That appointment of replacement M & E consultants at an additional cost of £50k be approved. (Vote: For 23, Abstentions 2) It was proposed by Councillor Morrish, seconded by Councillor Brenton and – That the revised layout of the customer hub at an additional cost of £133k be rejected. (Vote: For 18, Against 3, Abstentions 4) The motion was carried. The Strategic Manager (Resources) presented the final section of the report, Digital by Default. The Committee was asked to approve the implementation of a Programme Board as outlined in the report. In accordance with the Constitution it was proposed by Councillor Eastman, seconded by Councillor S inch and – That in view of the fact 3 hours had elapsed since the meeting had commenced, the meeting should continue. (Vote: For 19, Against 5, Abstentions 1) There were concerns that the proposed Programme Board looked rather like an Executive Council. The Strategic Manager (Resources) reassured Members that it was only a model for managing a range of projects. It was proposed by Councillor Whittaker and seconded by Councillor Christie That Members would need more information about how the Programme Board would operate and therefore, deferred. (Vote: ... view the full minutes text for item 10.
Word for word from the decision Torridge published for this meeting.Source: democracy.torridge.gov.uk
To update Full Council on progress made within the various projects and options for improving the Governance and oversight of the Programme along with appropriate recommendations.
1. INTRODUCTION
The original Transforming Torridge Programme (TTP) was first approved at Full Council at its meeting on 9th October 2014. A further Full Council meeting on 12th January 2015 approved the budget of £1.6m and the project strands making up the Programme approved, which were:
(a) Office Accommodation (b) Customer First – the reception hub (c) Business Innovation – also known as channel shift (d) Locality working
It was reported that the overall Programme of change would take around 2-3 years to implement on an incremental basis rather than a “big bang approach”. The reason for the programme was to ensure that the Council could deliver balanced budgets to 2020, taking into account the Central Government funding reductions.
There has been a great deal of progress against the principle targets within the Programme and the first major phase of the office accommodation project is currently on site at Riverbank House “Bank End Building”.
This report updates Members on all aspects of the Programme and further projects associated and now incorporated within Torridge’s overall Transformational Programme.
2. REPORT
2.1Office Accommodation
The main focus of the Accommodation strand is centred on the relocation of staff from Bridge Buildings onto a single site adjacent to Riverbank House plus significant enhancement of Riverbank House to create a multi service customer facing reception hub, which will offer access to all services for customers.
In April 2016 tenders were received for this element of work on a design and build basis with the most cost advantageous price (post value engineering being £971k (split £759k for the new build and £212k for the customer hub).
At Full Council on 6th June 2016 these quotes were rejected and officers instructed to go back to the market and seek further tenders based around a traditional contract approach with the aim of seeking a better quote for the works. The results of this second tendering exercise produced contract quotes of £731k and £209k respectively providing an overall estimated cost of £940k (risk to actual cost if changes to specification or issues arise), which would represent an assumed saving of around £31k. However, additional costs of around £20k were incurred as a result of the retendering exercise for such costs as architects fees.
Main Building
Work has been progressing well on site and the building has started to take shape. However, managing traditional build contracts does pose increased risk and often results in additional costs where issues arise during the build and the Project Manager must make instructions for the continuance of work. To date the final sum of the project has been forecast at £718k representing a small saving against the original contract sum.
More recently however, the mechanical and engineering consultant awarded the work has gone into administration, which will result in additional costs being incurred in order to complete the build. A summary of the revised costs are:
Description £’000 Contract projection – May 2017 718 Additional M&E consultant costs 12 Additional costs – change specification as required by new M&E consultants 30 Costs of delay (two weeks) 7 Plus Contingency 14 Revised Contract Sum / costs 781
The overall retendered estimated cost of the project is £801k compared to £759k to the original tender exercise and a £50k increase in costs is required to complete the building project. Had the original design and build contract been awarded many of the costs since incurred would have been avoided. However, now in order to complete the works a further £50k is needed to be allocated to the project budget.
2.2Customer Hub
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.