That a loan of £100,000 to the Atlantic Racquet Centre with the following terms be recommended to Full Council: a) a. Repayment term of 10 years with repayments commencing when the first loan has been repaid in full. b. Interest rate chargeable at PWLB 10 year annuity rate at the time of approval c. Early repayment of the loan should the Daddon Hill Section 106 monies be released. b) As the loan to ARC is classed as Capital expenditure that formal approval is given to increase the approved capital program by £100,000. (Vote: For – unanimous) That a loan of £100,000 to the Atlantic Racquet Centre with the following terms be recommended to Full Council: a) a. Repayment term of 10 years with repayments commencing when the first loan has been repaid in full. b. Interest rate chargeable at PWLB 10 year annuity rate at the time of approval c. Early repayment of the loan should the Daddon Hill Section 106 monies be released. b) As the loan to ARC is classed as Capital expenditure that formal approval is given to increase the approved capital program by £100,000. (Vote: For – unanimous)
Word for word from the decision Torridge published for this meeting.Source: democracy.torridge.gov.uk
To consider the a loan request from the Atlantic Racquets Centre for £100,000 to help them complete their facility at Caddsdown.
1. INTRODUCTION
The Atlantic Racquet Centre (ARC) was established as a charity in April 2014 with the aim of providing an affordable and sustainable multi-sports facility for the benefit of the local community. It opened its doors to the public in 2015, with six outdoor floodlit tennis courts and a temporary clubhouse. In January 2018 an indoor sports facility was opened which provides an additional 4 tennis courts and three badminton courts.
Since opening the Centre has been very successful and is a highly valued sporting and community asset.
2. REPORT
In August 2020 Councillor Langford submitted a written notice of motion at Full Council requesting that a £100,000 loan be provided to the ARC. The written notice of motion was approved at Full Council, endorsed at Community and Resources committee and the loan request was subsequently agreed by Full Council in December 2020.
At that time ARC had secured funding from the Lawn Tennis Association (LTA) and loan funding for phase 2 of the development: Phase 2 of the project will has delivered the following;
• 10 table tennis tables • Additional badminton court • 2 squash courts • 2 fitness studios • Gym • Bar and Cafeteria • Changing rooms • Toilets • Office • Car Park
ARC provided budgetary and cash flow projections up to 2026, in order to provide reassurance regarding the repayment of any loan to be provided. The financial information provided was examined by the Council’s Finance team and found to be satisfactory. In order for ARC to proceed with Phase 2 of the development the following loan terms were proposed for member approval.
• £100,000 loan repayable over 10 years • Loan repayment holiday of one year, first repayment January 2022 • Interest rate linked to Public Works Loan Board 10 year annuity rate currently 1.96%
Contained within a section 106 agreement associated with the Daddon Hill Development a contribution of £100,000 has been agreed for the Atlantic Racquets Centre. Those funds will be released on the occupation of the 151st dwelling of the development and are index linked, consequently when released at a point in the future the indexation will reduce or negate any interest costs charged to the ARC.
This loan request was approved and ARC have been repaying at a rate of £10K per annum.
Further loan request.
It was always know that a final phase of the project was in the plan for ARC. An application for £300,000 was made to the Community Regeneration Partnership process (formerly Levelling Up Partnership) but that was unsuccessful and that has meant that ARC have not been able to complete the facility and realise its full potential.
Subsequently in May 2025 the following request was received by the Council:
1st May 2025
Dear Steve
Firstly, can I thank you and Sean for your time over the last few months which has been greatly appreciated
As you know we were very disappointed to have our grant application for £300k rejected from the recent government levelling–up funding awarded to Torridge. Particularly as things had been looking very favourable for our application in the pre-general election submission stage.
Our application was made to enable us to complete phase 6 of our facilities project at ARC which is our Community Hub and Learning Space which will feature a multi-use hall and community café.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Harbour Masters Quarterly ReportIt was agreed that future reports would state the quarterly period. When asked the Director of Communities & Place ad...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.