That a Capital investment of £50,000 be made from the Capital budget to secure external funding of £50,000 that will allow the implementation of the first phase of a £200,000 skate project. That the new proposed site on the redundant waste land within the grounds of Bideford Football Club be agreed. That Officers be authorised to prepare and submit a planning application for the skate park on the identified site. (Vote: For 29, Against 1)
Word for word from the decision Torridge published for this meeting.Source: democracy.torridge.gov.uk
Agenda Item REPORT OF Commercial and Leisure Services Manager To: Full Council
Subject: Relocation of Bideford Skate Park
Date: January 2018
PURPOSE OF REPORT: To request that Members ratify the recommendations made by Community & Resources Committee of allocating £50,000 capital investment for the relocation of Bideford’s Skate Park facility and that Members agree the change of proposed location for the facility.
1. INTRODUCTION
Officers have secured external funding of £50,000 form Sport England towards the provision of a new permanent concrete skate facility in Bideford. There is however a stipulation to the payment of the money that it must be matched by the Authority and that the project commences in April 2018.
£100,000 worth of 106 developer contributions have also been secured for the development of a skate park but these will not be available until 2020/2021 at the earliest due to the development timeframe clauses within the agreement.
2. REPORT
At the Community & Resources Committee of Monday 4th December 2017, Members unanimously determined that a recommendation be made to Full Council for a Capital investment of £50,000 during the 2017/2018 budget to secure the external funding of £50,000.
The funding will allow the commencement of the first phase of a 2 phase project in April 2018. The second phase of the project will then be completed when the 106 monies become available.
The original proposed location for the Skate facility was to be adjacent to the South West Water pumping station in the Cattle Market car park, Bideford.
Unfortunately subsequent investigations identified that the majority of the budget would be utilised solely in preparing the area, demolishing the existing waste areas and working around unseen sewage works should the cattle market proposal advance.
However since the report of 4 December 2017 and following extensive consultations a more suitable, cost effective and safer location has been identified as the redundant tennis courts that sit within the Bideford Football Club grounds (APPENDIX A).
The newly proposed site is far easier to develop and would allow for a much better return for investment in terms of the provision that can be delivered. The scheme shown as (APPENDIX B) has been compiled following the consultations and a pre-app has been submitted. With members’ consent a full planning application will now be prepared for presentation at Planning Committee on 5 April for development in this location. The redundant site is currently, unofficially, utilised by the Bideford Football Club and the adjacent car wash business without the permission of the Council for car parking.
In the immediate vicinity of the sports ground there is ample parking to accommodate the parking requirements of these users and it should also be noted that when football matches are usually played (evenings, Saturday afternoon or Sunday) parking on the adjacent Pill car park is free.
3. IMPLICATIONS
Legal Implications All necessary consents will be sought.
Financial Implications A £50,000 capital investment will act as the catalyst for the provision of a £200,000 destination skate park for the District.
Human Resources Implications N/A
Sustainability/Biodiversity Implications Being constructed from concrete, the proposed facility will be built to last and therefore maintenance liabilities will be minimised. In addition, a concrete skate park with appropriate additional acoustic works as proposed in APPENDIX B will minimise noise levels and will therefore reduce possible nuisance to property owners in the vicinity.
Equality/Diversity Provision of an all access facility.
Risk Management If this proposed project does not come to fruition it is highly unlikely that a suitable skate park facility for the town and District will be provided for years to come. The site is a secure Council owned location within a King George V covenant.
Compliance with Policies and Strategies Will follow all appropriate financial, procurement and H&S procedures.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.