risk: Carbon Neutral 2030 Aspiration risk likely to remain AMBER due to reduced future grant funding. Report P8
  • Other: A new risk matrix format was proposed following review by the Risk Champions Group. Report P7

Who and where

  • Council officers and Members involved in risk reporting Report P2, P7
  • Service Management Teams contributing to the risk register Report P6

Timeline

  • July 2025: Three risks categorised as RED on the Strategic Risk Register. Report P3
  • 29 September 2025: Audit Committee considered the report and recommended adoption by Full Council. Report P1, P12
  • 28 October 2025: Full Council adopted the Risk Management Strategy and Guidance.
  • January 2026: New risk matrix format to be used for reporting, if approved. Report P7

Plain English for the jargon

  • SRR: Strategic Risk Register
  • RED risk: Highest risk category in the council's risk matrix
  • AMBER risk: Medium risk category in the council's risk matrix
  • Risk Champions Group: Council group that reviewed the changes to the risk management guidance
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
ItemC 25/98

Resolved

RESOLVED : That the Strategy and accompanying Guidance be adopted.
Word for word from the decision Tonbridge and Malling published for this meeting. Source: democracy.tmbc.gov.uk

Follow this further

Built from Tonbridge and Malling's papers

What the report saysPro

Report to Council

Risk management

Item AU 25/43 referred from Audit Committee of 29 September 2025

The report of Management Team provided an update on the risk management process and the Strategic Risk Register (SRR). An update in respect of the work being undertaken within the Council to champion risk management was also provided.

In July 2025, there were 3 risks categorised as RED as summarised below and these remained RED.

 Achievement of Savings and Transformation Strategy  Failure to agree a Local Plan  Managed exit from the Agile System

Reference was made to the risk in respect of ‘Devolution and Local Government Reorganisation’, which remained as AMBER at this stage, although it was recognised that the ongoing risk assessment would be informed by the work underway regarding the submissions from the Kent authorities with the assistance of an appointed strategic partner.

A schedule of ongoing risks and risks identified by Service Management Teams and Management Team since the last report to the Committee in July 2025 was attached at Annex 2 to the report.

As part of the arrangements in place to ensure risk management maintained a high profile within the Council, the Risk Management Strategy (attached at Annex 3) and accompanying guidance (attached at Annex 4) were subject to annual review. Following changes to the guidance and consideration by the Risk Champions Group, a new format of the risk matrix was proposed and attached at Annex 5, and if approved by Council would be used for reporting from January 2026.

During discussion, Members challenged the AMBER risk rating for ‘Carbon Neutral 2030 Aspiration’ despite various works having been carried out and the success of grant applications, however it was likely that the risk would remain AMBER due to a reduction in future grant funding.

RECOMMENDED*: That

(1) the updates to the Strategy Risk Register since the last iteration with particular emphasis on those risks categorised as RED as shown in Annexes 1 and 1a, be noted;

(2) the service risks identified in Annex 2, be noted; and

(3) the Risk Management Strategy and accompanying Risk Management Guidance, subject to any amendments required, be reviewed and adopted by Full Council.

*Recommended to Cabinet

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Executive Summery: Strategic Risk Register 25/98Appendix 1 210 KB Download
PDF
Strategic Risk Register 25/98Appendix 1a 272 KB Download
PDF
Service Risks 25/98Appendix 2 492 KB Download
PDF
Recommendations of the Audit Committee: 29 September 2025 25/98Report 123 KB DownloadRead as text
PDF
Report of Management Team 25/98Report 161 KB Download
PDF
Risk ManagementReport 89 KB Download

At this meeting

Whole meeting

Who was there

40 of 44 attended
CB
Councillor Christopher BrownChair, present
KT
Councillor Kim TannerVice-Chair, present
LA
Councillor Lee AthwalCommittee Member, present
BB
Councillor Bill BanksCommittee Member, present
KB
Councillor Kath BartonCommittee Member, present
MS
Councillor Mrs Sue BellCommittee Member, present
AB
Councillor Angus BennisonCommittee Member, present
RB
Councillor Robin BettsCommittee Member, present
TB
Councillor Timothy BishopCommittee Member, present
MB
Councillor Matt BoughtonCommittee Member, present
PB
Councillor Paul BoxallCommittee Member, apologies
GB
Councillor Garry BridgeCommittee Member, present

All 44 on the meeting page

On this subject at Tonbridge and Malling

Search all
  1. Risk ManagementThis decision
  2. Risk ManagementNoted
  3. Risk ManagementNoted
  4. Risk ManagementNoted
  5. Risk ManagementNoted
  6. Risk ManagementNoted

More from Tonbridge and Malling Council

All decisions
MeetingDecisionOutcome
3 Sep 2026 MinutesThat the of the proceedings of the meeting of the Council held on 14 July 2026 be approved as a correct record and si... Approved Open
3 Sep 2026 Scheme of Allowances - Special Responsibility Allowances for Chair/Vice-Chair of Planning CommitteeRESOLVED : That (1) the Special Responsibility Allowance payable to the Chair of the Planning Committee be set at £5,... Agreed Open
3 Sep 2026 Changes to Committee Appointments 2026/27RESOLVED : That Cllr L Chapman replace Cllr R Dalton as a Conservative appointment to the Planning Committee for the ... Decided Open
3 Sep 2026 Local Code of Corporate GovernanceRESOLVED : That the updates and amendments to the Local Code of Corporate Governance (Annex 1) be approved and adopted. Approved Open
3 Sep 2026 Treasury Management Performance Update and Annual Report for 2025/26RESOLVED : That (1) the action taken by Officers in respect of Treasury Management activity for April to May 2026 be ... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies