Transforming Torridge Programme - Progress Report

Noted Committee 1 paper

Full Council noted this item on Monday 8 April 2019. Below is the council's own wording, with the papers it was decided on.

Item77

Resolved

(a) The progress made, as highlighted in the report, be noted. (b) The Bideford Skate Park amendment to the Capital Programme to £0.203m in order to reflect the total cost of the project including external grants be approved. (c) An increase of £1m in the Capital Programme be approved for the provision of homeless accommodation, with expenditure subject to approval by Community & Resources Committee of a business case(s) demonstrating a financially viable and suitable (e.g. location) scheme (d) An increase to TDCs approved borrowing of £1m to cover the additional resources required to fund the growth in the Capital Programme be approved. (e) The inclusion of a replacement integrated HR / Payroll system in the Capital Programme be approved at an estimated cost of £0.1m to be funded from the balance remaining following the procurement of ... view the full minutes text for item 77.
Word for word from the decision Torridge published for this meeting. Source: democracy.torridge.gov.uk

Follow this further

Built from Torridge's papers

What the report saysPro

Report to Full Council

Purpose of report

To provide Members with a progress report on what is the most fundamental change programme Torridge has embarked on.

1. INTRODUCTION

The original Transforming Torridge Programme (TTP) was first approved at Full Council at its meeting on 9th October 2014. A further Full Council meeting on 12th January 2015 approved the budget of £1.6m and the project strands making up the Programme approved, which were:

(a) Office Accommodation (b) Customer First – the reception hub (c) Business Innovation – also known as channel shift (d) Locality working

It was reported that the overall Programme of change would take around 2-3 years to implement on an incremental basis rather than a “big bang approach”.

There has been a great deal of progress against the principle targets within the Programme and the first major phase of the office accommodation project has been completed with staff now fully occupying the new building “Riverside”.

This report updates Members on all aspects of the Programme and further projects associated and now incorporated within Torridge’s overall Transformational Programme.

2. REPORT

2.1Programme Board

The last meeting of the Programme Board took place on Thursday 14 March 2019 and will therefore be the last report from the Board during this Council. There is one further meeting scheduled for the 11 April, which will be the final one of this Council.

2.2Progress reported

 Waste & recycling service change The Waste and Recycling Manager reported to the Programme Board (PB) the post project review (PPR), which aims to look back and evaluate how major projects are implemented, their successes and any learning points that can be used in other projects going forward.

The PB considered that the project was successful and delivered well particularly in light of such a major change programme and done so in the absence of also achieving moving the service to a single depot site.

Whilst in any major projects there are learning points to take, which with the benefit of hindsight often appear a lot more straight forward after the event. The most considerable challenge the team faced was the demand from customers for new receptacles for recycling materials and the then increase in volumes of recycling requiring collection, which whilst a good news story had a knock impact in terms of the costs of allocating additional resources. .

 Bideford Skate Park

Work has now started on site and it is projected that the works will be completed by mid May.

All funding has now been secured and received with external grants amounting to £0.078m and TDCs contribution at £0.125m providing a total of £0.203m for the project. However, TDCs current Capital Programme Budget only reflects the value of resources allocated to the project by TDC at £0.117m (£0.125m less £0.008m spent) and therefore approval is needed to amend to the total budget inclusive of external grant funding.

 Caddsdown Blue

Work has started on site, the site has been cleared and foundation / substructure works commenced. The steel frame is due for delivery mid-April with an overall completion of all works by the end of November 2019. Early access has been agreed with the contractor for the largest unit to accommodate the pre-let of this unit.

 Wilkey’s field car park, Westward Ho!

The legal issues relating to the land transfer have been finalised and the documents sent to the Land Registry for completion of the transfer. We have permission to access site under license whilst the legal transfer with the Land Registry is processed. This will allow work to get started and minimise the risk of the car park not being operational for the 2019 summer season.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Transforming Torridge Programme: Progress ReportReport 96 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

29 of 42 attended
SI
Councillor Simon InchChair, present
DM
Councillor Dermot McGeoughDeputy Chair, present
RB
Councillor Richard BoughtonCommittee Member, present
AB
Councillor Alison BoyleCommittee Member, apologies
DB
Councillor David BrentonCommittee Member, present
MB
Councillor Margaret BrownCommittee Member, present
CC
Councillor Cheryl Cottle-HunkinCommittee Member, present
AD
Councillor Anna DartCommittee Member, apologies
KD
Councillor Kenny DavisCommittee Member, present
GD
Councillor Gaston DezartCommittee Member, present
AE
Councillor Andrew EastmanCommittee Member, present
ZG
Councillor Zyg GregorekCommittee Member, present

All 42 on the meeting page

On this subject at Torridge

Search all
  1. Transforming Torridge Programme - Progress ReportThis decision
  2. Transforming Torridge Programme (standing item)Noted
  3. Transforming Torridge Programme (standing item)Noted
  4. Transforming Torridge Programme (standing item)Noted
  5. Transforming Torridge Programme - Progress ReportApproved
  6. Transforming Torridge Programme - Progress ReportApproved

More from Torridge Full Council

All decisions
MeetingDecisionOutcome
27 Jul 2026 Council MinutesThat the minutes of the meeting held on the 22 nd June 2026 be confirmed as a correct record and signed by the Chair.... Decided Open
27 Jul 2026 Written Notice of Motion from Councillor C LeatherThat the Notice of Motion be approved. (Vote: For – Unanimous). The Motion was carried. Approved Open
22 Jun 2026 Council MinutesThat the minutes of the meeting held on 27 th April 2026 be confirmed as a correct record and signed by the Chair. (V... Decided Open
22 Jun 2026 Agreement of Agenda Items Part I and IIThat the agenda as circulated be agreed. (Vote: For, Unanimous) Agreed Open
22 Jun 2026 Northam Neighbourhood PlanThat Full Council: 1. Accept the recommendations of the Examiner in relation to the Northam Neighbourhood Plan, as se... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies