That the recommendations on the report be approved. A recorded vote was taken. Councillor For Against Abstention BOUGHTON, R X BRENTON, D X BRIGHT, C X BROWN, M X BUSHBY, D X CHRISTIE, P S X CLARKE, M X COTTLE-HUNKIN, C X CRAIGIE, R DART, A L X FORD, L X GUBB, J X HACKETT, P J W X HAMES, P X HARDING, S X HAWKINS, C X HEPPLE, K X HICKS, R H X HODSON, C X HURLEY, D X HUTCHINGS, J X INCH, A T X JAMES, K J X JONES, D X LANGFORD, S X LAWS, N X LEATHER, C X LOCK, R A X McGEOUGH , D A D X McKENZIE , J MANLEY, J NEWTON, S X PENNINGTON, P W X ROSSI, G WATSON, P X WISEMAN, R (Vote: For – Unanimous)
Word for word from the decision Torridge published for this meeting.Source: democracy.torridge.gov.uk
To seek member approval for the provision of a £100,000 loan to the Atlantic Racquet Centre (ARC), Bideford.
1. INTRODUCTION
Councillor Langford submitted a written notice of motion at Full Council on the 10th August 2020, requesting that a £100,000 loan be provided to the ARC. The written notice of motion was approved at full council and subsequently officers from the Council met with the trustees of the ARC and Councillor Langford to discuss the provision of a loan to the ARC.
Subsequent to the meeting ARC provided budgetary and cash flow projections up to 2026, in order to provide reassurance regarding the repayment of any loan to be provided. The financial information provided was examined by the Council’s Finance team and found to be satisfactory.
The ARC was established as a charity in April 2014 with the aim of providing an affordable and sustainable multi-sports facility for the benefit of the local community. It opened its doors to the public in 2015, with six outdoor floodlit tennis courts and a temporary clubhouse. In January 2018 an indoor sports facility was opened which provides an additional four tennis courts and three badminton courts.
The ARC has secured funding of £375,000 from the Lawn Tennis Association (LTA) £287,500 grant funding and £87,500 loan funding for phase 2 of the development: Phase 2 of the project will deliver the following
10 table tennis tables Additional badminton court 2 squash courts 2 fitness studios Gym Bar and Cafeteria Changing rooms Toilets Office Car Park
Appendix 1 provides fuller details of the current range of activities undertaken by the ARC. 2. REPORT
The projected cost of the Phase 2 development is £581k, the original funding for the project was as detailed below:
LTA Grant £287.5k LTA Loans £ 87.5k Retentions from previous grants £ 34.0k ARC Cash Balances £ 71.8k Release of Section 106 monies £100.0k The Daddon Hill Farm Development
However it has now become clear that the Section 106 monies identified may not be realised for some time, and that in order to progress this development an alternative source of funding needed to be secured.
In order for ARC to proceed with Phase 2 of the development the following loan terms are proposed for member approval.
£100,000 loan repayable over 10 years Loan repayment holiday of one year, first repayment January 2022 Interest rate linked to Public Works Loan Board 10 year annuity rate currently 1.96%
The £100k Section 106 monies is index linked, consequently should it be released at a point in the future it will negate any interest costs charged to the ARC.
Community and Resources committee on the 19th October recommended that formal approval was sought from Full Council to approve the loan of £100k to ARC as per the above terms.
3. IMPLICATIONS
Legal Implications Should Full Council decide to approve the provision of the loan a formal contract will be drawn up and signed by both parties.
Financial Implications The financial implications are detailed within the report
Human Resources Implications N/A
Sustainability Implications N/A
Equality/Diversity N/A
Risk Management N/A
Compliance with Policies and Strategies Full Council on the 28th October 2019 agreed to provide the Council with the facility to make loans of up to £250,000 subject to Community and Resources and Full Council approval. Community and Resources on the 19th October provided their approval. Leader Member Views Councillor Cottle Hunkin “ The Atlantic Racquet Centre is a valuable asset within Torridge and the completion of phase 2 will significantly increase its reach within our community. The provision of loan funding of £100k is a prudent and measured use of the Council’s resources and I support this proposal”
Recommendations
That members approve the following
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.