AI summaryTonbridge and Malling Cabinet endorses action plan to address Planning Advisory Service review recommendations, with progress updates to scrutiny committee.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedPAS Review recommendations noted and Action Plan endorsed with amendments
MoneyNot specified in reportCosts met from Transformation Reserve budget allocation
What happens nextReview into application adjournmentsReview of Area Planning Committee adjournment process under Rule 15.24
Who it affectsPlanning service and applicantsChanges affect Development Management and committee processes

What was decided

Cabinet noted the PAS Review report contents and endorsed the Action Plan, subject to amendments, for delivering the recommendations. Report 3.1, 3.2

Cabinet approved the proposed timescales in the Action Plan and agreed progress will be a standing item at future Housing and Planning Scrutiny Select Committee meetings. Report 3.3, 9.1

Cabinet agreed to a review into the adjournment of applications at Area Planning Committees under Committee Procedure Rule 15.24 to explore streamlining the process. Report 8.1

Why

A PAS Review was an identified project in the Council's 25/26 Annual Service Delivery Plan, undertaken between 15 and 18 September 2025. Report 4.1, 4.2, 4.3

The Review team gave a debrief and issued a final draft report in November 2025, which has been turned into an action plan with proposed actions, timescales and ownership. Report 5.1

Issues identified about appeals percentages have been added to the Planning Service Risk Register and Strategic Risk Register. Report 7.1

What happens next

Officers will monitor progress through regular meetings between senior members and officers, plus team meetings and one-to-ones. Report 9.1

The first formal review of the Action Plan is scheduled for the Housing and Planning Scrutiny Select Committee in May 2026. Report 3.3, 9.2

Any action plan items requiring funding will go through the Council's usual business case and financial management processes, with legislative changes possibly needed for Planning Committee structure reforms. Report 6.2, 8.1

Options considered

  • Chosen: Endorse and adopt the proposed Action Plan as set out in Annex 3. Subject to amendments (i), (ii) and (iii) agreed at the meeting Report 3.2, 5.1
  • Chosen: Undertake a review into the adjournment of applications at Area Planning Committees. To explore if the current process could be streamlined under Committee Procedure Rule 15.24
  • Rejected: Reject the recommendations of the Housing and Planning Scrutiny Select Committee

Implications

  • Risk: Appeals percentage issues from the PAS Review have been added to the Planning Service Risk Register and the Strategic Risk Register. Report 7.1
  • Legal: Legislative changes may be required to implement proposed changes to Planning Committee structures, and timescales are outside the Council's control. Report 8.1
  • Financial: Review costs were met from the Transformation Reserve, and any future funded actions will require a business case under usual financial management processes. Report 6.1, 6.2
  • Equalities: Decisions have been analysed under the Public Sector Equality Duty and do not vary between groups of people. Report 10.2, P29
  • Climate: Climate change advice was not sought in preparing the options and recommendations; no significant impact on carbon or biodiversity identified.
  • Staffing: Officers will monitor progress through regular meetings between senior members and officers, plus team meetings and one-to-ones. Report 9.1

Who and where

  • Development Management officers and Planning Service staff Report 4.3, 9.1
  • Members of the Housing and Planning Scrutiny Select Committee Report 3.3, 9.2
  • Planning applicants and users of the planning service Report 10.2, P29
  • Area Planning Committee members handling adjourned applications

Timeline

  • 20 May 2025: Scope of the PAS Review presented to committee members for endorsement Report 4.2
  • July 2025: Operational Development Management review with workshops held Report 4.3
  • 15 to 18 September 2025: Full PAS Review took place on site Report 4.4
  • Late October 2025: Draft report received by officers
  • November 2025: Final draft of the PAS Review report issued
  • 2 December 2025: Housing and Planning Scrutiny Select Committee considered the review and Action Plan Report P5
  • 6 January 2026: Cabinet adopted the Action Plan with amendments
  • May 2026: First formal review point of the Action Plan at scrutiny committee Report 3.3, 9.2

Plain English for the jargon

  • PAS: Planning Advisory Service
  • PAS Review: Independent peer review of the Council's planning service
  • HPSSC: Housing and Planning Scrutiny Select Committee
  • Development Management: The council function that processes planning applications
  • Transformation Reserve: Council reserve used to fund transformation projects
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
ItemCB 26/8

Resolved

RESOLVED : That (1) the contents of the Planning Advisory Service Review report, including the recommendations for action, be noted; (2) subject to the amendments set out at (i) (ii) and (iii) above, the proposed Action Plan (Annex 3) for delivering on the Planning Advisory Service Review recommendations be endorsed and adopted; (3) the proposed timescales in the Action Plan be noted and approved; (4) an update on progress on the Action Plan be reported as a standing item on future Housing and Planning Scrutiny Select Committee agendas; and (5) a review into the adjournment of applications at Area Planning Committees, in accordance with Committee Procedure Rule 15.24, be undertaken to explore if the current process could be streamlined. [Subsequent to the meeting, the Action Plan was updated to reflect amendments (i), (ii), (iii) and (v)]
Word for word from the decision Tonbridge and Malling published for this meeting. Source: democracy.tmbc.gov.uk

Follow this further

Built from Tonbridge and Malling's papers

What the report saysPro

Report to Cabinet

Recommendations

Members are asked to:

3.1NOTE the contents of the Planning Advisory Service Review Report including the recommendations for action and RECOMMEND to Cabinet that they endorse this report.

3.2ENDORSE the proposed action plan for delivering on the PAS Review recommendations and RECOMMEND to Cabinet that this is adopted.

3.3NOTE the proposed timescales in the action plan and AGREE that progress will be reported back to the Housing & Planning Scrutiny Select Committee in May 2026.

HPSSC NKD P1-Public 02 December 2025 2

4 Introduction and Background

4.1The undertaking of a PAS Review is an identified project in the Council’s 25/26 Annual Service Delivery Plan.

4.2The scope of the review was presented to Members of this committee on 20 May 2025 for endorsement.

4.3The Review took place in two stages – the first was a review of operational Development Management matters, which included a desktop review of performance information and a series of workshop sessions with Development Management Officers in July 2025. A specific report on this element of the review has been provided and is appended to this report as Annex 1.

4.4The second stage was the full PAS Review, which took place between Monday 15 and Thursday 18 September 2025. The PAS Review team comprised of:

· Councillor David Brackenbury, North Northamptonshire Council · Mark Cassidy, Chief Officer – Planning and Climate Change, Lancaster City Council · Christine Lyons, Executive Director Growth and Partnerships, Basildon Borough Council · Rachel Murtagh, Principal Consultant, PAS · Peter Ford, Peer Review Manager and Principal Consultant, PAS · 4.5 The PAS team ran a debrief session at the end of their time at the Council to give initial feedback. The draft report was received by officers in late October and reviewed for factual issues before a final draft was issued in November. It is appended to this report as Annex 2.

5 PAS Review Action Plan

5.1The PAS Review report makes a number of recommendations which have been formulated into an action plan with a proposed set of actions, timescales and ownership. This is appended to the report at Annex 3 for Members’ consideration.

6 Financial and Value for Money Considerations

6.1The costs of the Review were met through a specific budget allocation drawn from the Transformation Reserve.

6.2Any items in the action plan that require funding, either on a one off or ongoing basis, will be subject to the Council’s usual business case and financial management processes.

HPSSC NKD P1-Public 02 December 2025 3

7 Risk Assessment

7.1The issues highlighted in the PAS review report that relate to appeals percentages have been reviewed and added to the Planning Service Risk Register and to the Strategic Risk Register.

8.1Legislative changes may be required to implement proposed changes to Planning Committee structures. The timescales for this are therefore outside of the Council’s control

9 Implementation

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
01 Report of Director of Planning,Housing and Environmental Health 26/8Report 239 KB DownloadRead as text
PDF
01.01 Annex 1 TMBC Planning Peer Review FINAL 26/8Appendix 1.2 MB Download
PDF
01.02 Annex 2 TMBC PAS DM Review Report FINAL 26/8Appendix 1.1 MB Download
PDF
01.03 Action Plan: for main Peer Review 26/8Report 401 KB Download
PDF
Planning Advisory Service: Review of the Council's Planning ServiceReport 195 KB Download

At this meeting

Whole meeting

Who was there

4 of 13 attended
MB
Councillor Matt BoughtonChair, present
RB
Councillor Robin Betts (Housing, Environment and Economy)Committee Member, apologies
MC
Councillor Martin Coffin (Finance, Waste and Technical Services)Committee Member, apologies
DK
Councillor Des Keers (Community Services)Committee Member, present
AM
Councillor Adem Mehmet (Infrastructure and Tonbridge Regeneration)Committee Member, present
MT
Councillor Mike Taylor (Planning)Committee Member, present
MS
Councillor Mrs Sue BellOther Member, in attendance
SC
Councillor Steve CrispOther Member, in attendance
MH
Councillor Mark HoodOther Member, in attendance
DK
Councillor Dennis KingOther Member, in attendance
MA
Councillor Mrs Anita Oakley MA BA (Hons)Other Member, in attendance
MR
Councillor Mark RhodesOther Member, in attendance

All 13 on the meeting page

On this subject at Tonbridge and Malling

Search all
  1. Planning Advisory Service - Review of the Council's Planning ServiceThis decision
  2. Matters Referred from Planning and Transportation Advisory BoardNoted
  3. Planning and Transportation Advisory Board - 24 July 2018 - VotingNoted
  4. Matters Referred from Planning and Transportation Advisory Board of 5 July 2016Noted

More from Tonbridge and Malling Cabinet

All decisions
MeetingDecisionOutcome
1 Sep 2026 MinutesThat the of the meeting of the Cabinet held on 30 June 2026 be approved as a correct record and signed by the Chairman. Approved Open
1 Sep 2026 Local Government Reorganisation - Establishment of West Kent Joint CommitteeRESOLVED : That (1) the Secretary of State’s decision to proceed with four unitary councils for Kent and Medway, as s... Noted Open
1 Sep 2026 Budgetary Control 2026/27 to July 2026RESOLVED : That (1) the net favourable variance of circa £66,093 as at the end of July 2026, when compared to the pro... Noted Open
1 Sep 2026 Risk ManagementRESOLVED : That (1) the updates to the Strategic Risk Register since the last iteration, with particular emphasis on ... Noted Open
1 Sep 2026 Artificial Intelligence Governance Framework PolicyRESOLVED : That (1) the , attached at Annex 1, be approved for adoption and implementation; (2) the establishment and... Approved Open