That a recommendation be made to Full Council for a Capital investment of £50,000 during the 2017/2018 budget to secure external funding of £50,000. That a recommendation be made to Full Council for a Capital investment of £50,000 during the 2017/2018 budget to secure external funding of £50,000. (Vote: For – unanimous)
Word for word from the decision Torridge published for this meeting.Source: democracy.torridge.gov.uk
Agenda Item REPORT OF Commercial and Leisure Services Manager To: Community & Resources Committee
Subject: Relocation of Bideford Skate Park Date: 21.11.2017
PURPOSE OF REPORT: To request Capital investment from the 2017/18 budget to secure external funding for the first phase of the relocation and development of a Torridge destination skate park adjacent to Victoria Park.
1. INTRODUCTION
Bideford skate park comprising of a free-standing bespoke ramp and rail equipment on a tar-mac service was condemned and removed in February of this year (2017) as the site was extremely run down and not health and safety compliant. In its place at a cost to the Council, a temporary wooden half pipe was provided so that users could still have some sort of provision whilst the Authority draws up plans on how to relocate and replace it with something more permanent. The intention is to relocate the facilities away from the current site, creating a concrete “destination” facility that will service the whole community and surround within the cattle market/car park area of Bideford. There has been positive feedback regarding the temporary facility but there is clear demand for a more suitable solution likened to similar facilities in Barnstaple and Ilfracombe.
2. REPORT
Officers have secured external funding of £50,000 towards the provision of a new permanent skate facility in Torridge. There is however a stipulation to the payment of the money that it must be matched by the Authority and that the project commences prior to April 2018.
£100,000 worth of 106 developer contributions have also been secured for the development of a skate park but these will not be available until 2020/2021 at the earliest due to the development timeframe clauses within the agreement.
This report is requesting that Members commit £50,000 of capital funds in this year’s budget to secure the external contribution of £50,000 and commence the first phase of a 2 phase project in March 2018. The second phase of the project will then be completed when the 106 monies become available. In the meantime Officers will continuously seek further, additional external funding to develop the best possible facility.
The Skate Park is the first element of a strategic leisure project to establish Victoria Park and surround as a main hub for sport and leisure provision in Bideford and for the surrounding areas. Over time it is anticipated that the area will comprise of the skate park, an artificial playing pitch, additional grassed rugby pitch, additional changing facilities and other recreational and aesthetical features. The proposals for Victoria Park are based on the strategic requirements of pitch provision for Torridge over the lifespan of the local plan and a pre-app has been submitted to this effect with the necessary site surveys being undertaken accordingly.
1 The location of the skate facility has been decided upon following discussions with the Authorities property team and engineers, skate industry professionals, architects, local clubs, school, the youth sector and police. The proposals within this report form a key element of the overall strategic “Master Plan” for the area that will be utilised accordingly following the determination of this committee for full public open consultation. Numerous other locations have been considered and suggested for the skate park but following the discussions and with external factors such as other non-leisure requirements, time constraints for the external funding and strategic placement needs for pitch provision, this is the preferred, most feasible and cost effective option.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Harbour Masters Quarterly ReportIt was agreed that future reports would state the quarterly period. When asked the Director of Communities & Place ad...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.